Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
22 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 0 | 0 | 0 | 0 | 0 | 0 | 74 | - |
- September - 2018 |
Tender called on 13/09/2018. |
No Image |
Cattle Breeding Diary Farm Harichand, District Charsadda | |||||||||||||||||||
22 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 0 | 0 | 0 | 0 | 0 | 0 | 74 | - |
- July - 2018 |
Approved. |
No Image |
Cattle Breeding Diary Farm Harichand, District Charsadda | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.133 | 0 | 19.437 | 19.437 | 19.437 | 2 | 2 | 18.696 | 51% |
5% May - 2021 |
02- Units
1. Domoltion completed
2. DPC Completed |
No Image |
1. Upgradation/Renovation of Hatchery at Bumborate
2. Upgradation/Renovation of Hatchery at Jughoor
Scope of work:
| |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.133 | 0 | 2 | 2 | 2 | 2 | 2 | 36.133 | 5% |
5% April - 2021 |
02 Units
Work order issued |
No Image |
1. Upgradation/Renovation of Hatchery at Bumborate
2. Upgradation/Renovation of Hatchery at Jughoor | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.133 | 0 | 2 | 2 | 2 | 0 | 0 | 36.133 | 5% |
- March - 2021 |
02 Units
Work order issued |
No Image |
1. Upgradation/Renovation of Hatchery at Bumborate
2. Upgradation/Renovation of Hatchery at Jughoor | |||||||||||||||||||
22 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.716 | 0 | 0 | 0 | 0 | 0 | 0 | 44.716 | - |
- September - 2018 |
Tendering under process. |
No Image |
Pure Buffaloes Breeding Farm DI.Khan | |||||||||||||||||||
22 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.716 | 0 | 0 | 0 | 0 | 0 | 0 | 44.716 | - |
- July - 2018 |
Tender will be floated after removal of ban by ECP. |
No Image |
Pure Buffaloes Breeding Farm DI.Khan | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0.5 | 0 | 0 | 0 | 0 | 0.5 | 49.5 | - |
1% December - 2020 |
Revsion in progress. |
No Image |
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0.5 | 0 | 0 | 0 | 0 | 0.5 | 49.5 | - |
1% December - 2020 |
Revsion in progress. |
No Image |
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 50 | - |
- October - 2020 |
Foundation in progress. |
No Image |
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 50 | - |
- September - 2020 |
Work in progress. |
No Image |
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 50 | - |
- August - 2020 |
Work in progress. |
No Image |
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0.5 | 0 | 0 | 0 | 0 | 0.5 | 49.5 | - |
1% May - 2021 |
Foundation in progress |
No Image |
Dubari Trout Hatcheries Lower Kohistan | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0.5 | 0 | 0 | 0 | 0 | 0.5 | 49.5 | - |
1% April - 2021 |
Foundation in progress |
No Image |
Dubari Trout Hatcheries Lower Kohistan | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0.5 | 0 | 0 | 0 | 0 | 0.5 | 49.5 | - |
1% March - 2021 |
Foundation in progress |
No Image |
Dubari Trout Hatcheries Lower Kohistan | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0.5 | 0 | 0 | 0 | 0 | 0.5 | 49.5 | - |
1% February - 2021 |
Dropped |
No Image |
Dubari Trout Hatcheries Lower Kohistan | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0.5 | 0 | 0 | 0 | 0 | 0.5 | 49.5 | - |
1% January - 2021 |
Foundation in progress. |
No Image |
Dubari Trout Hatcheries Lower Kohistan | |||||||||||||||||||
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.086 | 2.629 | 9.032 | 9.032 | 9.032 | 4.373 | 7.002 | 9.425 | 55% |
33% December - 2018 |
Naran - 80% work completed. Shino - work in progress. |
No Image |
1) Naran
2) Shino | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 16 | 40 | 40 | 40 | 20 | 36 | 32.889 | 63% |
40% December - 2020 |
Work in progress. |
No Image |
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 16 | 40 | 40 | 40 | 20 | 36 | 32.889 | 63% |
40% December - 2020 |
Work in progress. |
No Image |
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.086 | 2.629 | 9.032 | 9.032 | 9.032 | 0 | 2.629 | 9.425 | 55% |
12% November - 2018 |
Naran - 80% work completed. Shino - work in progress. |
No Image |
1) Naran
2) Shino | |||||||||||||||||||
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.086 | 2.629 | 9.032 | 9.032 | 9.032 | 0 | 2.629 | 9.425 | 55% |
12% November - 2018 |
Naran - 80% work completed. Shino - work in progress. |
No Image |
1) Naran
2) Shino | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 0 | 40 | 40 | 40 | 0 | 0 | 48.889 | 45% |
- October - 2020 |
Work in progress. |
No Image |
22 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.17 | 0 | 0 | 0 | 0 | 0 | 0 | 57.17 | - |
- September - 2018 |
Tender under process. |
No Image |
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi) | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 0 | 40 | 40 | 40 | 0 | 0 | 48.889 | 45% |
- September - 2020 |
Work in progress. |
No Image |
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 0 | 0 | 0 | 0 | 0 | 0 | 88.889 | - |
- August - 2020 |
Work in progress. |
No Image |
22 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2018 |
PC-I/DCE for Rs.106.860 m submitted to Director Live Stock Jabba on 09/11/2017. |
No Image |
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi) | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 0 | 0 | 0 | 0 | 0 | 0 | 88.889 | - |
- July - 2020 |
Work in progress. |
No Image |
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 16 | 23 | 23 | 23 | 23 | 39 | 49.889 | 44% |
44% May - 2021 |
Developmental Work in Progress.
