Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2019, February - 2020, February - 2021, February - 2018, March - 2019, March - 2020, March - 2021, March - 2018, April - 2019, April - 2020, April - 2021, April - 2018, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
14-02-16 - - 17-11-15 - 35.961 25.697 7 7 7 6.609 32.306 3.264 91% 90%
December - 2017
Main building, staff building, guard room - finishing in progress.
No Image
Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
14-02-16 - - 17-11-15 - 35.961 25.697 0 0 0 0 25.697 10.264 - 71%
September - 2017
Main building - roof laid. Staff building - finishing in progress. BW in progress. Balance funds demanded.
No Image
Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
14-02-16 - - 17-11-15 - 35.961 25.697 0 0 0 0 25.697 10.264 - 71%
August - 2017
Main building - roof laid. Staff building - roof laid. BW in progress.
No Image
Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
14-02-16 - - 17-11-15 - 35.961 25.697 0 0 0 0 25.697 10.264 - 71%
July - 2017
Main building - roof laid. Staff building - roof laid. BW in progress.
No Image
Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
30-11--1 30-11--1 - 30-11--1 - 35.961 25.697 7 7 7 4.405 30.102 3.264 91% 84%
November - 2017
Main building, staff building, guard room - finishing in progress.
No Image
Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
30-11--1 30-11--1 - 30-11--1 - 35.961 25.697 7 7 7 0 25.697 3.264 91% 71%
October - 2017
Main building - roof laid. Staff building - finishing in progress. BW in progress.
No Image
Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
30-11--1 30-11--1 - 30-11--1 - 35.961 25.697 15.6 15.634 15.634 5.996 31.693 0 100% 88%
June - 2018
Main building, staff building, guard room - finishing in progress.
No Image
Construction of Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
30-11--1 30-11--1 - 30-11--1 - 35.961 25.697 15.6 15.6 15.6 7 32.697 0 100% 91%
May - 2018
Main building, staff building, guard room - finishing in progress.
No Image
Construction of Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
30-11--1 30-11--1 - 30-11--1 - 35.961 25.697 7 7 7 7 32.697 3.264 91% 91%
April - 2018
Main building, staff building, guard room - finishing in progress.
No Image
Construction of Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
30-11--1 30-11--1 - 30-11--1 - 35.961 25.697 7 7 7 7 32.697 3.264 91% 91%
March - 2018
Main building, staff building, guard room - finishing in progress.
No Image
Construction of Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
30-11--1 30-11--1 - 30-11--1 - 35.961 25.697 7 7 7 6.699 32.396 3.264 91% 90%
February - 2018
Main building, staff building, guard room - finishing in progress.
ADP's Images
Construction of Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Battagram
30-11--1 30-11--1 - 30-11--1 - 35.961 25.697 7 7 7 6.609 32.306 3.264 91% 90%
January - 2018
Main building, staff building, guard room - finishing in progress.
No Image
Regional office of ACE at Phagora Battagram
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
- - - 17-11-15 - 31.685 0 0 0 0 0 0 31.685 - -
December - 2017
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
- - - 17-11-15 - 31.685 0 0 0 0 0 0 31.685 - -
September - 2017
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
- - - 17-11-15 - 31.685 0 0 0 0 0 0 31.685 - -
August - 2017
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
- - - 17-11-15 - 31.685 0 0 0 0 0 0 31.685 - -
July - 2017
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.685 0 0 0 0 0 0 31.685 - -
November - 2017
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.685 0 0 0 0 0 0 31.685 - -
October - 2017
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.685 0 0 0 0 0 0 31.685 - -
June - 2018
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.685 0 0 0 0 0 0 31.685 - -
May - 2018
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.685 0 0 0 0 0 0 31.685 - -
April - 2018
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.685 0 0 0 0 0 0 31.685 - -
March - 2018
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.685 0 0 0 0 0 0 31.685 - -
February - 2018
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.685 0 0 0 0 0 0 31.685 - -
January - 2018
Work order issued on 29/01/2016 but site not available.
No Image
DI.Khan
107
(OG)
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 19.977 5.016 12.7 12.7 6.35 0 5.016 2.261 89% 25%
December - 2018
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress.
No Image
Peshawar
107
(OG)
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 19.977 5.016 12.7 12.7 6.35 0 5.016 2.261 89% 25%
November - 2018
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress.
No Image
Peshawar
107
(OG)
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 19.977 5.016 12.7 12.7 6.35 0 5.016 2.261 89% 25%
November - 2018
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress.
No Image
Peshawar
107
(OG)
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 19.977 5.016 12.7 8.85 2.5 2.5 7.516 2.261 89% 38%
April - 2019
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress.
