Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 15.479798 | 1 | 1 | 1 | 1 | 16.479798 | 65.02 | 20% |
20% October - 2020 |
Earth work completed. Drain work in progress.
Demand Rs. 30 M |
No Image |
1) Rehabilitation of Civil Station roads (16 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 1 | 1 | 1 | 1 | 1 | 80.5 | 1% |
1% September - 2020 |
Earth work completed. Drain work in progress.
Demand Rs. 30 M |
No Image |
1) Rehabilitation of Civil Station roads (16 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 1 | 1 | 1 | 1 | 1 | 80.5 | 1% |
1% August - 2020 |
Earth work completed. Drain work in progress.
Demand Rs. 30 M |
No Image |
1) Rehabilitation of Civil Station roads (16 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 0 | 0 | 0 | 0 | 0 | 81.5 | - |
- July - 2020 |
Earth work completed. Drain work in progress. |
No Image |
1) Rehabilitation of Civil Station roads (16 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 15.479798 | 13 | 13 | 13 | 13 | 28.479798 | 53.02 | 35% |
35% March - 2021 |
22 units
Earth work completed. Drain work in progress.
Demand Rs. 30 M |
No Image |
| |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 15.479798 | 13 | 13 | 13 | 13 | 28.479798 | 53.02 | 35% |
35% February - 2021 |
22 units
Earth work completed. Drain work in progress.
Demand Rs. 30 M |
No Image |
| |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 15.479798 | 13 | 13 | 13 | 13 | 28.479798 | 53.02 | 35% |
35% January - 2021 |
22 units
Earth work completed. Drain work in progress.
Demand Rs. 30 M |
No Image |
1) Rehabilitation of Civil Station roads (16 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 15.479798 | 13 | 13 | 13 | 13 | 28.479798 | 53.02 | 35% |
35% May - 2021 |
22 units
Earth work completed. Drain work in progress.
Demand Rs. 10 M |
No Image |
| |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 15.479798 | 13 | 13 | 13 | 13 | 28.479798 | 53.02 | 35% |
35% April - 2021 |
22 units
Earth work completed. Drain work in progress.
Demand Rs. 10 M |
No Image |
| |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 1.5 | 1.5 | 1.5 | 1.5 | 1.5 | 48.5 | 3% |
3% October - 2020 |
Work in progress (3 units).
Demand Rs. 30 M |
No Image |
1) Sujbiar Kandow road (9 Km)
2 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 1.5 | 1.5 | 1.5 | 0 | 0 | 48.5 | 3% |
- September - 2020 |
Work in progress (3 units).
Demand Rs. 30 M |
No Image |
1) Sujbiar Kandow road (9 Km)
2 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 1.5 | 1.5 | 1.5 | 0 | 0 | 48.5 | 3% |
- August - 2020 |
Work in progress (3 units).
Demand Rs. 30 M |
No Image |
1) Sujbiar Kandow road (9 Km)
2 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 50 | - |
- July - 2020 |
Work in progress (3 units). |
No Image |
1) Sujbiar Kandow road (9 Km)
2 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 16.8 | 3 | 3 | 3 | 2.5 | 19.3 | 30.2 | 40% |
39% May - 2021 |
Work in progress
1 65% work completed
2 65% work completed
3 50% work completed
Demand Rs. 10 M |
No Image |
1 Sujbiar Kandow road (9 Km)
2 Battagram Shamlai Hill Road (17 KM)
3 Kuzabanda Chattarplain Road (25 KM) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 16.8 | 3 | 3 | 3 | 2.5 | 19.3 | 30.2 | 40% |
39% April - 2021 |
Work in progress
1 65% work completed
2 65% work completed
3 50% work completed
Demand Rs. 10 M |
No Image |
1 Sujbiar Kandow road (9 Km)
2 Battagram Shamlai Hill Road (17 KM)
3 Kuzabanda Chattarplain Road (25 KM) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 16.8 | 3 | 3 | 3 | 2.5 | 19.3 | 30.2 | 40% |
39% March - 2021 |
Work in progress
1 65% work completed
2 65% work completed
3 50% work completed |
No Image |
1 Sujbiar Kandow road (9 Km)
2 Battagram Shamlai Hill Road (17 KM)
3 Kuzabanda Chattarplain Road (25 KM) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 16.8 | 3 | 3 | 3 | 2.5 | 19.3 | 30.2 | 40% |
39% February - 2021 |
Work in progress
1 65% work completed
2 65% work completed
3 50% work completed |
No Image |
1 Sujbiar Kandow road (9 Km)
2 Battagram Shamlai Hill Road (17 KM)
3 Kuzabanda Chattarplain Road (25 KM) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 3 | 3 | 3 | 1 | 1 | 47 | 6% |
2% January - 2021 |
Work in progress (3 units).
