Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, February - 2021, February - 2018, March - 2021, March - 2018, April - 2021, April - 2018, May - 2021, May - 2018, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2020, September - 2017, October - 2020, October - 2017, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
05-05-14 30-06-18 - 27-02-14 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
December - 2017
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
05-05-14 30-06-18 - 27-02-14 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
September - 2017
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
05-05-14 30-06-18 - 27-02-14 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
August - 2017
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
05-05-14 30-06-18 - 27-02-14 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
July - 2017
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
November - 2017
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
October - 2017
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
June - 2018
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
May - 2018
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
April - 2018
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
March - 2018
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
February - 2018
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road
2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 13.097 14.5 0 0 0 0 14.5 0 - 100%
January - 2018
Completed (2 units).
No Image
1) Restoration of RW at Qalandarabad Turnawal road 2) Shifting of Asphalt Batching Plant Gohar Abad Havelian to Mangal site
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
- 30-06-18 - 18-07-17 - 16.077 0 4.5 4.5 4.5 4.5 4.5 11.577 28% 28%
December - 2017
Work in progress. Road temporary restored. Work on structure in progress.
No Image
1) Restoration of Washed away portion (610 mtr) Mastuj Broghal Pass road at Onawouch due to glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
- 30-06-18 - 18-07-17 - 16.077 0 0 0 0 0 0 16.077 - -
September - 2017
Work started.
No Image
1) Restoration of Washed away portion (610 mtr) Mastuj Broghal Pass road at Onawouch due to glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
- 30-06-18 - 18-07-17 - 16.077 0 0 0 0 0 0 16.077 - -
August - 2017
Approved in DDWP on 18/07/2017. Site not yet identified. Summary approved.
No Image
1) Restoration of Washed away portion (610 mtr) Mastuj Broghal Pass road at Onawouch due to glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
- 30-06-18 - 27-02-14 - 0 0 0 0 0 0 0 0 - -
July - 2017
Site not yet identified. Summary approved.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
30-11--1 30-11--1 - 30-11--1 - 16.077 0 0 0 0 0 0 16.077 - -
November - 2017
Work in progress.
No Image
1) Restoration of Washed away portion (610 mtr) Mastuj Broghal Pass road at Onawouch due to glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
30-11--1 30-11--1 - 30-11--1 - 16.077 0 0 0 0 0 0 16.077 - -
October - 2017
Work in progress.
No Image
1) Restoration of Washed away portion (610 mtr) Mastuj Broghal Pass road at Onawouch due to glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
30-11--1 30-11--1 - 30-11--1 - 16.077 0 4.5 4.5 4.5 4.5 4.5 11.577 28% 28%
June - 2018
90% work completed.
No Image
1) Restoration of washed away portion (610 mtr) Mastuj Broghil Pass road at Unawuch due to Glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
30-11--1 30-11--1 - 30-11--1 - 16.077 0 6.5 6.5 6.5 4.5 4.5 9.577 40% 28%
May - 2018
Work in progress. Road temporary restored. Work on structure in progress.
No Image
1) Restoration of washed away portion (610 mtr) Mastuj Broghil Pass road at Unawuch due to Glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
30-11--1 30-11--1 - 30-11--1 - 16.077 0 6.5 6.5 6.5 4.5 4.5 9.577 40% 28%
April - 2018
Work in progress. Road temporary restored. Work on structure in progress.
No Image
1) Restoration of washed away portion (610 mtr) Mastuj Broghil Pass road at Unawuch due to Glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
30-11--1 30-11--1 - 30-11--1 - 16.077 0 6.5 6.5 6.5 4.5 4.5 9.577 40% 28%
March - 2018
Work in progress. Road temporary restored. Work on structure in progress.
No Image
1) Restoration of washed away portion (610 mtr) Mastuj Broghil Pass road at Unawuch due to Glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
30-11--1 30-11--1 - 30-11--1 - 16.077 0 4.5 4.5 4.5 4.5 4.5 11.577 28% 28%
February - 2018
Work in progress. Road temporary restored. Work on structure in progress.