No Image
Peshawar
107
(OG)
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 19.977 5.016 12.7 8.85 2.5 0 5.016 2.261 89% 25%
March - 2019
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress.
No Image
Peshawar
107
(OG)
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 19.977 5.016 12.7 8.85 2.5 0 5.016 2.261 89% 25%
March - 2019
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress.
No Image
Peshawar
107
(OG)
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 19.977 5.016 12.7 8.85 8.85 0 5.016 2.261 89% 25%
February - 2019
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress.
No Image
Peshawar
107
(OG)
160530-Provision for Design of Structural / Plumbing / Elect / Air Conditioning various Buildings in KPK.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 19.977 5.016 12.7 12.7 2.5 0 5.016 2.261 89% 25%
January - 2019
Structure design of GDC (boys/girls). Primary and seconadry schools, BHU, RHCs, Zone 2B (0.75 bearing capacity) completed. Plumbing design in progress.
No Image
Peshawar
107
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 5 3.75 3.75 0 0 46.5 10% -
December - 2019
Work order issued. Site is not H/O. Proposed for dropping from ADP. Revised DCE re-Submitted. Deffered in PDWP on 18-11-2019.
No Image
Islamabad
107
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 5 3.75 0 0 0 46.5 10% -
November - 2019
Work order issued. Site is not H/O. Proposed for dropping from ADP. Revised DCE re-Submitted. Deffered in PDWP on 18-11-2019.
No Image
Islamabad
107
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 5 5 1.25 0 0 46.5 10% -
October - 2019
Work order issued. Site is not H/O. Proposed for dropping from ADP. Revised Dce re-Submitted.
No Image
Islamabad
107
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 5 5 1.25 0 0 46.5 10% -
September - 2019
Work order issued. Site is not H/O. Proposed for dropping from ADP. Revised Dce re-Submitted.
No Image
Islamabad
107
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 5 1.25 0 0 0 46.5 10% -
May - 2020
Work order issued. Site is not H/O. Proposed for dropping from ADP. Revised DCE re-Submitted. Deffered in PDWP on 18-11-2019.
No Image
Islamabad
107
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 5 1.25 0 0 0 46.5 10% -
April - 2020
Work order issued. Site is not H/O. Proposed for dropping from ADP. Revised DCE re-Submitted. Deffered in PDWP on 18-11-2019.
No Image
Islamabad
107
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 5 1.25 0 0 0 46.5 10% -
March - 2020
Work order issued. Site is not H/O. Proposed for dropping from ADP. Revised DCE re-Submitted. Deffered in PDWP on 18-11-2019.
No Image
Islamabad
107
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 5 1.25 0 0 0 46.5 10% -
February - 2020
Work order issued. Site is not H/O. Proposed for dropping from ADP. Revised DCE re-Submitted. Deffered in PDWP on 18-11-2019.
No Image
Islamabad
107
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 5 1.25 0 0 0 46.5 10% -
January - 2020
Work order issued. Site is not H/O. Proposed for dropping from ADP. Revised DCE re-Submitted. Deffered in PDWP on 18-11-2019.
No Image
Islamabad
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Provincial
- - - 17-11-15 - 100 25.697 33.837 33.837 0 0 25.697 40.466 60% 26%
December - 2017
Work in progress.
No Image
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Provincial
- - - 17-11-15 - 100 25.697 33.837 33.837 0 0 25.697 40.466 60% 26%
September - 2017
Work in progress.
No Image
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Provincial
- - - 17-11-15 - 100 25.697 33.837 33.837 0 0 25.697 40.466 60% 26%
August - 2017
Work in progress.
No Image
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Provincial
- - - 17-11-15 - 100 25.697 33.837 33.837 0 0 25.697 40.466 60% 26%
July - 2017
Work in progress.
No Image
107
(OG)
191088-170353-Uplifting the Scio-Economic Condition & Gender Mainstreaming of Livestock Farmers Through PPP in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 130.665 108.577 0 0 0 0 108.577 0 - -
December - 2020
No Image
107
(OG)
191088-170353-Uplifting the Scio-Economic Condition & Gender Mainstreaming of Livestock Farmers Through PPP in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 130.665 108.577 0 0 0 0 108.577 0 - -
December - 2020
No Image
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 25.697 33.837 33.837 0 0 25.697 40.466 60% 26%
November - 2017
Work in progress.
No Image
107
(OG)
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 25.697 33.837 33.837 0 0 25.697 40.466 60% 26%
October - 2017
Work in progress.
No Image
107
(OG)
191088-170353-Uplifting the Scio-Economic Condition & Gender Mainstreaming of Livestock Farmers Through PPP in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 130.665 108.577 0 0 0 0 108.577 0 - -
October - 2020
No Image