Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 4.94 | 4.94 | 4.94 | 0 | 0 | 276.446 | 2% |
- October - 2020 |
2 block GF roof laid. Ist Floor S/S in progress.
OHT S/S in progress. |
No Image |
Construction of Residenctial requirments for | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 4.94 | 4.94 | 4.94 | 0 | 0 | 276.446 | 2% |
- September - 2020 |
2 block GF roof laid. Ist Floor S/S in progress.
OHT S/S in progress. |
No Image |
Construction of Residenctial requirments for | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 0 | 0 | 0 | 0 | 0 | 281.386 | - |
- August - 2020 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 0 | 0 | 0 | 0 | 0 | 281.386 | - |
- July - 2020 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 44.783 | 23.94 | 41.94 | 41.94 | 28.799 | 73.582 | 212.663 | 24% |
26% May - 2021 |
01- Unit
1st floor roof laid.
S/structure in progress |
No Image |
Construction of Residences for Ditrict Judicairy Abbottabad.
Scope of work:
| |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 44.783 | 23.94 | 41.94 | 41.94 | 23.94 | 68.723 | 212.663 | 24% |
24% April - 2021 |
1. 1st floor roof laid.
2. S/structure in progress |
No Image |
Construction of Residences for Ditrict Judicairy Abbottabad. | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 44.783 | 23.94 | 23.94 | 23.94 | 22.14 | 66.923 | 212.663 | 24% |
24% March - 2021 |
1. 1st floor roof laid.
2. S/structure in progress |
No Image |
Construction of Residenctial requirments for | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 44.783 | 23.94 | 23.94 | 23.94 | 22.14 | 66.923 | 212.663 | 24% |
24% February - 2021 |
1. 1st floor roof laid.
2. S/structure in progress |
No Image |
Construction of Residenctial requirments for | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 44.783 | 20.94 | 20.94 | 20.94 | 19.635 | 64.418 | 215.663 | 23% |
23% January - 2021 |
2 block GF roof laid. Ist Floor S/S in progress.
OHT S/S in progress. |
No Image |
Construction of Residenctial requirments for | |||||||||||||||||||
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
- | - | - | 11-02-15 | - | 130 | 5.142 | 5.325 | 10.163 | 0 | 0 | 5.142 | 119.533 | 8% |
4% December - 2017 |
RCC bridge in progress, 2 Km road work restarted. Revised DCE submitted to P&D. Pre-PDWP held. |
No Image |
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
- | - | - | 11-02-15 | - | 130 | 5.142 | 5.325 | 5.325 | 5.325 | 0 | 5.142 | 119.533 | 8% |
4% September - 2017 |
RCC bridge in progress, 2 Km road work restarted. |
No Image |
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
- | - | - | 11-02-15 | - | 130 | 5.142 | 5.325 | 5.325 | 5.325 | 0 | 5.142 | 119.533 | 8% |
4% August - 2017 |
RCC bridge in progress, 2 Km road work restarted. |
No Image |
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
- | - | - | 11-02-15 | - | 130 | 5.142 | 5.325 | 5.325 | 5.325 | 0 | 5.142 | 119.533 | 8% |
4% July - 2017 |
RCC bridge in progress, 2 Km road work restarted. |
No Image |
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 5.142 | 5.325 | 10.163 | 0 | 0 | 5.142 | 119.533 | 8% |
4% November - 2017 |
RCC bridge in progress, 2 Km road work restarted. Revised DCE submitted to P&D . Pre PDWP held. |
No Image |
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 5.142 | 5.325 | 5.325 | 5.325 | 0 | 5.142 | 119.533 | 8% |
4% October - 2017 |
RCC bridge in progress, 2 Km road work restarted. Revised DCE submitted to SOR. |
No Image |
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 115.656 | 31.698 | 15 | 3.29 | 3.29 | 3.29 | 34.988 | 68.958 | 40% |
30% June - 2018 |
RCC bridge (1 span) in progress, 2 Km road work in progress |
No Image |
Garam Chashma Kandujal road i/c 2 brides
(2 Km Shingle Roads
