Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
- | - | - | 29-05-14 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- December - 2017 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
- | - | - | 29-05-14 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- September - 2017 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
- | - | - | 29-05-14 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- August - 2017 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
- | - | - | 29-05-14 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- July - 2017 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- November - 2017 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- October - 2017 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 0 | 0 | 0 | 0 | 0 | 0 | 14 | - |
- June - 2018 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
One each at Abbottabad and Nowshera | |||||||||||||||||||
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- May - 2018 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
One each at Abbottabad and Nowshera | |||||||||||||||||||
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- April - 2018 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
One each at Abbottabad and Nowshera | |||||||||||||||||||
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- March - 2018 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
One each at Abbottabad and Nowshera | |||||||||||||||||||
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- February - 2018 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
One each at Abbottabad and Nowshera | |||||||||||||||||||
630 (OG) |
140012-F/S and Establishment of Home Economics Colleges (one each at Abbottabad & Nowshera). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 0 | 12 | 12 | 12 | 0 | 0 | 2 | 86% |
- January - 2018 |
LOA issued to M/S AID. PC-I/DEC under preparation. Site not H/O. |
No Image |
One each at Abbottabad and Nowshera | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 0 | 1.5 | 1.5 | 1.5 | 0.242 | 0.242 | 25.699 | 6% |
1% December - 2018 |
Soil investigation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 0 | 1.5 | 1.5 | 1.5 | 0.242 | 0.242 | 25.699 | 6% |
1% November - 2018 |
Soil investigation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 0 | 1.5 | 1.5 | 1.5 | 0.242 | 0.242 | 25.699 | 6% |
1% November - 2018 |
Soil investigation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 0 | 1.5 | 1.5 | 1.5 | 0.5 | 0.5 | 25.699 | 6% |
2% April - 2019 |
Soil investigation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 0 | 0.5 | 0.5 | 0.5 | 0.5 | 0.5 | 26.699 | 2% |
2% March - 2019 |
Soil investigation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 0 | 0.5 | 0.5 | 0.5 | 0.5 | 0.5 | 26.699 | 2% |
2% March - 2019 |
Soil investigation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 0 | 0.5 | 0.5 | 0.5 | 0.242 | 0.242 | 26.699 | 2% |
1% February - 2019 |
Soil investigation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 0 | 1.5 | 1.5 | 1.5 | 0.242 | 0.242 | 25.699 | 6% |
1% January - 2019 |
Soil investigation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 2.297 | 2 | 2 | 2 | 2 | 4.297 | 32.446 | 12% |
12% December - 2018 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 2.297 | 2 | 2 | 2 | 2 | 4.297 | 32.446 | 12% |
12% November - 2018 |
Levelling/dressing completed. Boundary wall in progress. |
No Image |
Dir Lower | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 2.297 | 2 | 2 | 2 | 2 | 4.297 | 32.446 | 12% |
12% November - 2018 |
Levelling/dressing completed. Boundary wall in progress. |
No Image |
Dir Lower | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 2.297 | 4 | 4 | 4 | 4 | 6.297 | 30.446 | 17% |
17% April - 2019 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 2.297 | 4 | 4 | 4 | 4 | 6.297 | 30.446 | 17% |
17% March - 2019 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 2.297 | 4 | 4 | 4 | 4 | 6.297 | 30.446 | 17% |
17% March - 2019 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 2.297 | 4 | 4 | 4 | 4 | 6.297 | 30.446 | 17% |
17% February - 2019 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 2.297 | 4 | 4 | 4 | 4 | 6.297 | 30.446 | 17% |
17% January - 2019 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 1.75 | 1.5 | 1.5 | 1.5 | 1.5 | 3.25 | 25.183 | 11% |
11% December - 2018 |
Main building - column completed. |
No Image |
Karak | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 1.75 | 1.5 | 1.5 | 1.5 | 1.5 | 3.25 | 25.183 | 11% |
11% November - 2018 |
DPC level. |
No Image |
Karak | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 1.75 | 1.5 | 1.5 | 1.5 | 1.5 | 3.25 | 25.183 | 11% |
11% November - 2018 |
DPC level. |
No Image |
Karak | |||||||||||||||||||
630 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 187.416 | 74.35 | 25 | 25 | 12.5 | 12.5 | 86.85 | 88.066 | 53% |
46% September - 2018 |
Length 11 Km - sub base 10 Km, WBM 4 Km completed. Rev approval accorded.
Demand for completion Rs. 100 M |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
630 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 187.416 | 74.35 | 25 | 25 | 12.5 | 12.5 | 86.85 | 88.066 | 53% |
46% July - 2018 |
Length 11 Km - sub base 10 Km, WBM 4 Km completed. Rev approval accorded. Minutes issued. AA awaited. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 1.75 | 3.5 | 3.5 | 3.5 | 3.5 | 5.25 | 23.183 | 18% |
18% April - 2019 |
Main building - column completed. |
No Image |
Karak | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 1.75 | 2.5 | 2.5 | 2.5 | 2.5 | 4.25 | 24.183 | 15% |
15% March - 2019 |
Main building - column completed. |
No Image |
Karak | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 1.75 | 2.5 | 2.5 | 2.5 | 2.5 | 4.25 | 24.183 | 15% |
15% March - 2019 |
Main building - column completed. |
No Image |
Karak | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 1.75 | 2.5 | 2.5 | 2.5 | 2.5 | 4.25 | 24.183 | 15% |
15% February - 2019 |
Main building - column completed. |
No Image |
Karak | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 1.75 | 1.5 | 1.5 | 1.5 | 1.5 | 3.25 | 25.183 | 11% |
11% January - 2019 |
Main building - column completed. |
No Image |
Karak | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- December - 2018 |
Work order issued. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- November - 2018 |
Work order issued. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- November - 2018 |
Work order issued. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- April - 2019 |
Work order issued. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- March - 2019 |
Work order issued. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- March - 2019 |
Work order issued. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- February - 2019 |
Work order issued. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- January - 2019 |
Work order issued. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.37 | 0 | 0 | 0 | 0 | 0 | 0 | 26.37 | - |
- December - 2018 |
Work started. |
No Image |
Judicial Hostel Malakand | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.37 | 0 | 0 | 0 | 0 | 0 | 0 | 26.37 | - |
- November - 2018 |
Work started. |
No Image |
Judicial Hostel Malakand | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.37 | 0 | 0 | 0 | 0 | 0 | 0 | 26.37 | - |
- November - 2018 |
Work started. |
No Image |
Judicial Hostel Malakand | |||||||||||||||||||
630 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.37 | 0 | 1 | 1 | 1 | 1 | 1 | 25.37 | 4% |
4% April - 2019 |
Work started. |
No Image |
Judicial Hostel Malakand | |||||||||||||||||||