Main Building Super Structrue work in Progress.
Type IV & Type V Quarter F/P work in Progress.
Boundary Wall work in Progress.
Revised PC-I of Rs: 113.284 M send to Fisheris Derptt: KPK Peshawar. |
No Image |
Scope of work:
| |||||||||||||||||||
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.086 | 2.629 | 9.032 | 9.032 | 9.032 | 4.373 | 7.002 | 9.425 | 55% |
33% April - 2019 |
Naran - 80% work completed. Shino - work in progress. |
No Image |
1) Naran
2) Shino | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 29.218 | 40 | 40 | 40 | 23 | 52.218 | 19.671 | 78% |
59% April - 2021 |
Developmental Work in Progress.
Main Building Super Structrue work in Progress.
Type IV & Type V Quarter F/P work in Progress.
Boundary Wall work in Progress. |
No Image |
Provincial Share-PM's Agriculture Emergency Program). Manshera | |||||||||||||||||||
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.086 | 2.629 | 9.032 | 9.032 | 9.032 | 4.373 | 7.002 | 9.425 | 55% |
33% March - 2019 |
Naran - 80% work completed. Shino - work in progress. |
No Image |
1) Naran
2) Shino | |||||||||||||||||||
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.086 | 2.629 | 9.032 | 9.032 | 9.032 | 4.373 | 7.002 | 9.425 | 55% |
33% March - 2019 |
Naran - 80% work completed. Shino - work in progress. |
No Image |
1) Naran
2) Shino | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 29.218 | 40 | 40 | 40 | 23 | 52.218 | 19.671 | 78% |
59% March - 2021 |
Developmental Work in Progress.
Main Building Super Structrue work in Progress.
Type IV & Type V Quarter F/P work in Progress.
Boundary Wall work in Progress. |
No Image |
Provincial Share-PM's Agriculture Emergency Program). Manshera | |||||||||||||||||||
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.086 | 2.629 | 9.032 | 9.032 | 9.032 | 4.373 | 7.002 | 9.425 | 55% |
33% February - 2019 |
Naran - 80% work completed. Shino - work in progress. |
No Image |
1) Naran
2) Shino | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 29.218 | 40 | 40 | 40 | 23 | 52.218 | 19.671 | 78% |
59% February - 2021 |
Developmental Work in Progress.
Main Building Super Structrue work in Progress.
Type IV & Type V Quarter F/P work in Progress.