ADP's Images
1) Restoration of Washed away portion (610 mtr) Mastuj Broghal Pass road at Onawouch due to glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Chitral
30-11--1 30-11--1 - 30-11--1 - 16.077 0 4.5 4.5 4.5 4.5 4.5 11.577 28% 28%
January - 2018
Work in progress. Road temporary restored. Work on structure in progress.
No Image
1) Restoration of Washed away portion (610 mtr) Mastuj Broghal Pass road at Onawouch due to glacial lake outburst flood (Glof) on 26/06/2017, District Chitral
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
- 30-06-18 - 27-02-14 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
December - 2017
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
November - 2017
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
October - 2017
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
- 30-06-18 - 27-02-14 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
September - 2017
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
- 30-06-18 - 27-02-14 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
August - 2017
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
- 30-06-18 - 27-02-14 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
July - 2017
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
June - 2018
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
May - 2018
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
April - 2018
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
March - 2018
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
February - 2018
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 11.3 11.3 0 0 0 0 11.3 0 - 100%
January - 2018
Completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
28-03-17 30-06-18 - 30-01-17 - 13.39 6.5 5 5 5 5 11.5 1.89 86% 86%
December - 2017
Bridge Bashirabad Pachagaye, bridge work completed. Road work in progress.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 13.39 6.5 5 5 5 5 11.5 1.89 86% 86%
November - 2017
Bridge Bashirabad Pachagaye, bridge work completed. Road work in progress.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 13.39 6.5 5 5 5 3.908 10.408 1.89 86% 78%
October - 2017
Bridge Bashirabad Pachagaye, bridge work completed. Road work in progress.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
28-03-17 30-06-18 - 30-01-17 - 13.39 6.5 5 5 5 0.742 7.242 1.89 86% 54%
September - 2017
Bridge Bashirabad Pachagaye, bridge work completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
28-03-17 30-06-18 - 30-01-17 - 13.39 6.5 5 5 5 0 6.5 1.89 86% 49%
August - 2017
Bridge Bashirabad Pachagaye, bridge work completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
28-03-17 30-06-18 - 30-01-17 - 13.39 6.5 0 0 0 0 6.5 6.89 - 49%
July - 2017
Bridge Bashirabad Pachagaye road, bridge structure completed.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 13.39 6.5 6.446 6.446 6.446 6.445 12.945 0.444 97% 97%
June - 2018
Bridge Bashirabad Pachagaye - road completed.
No Image
Reconstruction of Canal Bridge on Pajaggi raod at Bashir Abad Peshawar
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 13.39 6.5 6.596 6.596 6.596 6.445 12.945 0.294 98% 97%
May - 2018
Bridge Bashirabad Pachagaye - road completed.
No Image
Reconstruction of Canal Bridge on Pajaggi raod at Bashir Abad Peshawar
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 13.39 6.5 6.596 6.596 6.596 6.495 12.995 0.294 98% 97%
April - 2018
Bridge Bashirabad Pachagaye, + Road - Complted.
No Image
Reconstruction of Canal Bridge on Pajaggi raod at Bashir Abad Peshawar
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 13.39 6.5 5 5 5 5 11.5 1.89 86% 86%
March - 2018
Bridge Bashirabad Pachagaye, bridge work completed. Road work in progress.
No Image
Reconstruction of Canal Bridge on Pajaggi raod at Bashir Abad Peshawar
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 13.39 6.5 5 5 5 5 11.5 1.89 86% 86%
February - 2018
Bridge Bashirabad Pachagaye, bridge work completed. Road work in progress.
No Image
Reconstruction of Canal Bridge on Pajaggi raod at Bashir Abad Peshawar
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 13.39 6.5 5 5 5 5 11.5 1.89 86% 86%
January - 2018
Bridge Bashirabad Pachagaye, bridge work completed. Road work in progress.
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Provincial
05-05-14 30-06-18 - 02-03-17 - 75 29.5 40.5 22.375 12.25 0 29.5 5 93% 39%
December - 2017
Completed (Umbrella).
No Image
1304
(OG)
130575-Emergent nature works in roads (Khyber Pakhtunkhwa).
Provincial
05-05-14 30-06-18 - 02-03-17 - 75 29.5 40.5 40.5 0 0 29.5 5 93% 39%
September - 2017
Completed (Umbrella).
No Image
Pages : 1 2