Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
- | - | - | 31-08-16 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% December - 2017 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% November - 2017 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% October - 2017 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
- | - | - | 31-08-16 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% September - 2017 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
- | - | - | 31-08-16 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% August - 2017 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
- | - | - | 31-08-16 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% July - 2017 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 2.239 | 2.239 | 2.239 | 5.016 | 7.2 | 64% |
25% June - 2018 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
Peshawar | |||||||||||||||||||
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 2.239 | 5.016 | 7.2 | 64% |
25% May - 2018 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
Peshawar | |||||||||||||||||||
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 2.239 | 5.016 | 7.2 | 64% |
25% April - 2018 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
Peshawar | |||||||||||||||||||
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 2.239 | 5.016 | 7.2 | 64% |
25% March - 2018 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
Peshawar | |||||||||||||||||||
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% February - 2018 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
Peshawar | |||||||||||||||||||
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% January - 2018 |
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress. |
No Image |
Peshawar | |||||||||||||||||||
108 (OG) |
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.5 | 0 | 41.5 | 46.5 | 20.75 | 0 | 0 | 10 | 81% |
- December - 2018 |
Work order issued. Site is not H/O. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
170549-Design of Chief Minister's Office and Conference Hall/Interior Decoration on main Block (First Floor) at Khyber Pakhtunkhwa House Islamabad |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.09 | 0 | 5 | 3.75 | 3.75 | 0 | 0 | 15.09 | 25% |
- December - 2019 |
Site not yet H/O. Tender approved. Non-clearance of site. Technical Evaluation is under process.
Deffered in PDWP on 18-11-2019. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.5 | 0 | 41.5 | 46.5 | 20.75 | 0 | 0 | 10 | 81% |
- November - 2018 |
Work order issued. Site is not H/O. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.5 | 0 | 41.5 | 46.5 | 20.75 | 0 | 0 | 10 | 81% |
- November - 2018 |
Work order issued. Site is not H/O. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
170549-Design of Chief Minister's Office and Conference Hall/Interior Decoration on main Block (First Floor) at Khyber Pakhtunkhwa House Islamabad |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.09 | 0 | 5 | 3.75 | 0 | 0 | 0 | 15.09 | 25% |
- November - 2019 |
Site not yet H/O. Tender approved. Non-clearance of site. Technical Evaluation is under process.
Deffered in PDWP on 18-11-2019. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
170549-Design of Chief Minister's Office and Conference Hall/Interior Decoration on main Block (First Floor) at Khyber Pakhtunkhwa House Islamabad |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.09 | 0 | 5 | 5 | 1.25 | 0 | 0 | 15.09 | 25% |
- October - 2019 |
Site not yet H/O. Tender approved. Non-clearance of site. Technical Evaluation is under process. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
170549-Design of Chief Minister's Office and Conference Hall/Interior Decoration on main Block (First Floor) at Khyber Pakhtunkhwa House Islamabad |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.09 | 0 | 5 | 5 | 1.25 | 0 | 0 | 15.09 | 25% |
- September - 2019 |
Site not yet H/O. Tender approved. Non-clearance of site. Technical Evaluation is under process. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
170549-Design of Chief Minister's Office and Conference Hall/Interior Decoration on main Block (First Floor) at Khyber Pakhtunkhwa House Islamabad |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.09 | 0 | 5 | 3.75 | 3.75 | 0 | 0 | 15.09 | 25% |
- May - 2020 |
Site not yet H/O. Tender approved. Non-clearance of site. Technical Evaluation is under process.
Deffered in PDWP on 18-11-2019. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.5 | 0 | 41.5 | 25.75 | 0 | 0 | 0 | 10 | 81% |
- April - 2019 |
Work order issued. Site is not H/O. Proposed for dropping from ADP. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
170549-Design of Chief Minister's Office and Conference Hall/Interior Decoration on main Block (First Floor) at Khyber Pakhtunkhwa House Islamabad |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.09 | 0 | 5 | 3.75 | 0 | 0 | 0 | 15.09 | 25% |
- April - 2020 |
Site not yet H/O. Tender approved. Non-clearance of site. Technical Evaluation is under process.