Demand Rs. 30 M |
No Image |
1) Sujbiar Kandow road (9 Km)
2 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 32.588 | 1 | 1 | 1 | 1 | 33.588 | 31.922 | 51% |
51% October - 2020 |
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work. |
No Image |
Construction of RCC Bridge at Kosht (55 m), U | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 32.588 | 1 | 1 | 1 | 1 | 33.588 | 31.922 | 51% |
51% September - 2020 |
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work. |
No Image |
Construction of RCC Bridge at Kosht (55 m), U | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 32.588 | 1 | 1 | 1 | 0 | 32.588 | 31.922 | 51% |
50% August - 2020 |
RCC bridge: 24/24 piles, 2/3 pile cap, 2/3 pier sh..
Work in progress, Rs 15.00 million is required to keep continue tempo of work. |
No Image |
Construction of RCC Bridge at Kosht (55 m), U | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 0 | 0 | 0 | 0 | 0 | 0 | 65.51 | - |
- July - 2020 |
RCC bridge: 24/24 piles, 2/3 pile cap, 2/3 pier sh |
No Image |
Construction of RCC Bridge at Kosht (55 m), U | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 32.588 | 3 | 3 | 3 | 1 | 33.588 | 29.922 | 54% |
51% May - 2021 |
RCC bridge: 8/12 girders launched,
Rs 15.00 million is required to keep continue tempo of work. |
No Image |
Construction of RCC Bridge at Kosht (55 m), | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 32.588 | 3 | 3 | 3 | 1 | 33.588 | 29.922 | 54% |
51% April - 2021 |
RCC bridge: 8/12 girders launched,
Rs 15.00 million is required to keep continue tempo of work. |
No Image |
Construction of RCC Bridge at Kosht (55 m), | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 32.588 | 3 | 3 | 3 | 1 | 33.588 | 29.922 | 54% |
51% March - 2021 |
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work. |
No Image |
Construction of RCC Bridge at Kosht (55 m), | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 32.588 | 3 | 3 | 3 | 1 | 33.588 | 29.922 | 54% |
51% February - 2021 |
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work. |
No Image |
Construction of RCC Bridge at Kosht (55 m), | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 32.588 | 3 | 3 | 3 | 1 | 33.588 | 29.922 | 54% |
51% January - 2021 |
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work. |
No Image |
Construction of RCC Bridge at Kosht (55 m), U | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 1 | 1 | 1 | 1 | 1 | 113.161 | 1% |
1% October - 2020 |
Test file in progress.
Demand Rs. 50 M |
No Image |
1) Restoration/reconstruction of Shalfalam Br | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 1 | 1 | 1 | 0 | 0 | 113.161 | 1% |
- September - 2020 |
Test file in progress.
Demand Rs. 50 M |
No Image |
1) Restoration/reconstruction of Shalfalam Br | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 1 | 1 | 1 | 0 | 0 | 113.161 | 1% |
- August - 2020 |
Test file in progress.
Demand Rs. 50 M |
No Image |
1) Restoration/reconstruction of Shalfalam Br | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 0 | 0 | 0 | 0 | 0 | 114.161 | - |
- July - 2020 |
Test file in progress.
Demand Rs. 50 M |
No Image |
1) Restoration/reconstruction of Shalfalam Br | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 8.928 | 4 | 4 | 4 | 4 | 12.928 | 101.233 | 11% |
11% March - 2021 |
Test file in progress.
Demand Rs. 50 M |
No Image |
1) Restoration/reconstruction of Shalfalam Bridge on River Panjokora Dir Lower
2 Spectra Engineerig Consultant
3 Khall Kozkalay Road | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 8.928 | 4 | 4 | 4 | 4 | 12.928 | 101.233 | 11% |
11% February - 2021 |
Test file in progress.
Demand Rs. 50 M |
No Image |
1) Restoration/reconstruction of Shalfalam Bridge on River Panjokora Dir Lower
2 Spectra Engineerig Consultant
3 Khall Kozkalay Road | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 4 | 4 | 4 | 4 | 4 | 110.161 | 4% |
4% January - 2021 |
Test file in progress.