RCC Bridge - 2 Nos
Land Acquisition) | |||||||||||||||||||
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 115.656 | 31.698 | 15 | 15 | 3.75 | 0 | 31.698 | 68.958 | 40% |
27% May - 2018 |
RCC bridge (1 span) in progress, 2 Km road work in progress |
No Image |
Garam Chashma Kandujal road i/c 2 brides
(2 Km Shingle Roads
RCC Bridge - 2 Nos
Land Acquisition) | |||||||||||||||||||
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 115.656 | 31.698 | 15 | 15 | 7.5 | 0 | 31.698 | 68.958 | 40% |
27% April - 2018 |
RCC bridge (1 span) in progress, 2 Km road work in progress (snowbound). |
No Image |
Garam Chashma Kandujal road i/c 2 brides
(2 Km Shingle Roads
RCC Bridge - 2 Nos
Land Acquisition) | |||||||||||||||||||
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 115.656 | 31.698 | 5.325 | 10.163 | 5.235 | 0 | 31.698 | 78.633 | 32% |
27% March - 2018 |
RCC bridge (1 span) in progress, 2 Km road work in progress (snowbound). |
No Image |
Garam Chashma Kandujal road i/c 2 brides
(2 Km Shingle Roads
RCC Bridge - 2 Nos
Land Acquisition) | |||||||||||||||||||
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 115.656 | 5.142 | 5.325 | 10.163 | 5.235 | 0 | 5.142 | 105.189 | 9% |
4% February - 2018 |
RCC bridge (1 span ) in progress,
2 Km road work in progress (snowbound) |
ADP's Images |
Garam Chashma Kandujal road i/c 2 brides | |||||||||||||||||||
1160 (OG) |
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 5.142 | 5.325 | 10.163 | 0 | 0 | 5.142 | 119.533 | 8% |
4% January - 2018 |
RCC bridge in progress, 2 Km road work restarted. Revised DCE submitted to P&D. Pre-PDWP held. |
No Image |
Chitral | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0 | 4.95 | 4.95 | 4.95 | 0 | 0 | 98.332 | 5% |
- October - 2020 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers i | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0 | 4.95 | 4.95 | 4.95 | 0 | 0 | 98.332 | 5% |
- September - 2020 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers i | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0 | 0 | 0 | 0 | 0 | 0 | 103.282 | - |
- August - 2020 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers i | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0 | 0 | 0 | 0 | 0 | 0 | 103.282 | - |
- July - 2020 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers i | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 20.925 | 26.95 | 26.95 | 26.95 | 6.117 | 27.042 | 55.407 | 46% |
26% May - 2021 |
01- Unit
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers
Scope of work:
| |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 20.925 | 26.95 | 26.95 | 26.95 | 6.117 | 27.042 | 55.407 | 46% |
26% April - 2021 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers i | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 20.925 | 26.95 | 26.95 | 26.95 | 5.559 | 26.484 | 55.407 | 46% |
26% March - 2021 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers i | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 20.925 | 6.95 | 6.95 | 6.95 | 4.95 | 25.875 | 75.407 | 27% |
25% February - 2021 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers i | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 20.925 | 26.95 | 26.95 | 26.95 | 4.95 | 25.875 | 55.407 | 46% |
25% January - 2021 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers i | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 4 | 4 | 4 | 4 | 4 | 445.286 | 1% |
1% October - 2020 |
Residences - complted
lodges - Finsihing in progres.
Type 4 quarter - Site not yet handed over |
No Image |
Construction of Tehsil Judicial Complex Parov | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 4 | 4 | 4 | 0 | 0 | 445.286 | 1% |
- September - 2020 |
Residences - complted
lodges - Finsihing in progres.