Deffered in PDWP on 18-11-2019. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.5 | 0 | 41.5 | 25.75 | 25.75 | 0 | 0 | 10 | 81% |
- March - 2019 |
Work order issued. Site is not H/O. Proposed for dropping from ADP. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.5 | 0 | 41.5 | 25.75 | 25.75 | 0 | 0 | 10 | 81% |
- March - 2019 |
Work order issued. Site is not H/O. Proposed for dropping from ADP. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
170549-Design of Chief Minister's Office and Conference Hall/Interior Decoration on main Block (First Floor) at Khyber Pakhtunkhwa House Islamabad |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.09 | 0 | 5 | 3.75 | 0 | 0 | 0 | 15.09 | 25% |
- March - 2020 |
Site not yet H/O. Tender approved. Non-clearance of site. Technical Evaluation is under process.
Deffered in PDWP on 18-11-2019. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.5 | 0 | 41.5 | 25.75 | 25.75 | 0 | 0 | 10 | 81% |
- February - 2019 |
Work order issued. Site is not H/O. Proposed for dropping from ADP. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
170549-Design of Chief Minister's Office and Conference Hall/Interior Decoration on main Block (First Floor) at Khyber Pakhtunkhwa House Islamabad |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.09 | 0 | 5 | 3.75 | 0 | 0 | 0 | 15.09 | 25% |
- February - 2020 |
Site not yet H/O. Tender approved. Non-clearance of site. Technical Evaluation is under process.
Deffered in PDWP on 18-11-2019. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.5 | 0 | 41.5 | 46.5 | 0 | 0 | 0 | 10 | 81% |
- January - 2019 |
Work order issued. Site is not H/O.
Proposed for Dropping from ADP. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
170549-Design of Chief Minister's Office and Conference Hall/Interior Decoration on main Block (First Floor) at Khyber Pakhtunkhwa House Islamabad |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.09 | 0 | 5 | 3.75 | 3.75 | 0 | 0 | 15.09 | 25% |
- January - 2020 |
Site not yet H/O. Tender approved. Non-clearance of site. Technical Evaluation is under process.
Deffered in PDWP on 18-11-2019. |
No Image |
Islamabad | |||||||||||||||||||
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
- December - 2020 |
No Image | |
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
- December - 2020 |
No Image | |
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
- October - 2020 |
No Image | |
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
- September - 2020 |
No Image | |
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
- August - 2020 |
No Image | |
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
July - 2020 |
No Image | |
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
- May - 2021 |
No Image | |
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
- April - 2021 |
No Image | |
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
- March - 2021 |
No Image | |
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
- February - 2021 |
No Image | |
108 (OG) |
191096-180543 - Control of Zoonotic / Contagious Diseases through existing Vety: Health Facilities & Establishment of Two Mobile Milk Testing Labs on Pilot Basis in Tribal Districts. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.8 | 43.517 | 0 | 0 | 0 | 0 | 43.517 | 0 | - |
- January - 2021 |
No Image | |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Provincial BD-1 |
- | - | - | 31-08-16 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% December - 2017 |
Approved for Rs.19.977 m in DDWP on 31/08/2016. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Provincial BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% November - 2017 |
Approved for Rs.19.977 m in DDWP on 31/08/2016. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Provincial BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% October - 2017 |
Approved for Rs.19.977 m in DDWP on 31/08/2016. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Provincial BD-1 |
- | - | - | 31-08-16 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% September - 2017 |
Approved for Rs.19.977 m in DDWP on 31/08/2016. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Provincial BD-1 |
- | - | - | 31-08-16 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% August - 2017 |
Approved for Rs.19.977 m in DDWP on 31/08/2016. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Provincial BD-1 |
- | - | - | 31-08-16 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% July - 2017 |
Approved for Rs.19.977 m in DDWP on 31/08/2016. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Provincial BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% June - 2018 |
Approved for Rs.19.977 m in DDWP on 31/08/2016. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Provincial BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% May - 2018 |
Approved for Rs.19.977 m in DDWP on 31/08/2016. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Provincial BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% April - 2018 |
Approved for Rs.19.977 m in DDWP on 31/08/2016. |
No Image |
108 (OG) |
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK. |
Provincial BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.977 | 2.777 | 10 | 10 | 4.5 | 0 | 2.777 | 7.2 | 64% |
14% March - 2018 |
Approved for Rs.19.977 m in DDWP on 31/08/2016. |
No Image |
Pages : 1 2 |