Demand Rs. 50 M |
No Image |
1) Restoration/reconstruction of Shalfalam Bridge on River Panjokora Dir Lower
2 Spectra Engineerig Consultant
3 Khall Kozkalay Road | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Lower HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 8.928 | 4 | 4 | 4 | 4 | 12.928 | 101.233 | 11% |
11% May - 2021 |
02 Units all in progress
Test file in progress.
Demand Rs. 50 M |
No Image |
1) Restoration/reconstruction of Shalfalam Bridge on River Panjokora Dir Lower
2) Khall Kozkalay Road | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Lower HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 8.928 | 4 | 4 | 4 | 4 | 12.928 | 101.233 | 11% |
11% April - 2021 |
02 Units all in progress
Test file in progress.
Demand Rs. 50 M |
No Image |
1) Restoration/reconstruction of Shalfalam Bridge on River Panjokora Dir Lower
2) Khall Kozkalay Road | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.103 | 0 | 1 | 1 | 1 | 1 | 1 | 79.103 | 1% |
1% October - 2020 |
3 units - all in progress.
Demand Rs. 20 M |
No Image |
1) Khall Kozkaly road PK-93
2) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.103 | 0 | 1 | 1 | 1 | 1 | 1 | 79.103 | 1% |
1% September - 2020 |
3 units - all in progress.
Demand Rs. 20 M |
No Image |
1) Khall Kozkaly road PK-93
2) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.103 | 0 | 1 | 1 | 1 | 0 | 0 | 79.103 | 1% |
- August - 2020 |
3 units - all in progress.
Demand Rs. 20 M |
No Image |
1) Khall Kozkaly road PK-93
2) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.103 | 0 | 0 | 0 | 0 | 0 | 0 | 80.103 | - |
- July - 2020 |
3 units - all in progress.
Demand Rs. 60 M |
No Image |
1) Khall Kozkaly road PK-93
2) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.103 | 0 | 2 | 2 | 2 | 2 | 2 | 78.103 | 2% |
2% May - 2021 |
3 units - all in progress.
Demand Rs. 20 M |
No Image |
1) Khall Kozkaly road PK-93
2) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.103 | 0 | 2 | 2 | 2 | 2 | 2 | 78.103 | 2% |
2% April - 2021 |
3 units - all in progress.
Demand Rs. 20 M |
No Image |
1) Khall Kozkaly road PK-93
2) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.103 | 0 | 2 | 2 | 2 | 2 | 2 | 78.103 | 2% |
2% March - 2021 |
3 units - all in progress.
Demand Rs. 20 M |
No Image |
1) Khall Kozkaly road PK-93
2) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.103 | 0 | 2 | 2 | 2 | 2 | 2 | 78.103 | 2% |
2% February - 2021 |
3 units - all in progress.
Demand Rs. 20 M |
No Image |
1) Khall Kozkaly road PK-93
2) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80.103 | 0 | 2 | 2 | 2 | 2 | 2 | 78.103 | 2% |
2% January - 2021 |
3 units - all in progress.
Demand Rs. 20 M |
No Image |
1) Khall Kozkaly road PK-93
2) | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 0 | 0 | 0 | 0 | 0 | 0 | 45 | - |
- October - 2020 |
Work order issued.
Over-lapping with other ADP scehme.
Revised DCE submitted for Rs. 835.357 M to SOR. |
No Image |
1) Construction & Rehabilitation of concr | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 0 | 0 | 0 | 0 | 0 | 0 | 45 | - |
- September - 2020 |
Work order issued.
Over-lapping with other ADP scehme.
Revised DCE submitted for Rs. 835.357 M to SOR |
No Image |
1) Construction & Rehabilitation of concr | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 0 | 0 | 0 | 0 | 0 | 0 | 45 | - |
- August - 2020 |
Work order issued.
Over-lapping with other ADP scehme.
Revised DCE submitted for Rs. 835.357 M to SOR |
No Image |
1) Construction & Rehabilitation of concr | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 0 | 0 | 0 | 0 | 0 | 0 | 45 | - |
- July - 2020 |
Work order issued.
Over-lapping with 1229 scope. |
No Image |
1) Construction & Rehabilitation of concr | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 30 | 0 | 0 | 0 | 0 | 30 | 15 | - |
67% May - 2021 |
Work order issued.
Over-lapping with other ADP scehme.
Revised DCE submitted for Rs. 835.357 M to SOR. |
No Image |
1. Construction & Rehabilitation of concrete Road at Dallan Main Noor Khel Road...
2. Rehab: of Dallan Mazreen Road
3. Rehab; of Dallan Lahori Banda Road.. | |||||||||||||||||||
Pages : 1 2 3 |