Type 4 quarter - Site not yet handed over |
No Image |
Construction of Tehsil Judicial Complex Parov | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- July - 2020 |
Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parov | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- May - 2021 |
Residences - complted
lodges - Finsihing in progres.
Type 4 quarter - Site not yet handed over |
No Image |
Construction of Tehsil Judicial Complex Parov | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- April - 2021 |
Residences - complted
lodges - Finsihing in progres.
Type 4 quarter - Site not yet handed over |
No Image |
Construction of Tehsil Judicial Complex Parov | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 4 | 4 | 4 | 4 | 4 | 445.286 | 1% |
1% March - 2021 |
Residences - complted
lodges - Finsihing in progres.
Type 4 quarter - Site not yet handed over |
No Image |
Construction of Tehsil Judicial Complex Parov | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 4 | 4 | 4 | 4 | 4 | 445.286 | 1% |
1% February - 2021 |
Residences - complted
lodges - Finsihing in progres.
Type 4 quarter - Site not yet handed over |
No Image |
Construction of Tehsil Judicial Complex Parov | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 4 | 4 | 4 | 4 | 4 | 445.286 | 1% |
1% January - 2021 |
Residences - complted
lodges - Finsihing in progres.
Type 4 quarter - Site not yet handed over |
No Image |
Construction of Tehsil Judicial Complex Parov | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
DI.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- August - 2020 |
Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parov | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 0 | 4.94 | 4.94 | 4.94 | 0.722 | 0.722 | 89.164 | 5% |
1% October - 2020 |
4- Units
2 - Finishing in progress.
2- work in progress.
Deamnd Rs. 30 M |
No Image |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 0 | 4.94 | 4.94 | 4.94 | 0.722 | 0.722 | 89.164 | 5% |
1% September - 2020 |
4- Units
2 - Finishing in progress.
2- work in progress.
Deamnd Rs. 30 M |
No Image |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 0 | 0 | 0 | 0 | 0 | 0 | 94.104 | - |
- August - 2020 |
4- Units
2 - Finishing in progress.
2- work in progress. |
No Image |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 0 | 0 | 0 | 0 | 0 | 0 | 94.104 | - |
- July - 2020 |
4- Units
2 - Finishing in progress.
2- work in progress. |
No Image |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 31.373 | 51.607 | 51.607 | 51.607 | 27.31 | 58.683 | 11.124 | 88% |
62% May - 2021 |
4- Units
2 - Finishing in progress.
2- work in progress. |
No Image |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 31.373 | 51.607 | 51.607 | 51.607 | 27.31 | 58.683 | 11.124 | 88% |
62% April - 2021 |
4- Units
2 - Finishing in progress.
2- work in progress. |
No Image |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 31.373 | 1.94 | 1.94 | 1.94 | 0.722 | 32.095 | 60.791 | 35% |
34% March - 2021 |
4- Units
2 - Finishing in progress.
2- work in progress.
Deamnd Rs. 30 M |
No Image |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 31.373 | 1.94 | 1.94 | 1.94 | 0.722 | 32.095 | 60.791 | 35% |
34% February - 2021 |
4- Units
2 - Finishing in progress.
2- work in progress.
Deamnd Rs. 30 M |
No Image |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 31.373 | 1.94 | 1.94 | 1.94 | 0.722 | 32.095 | 60.791 | 35% |
34% January - 2021 |
4- Units
2 - Finishing in progress.
2- work in progress.
Deamnd Rs. 30 M |
No Image |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Peshawar MPD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 3.632 | 0 | 0 | 0 | 0 | 3.632 | 0 | - |
May - 2021 |
No Image | |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
1160 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Peshawar MPD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 3.632 | 0 | 0 | 0 | 0 | 3.632 | 0 | - |
April - 2021 |
No Image | |
Residences and allied facilities for Judicial Offi | |||||||||||||||||||
Pages : 1 2 3 |