Boundary Wall work in Progress. |
No Image |
Provincial Share-PM's Agriculture Emergency Program). Manshera | |||||||||||||||||||
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.086 | 2.629 | 9.032 | 9.032 | 9.032 | 4.373 | 7.002 | 9.425 | 55% |
33% January - 2019 |
Naran - 80% work completed. Shino - work in progress. |
No Image |
1) Naran
2) Shino | |||||||||||||||||||
22 (OG) |
190102-Development of Cold Water Fisheries in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.889 | 29.218 | 40 | 40 | 40 | 13.218 | 42.436 | 19.671 | 78% |
48% January - 2021 |
Dev: work in progress, M/B S/Structure in progress, B/Wall completed |
No Image |
Provincial Share-PM's Agriculture Emergency Program). Manshera | |||||||||||||||||||
22 (OG) |
150085-Strengthening and Rehabilitation of Animal Husbandry Inservice Training Institute (AHITI), Peshawar. |
Peshawar BD-1 |
08-10-16 | 30-06-18 | - | 07-10-15 | - | 36 | 36 | 0 | 0 | 0 | 0 | 36 | 0 | - |
100% December - 2017 |
Completed. Demand Rs.5.5 m liability. |
No Image |
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
PC-I/DCE for Rs.47.498 m submitted to AD Fisheries on 21/09/2016. |
No Image |
Carp Hatchery at Sher Abad PK-07 Peshawar | |||||||||||||||||||
22 (OG) |
150085-Strengthening and Rehabilitation of Animal Husbandry Inservice Training Institute (AHITI), Peshawar. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36 | 36 | 0 | 0 | 0 | 0 | 36 | 0 | - |
100% November - 2017 |
Completed. Demand Rs.5.5 m liability. |
No Image |
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-I/DCE for Rs.47.498 m submitted to AD Fisheries on 21/09/2016. |
No Image |
Carp Hatchery at Sher Abad PK-07 Peshawar | |||||||||||||||||||
22 (OG) |
160635-Development of Farm Fisheries in Khyber Pakhtunkhwa. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-I/DCE for Rs.47.498 m submitted to AD Fisheries on 21/09/2016. |
No Image |
Carp Hatchery at Sher Abad PK-07 Peshawar | |||||||||||||||||||
22 (OG) |
150085-Strengthening and Rehabilitation of Animal Husbandry Inservice Training Institute (AHITI), Peshawar. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36 | 36 | 0 | 0 | 0 | 0 | 36 | 0 | - |
100% October - 2017 |
Completed. Demand Rs.3 m. |
No Image |
22 (OG) |
150085-Strengthening and Rehabilitation of Animal Husbandry Inservice Training Institute (AHITI), Peshawar. |
Peshawar BD-1 |
- | 30-06-18 | - | 07-10-15 | - | 36 | 36 | 0 | 0 | 0 | 0 | 36 | 0 | - |
100% September - 2017 |
Completed. Demand Rs.3 m. |
No Image |
22 (OG) |
150085-Strengthening and Rehabilitation of Animal Husbandry Inservice Training Institute (AHITI), Peshawar. |
Peshawar BD-1 |
- | 30-06-18 | - | 07-10-15 | - | 36 | 36 | 0 | 0 | 0 | 0 | 36 | 0 | - |
100% August - 2017 |
Completed. |
No Image |
22 (OG) |
150085-Strengthening and Rehabilitation of Animal Husbandry Inservice Training Institute (AHITI), Peshawar. |
Peshawar BD-1 |
- | 30-06-18 | - | 07-10-15 | - | 36 | 36 | 0 | 0 | 0 | 0 | 36 | 0 | - |
100% July - 2017 |
Completed. |
No Image |
22 (OG) |
150085-Strengthening and Rehabilitation of Animal Husbandry Inservice Training Institute (AHITI), Peshawar. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.979 | 36 | 0 | 0 | 0 | 0 | 36 | 23.979 | - |
60% June - 2018 |
Completed. |
No Image |
Shakar Pura Road Daudzai PK-09, Peshawar (construction of hostel, BW and special repair) | |||||||||||||||||||
22 (OG) |
150085-Strengthening and Rehabilitation of Animal Husbandry Inservice Training Institute (AHITI), Peshawar. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36 | 36 | 0 | 0 | 0 | 0 | 36 | 0 | - |
100% May - 2018 |
Completed.
Demand Rs.5.5 m liability. |
No Image |
Shakar Pura Road Daudzai PK-09, Peshawar (construction of hostel, BW and special repair) | |||||||||||||||||||
22 (OG) |
150085-Strengthening and Rehabilitation of Animal Husbandry Inservice Training Institute (AHITI), Peshawar. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36 | 36 | 0 | 0 | 0 | 0 | 36 | 0 | - |
100% April - 2018 |
Completed.
Demand Rs.5.5 m liability. |
No Image |
Shakar Pura Road Daudzai PK-09, Peshawar (construction of hostel, BW and special repair) | |||||||||||||||||||