Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 31.693 | 5 | 5 | 5 | 3.366 | 35.059 | 0 | 100% |
97% December - 2018 |
Main building, staff building, guard room - finishing in progress. |
No Image |
Construction of Regional office of ACE at Phagora Battagram | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 31.693 | 5 | 5 | 5 | 3.416 | 35.109 | 0 | 100% |
98% November - 2018 |
Main building, staff building, guard room - finishing in progress. |
No Image |
Construction of Regional office of ACE at Phagora Battagram | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 31.693 | 5 | 5 | 5 | 3.416 | 35.109 | 0 | 100% |
98% November - 2018 |
Main building, staff building, guard room - finishing in progress. |
No Image |
Construction of Regional office of ACE at Phagora Battagram | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 31.6927 | 9.6 | 9.6 | 9.6 | 4.701 | 36.3937 | 0 | 100% |
100% April - 2019 |
Main building, staff building, guard room - finishing in progress. |
No Image |
Construction of Regional office of ACE at Phagora Battagram | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 31.6927 | 9.6 | 9.6 | 9.6 | 4.701 | 36.3937 | 0 | 100% |
100% March - 2019 |
Main building, staff building, guard room - finishing in progress. |
No Image |
Construction of Regional office of ACE at Phagora Battagram | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 31.6927 | 9.6 | 9.6 | 9.6 | 4.701 | 36.3937 | 0 | 100% |
100% March - 2019 |
Main building, staff building, guard room - finishing in progress. |
No Image |
Construction of Regional office of ACE at Phagora Battagram | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 31.6927 | 9.6 | 9.6 | 9.6 | 4.198 | 35.8907 | 0 | 100% |
100% February - 2019 |
Main building, staff building, guard room - finishing in progress. |
No Image |
Construction of Regional office of ACE at Phagora Battagram | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 31.6927 | 9.6 | 9.6 | 9.6 | 3.366 | 35.0587 | 0 | 100% |
97% January - 2019 |
Main building, staff building, guard room - finishing in progress. |
No Image |
Construction of Regional office of ACE at Phagora Battagram | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.685 | 0 | 0 | 0 | 0 | 0 | 0 | 31.685 | - |
- December - 2018 |
Work order issued on 29/01/2016 but site not available. |
No Image |
DI.Khan | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.685 | 0 | 0 | 0 | 0 | 0 | 0 | 31.685 | - |
- November - 2018 |
Work order issued on 29/01/2016 but site not available. |
No Image |
DI.Khan | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.685 | 0 | 0 | 0 | 0 | 0 | 0 | 31.685 | - |
- November - 2018 |
Work order issued on 29/01/2016 but site not available. |
No Image |
DI.Khan | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.685 | 0 | 0 | 0 | 0 | 0 | 0 | 31.685 | - |
- April - 2019 |
Work order issued on 29/01/2016 but site not available. |
No Image |
DI.Khan | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.685 | 0 | 0 | 0 | 0 | 0 | 0 | 31.685 | - |
- March - 2019 |
Work order issued on 29/01/2016 but site not available. |
No Image |
DI.Khan | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.685 | 0 | 0 | 0 | 0 | 0 | 0 | 31.685 | - |
- March - 2019 |
Work order issued on 29/01/2016 but site not available. |
No Image |
DI.Khan | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.685 | 0 | 0 | 0 | 0 | 0 | 0 | 31.685 | - |
- February - 2019 |
Work order issued on 29/01/2016 but site not available. |
No Image |
DI.Khan | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.685 | 0 | 0 | 0 | 0 | 0 | 0 | 31.685 | - |
- January - 2019 |
Work order issued on 29/01/2016 but site not available. |
No Image |
DI.Khan | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 10 | 10.705 | 10.705 | 10.705 | 3.516 | 13.516 | 21.77 | 49% |
32% December - 2019 |
SS in progress. |
No Image |
Construction of the Sereatriat Tehsil Building, Pattan Lower Kohistan | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 10 | 10.705 | 10.705 | 10.705 | 5 | 15 | 21.77 | 49% |
35% November - 2019 |
SS in progress. |
No Image |
Construction of the Sereatriat Tehsil Building, Pattan Lower Kohistan | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 10 | 10.705 | 10.705 | 10.705 | 5 | 15 | 21.77 | 49% |
35% October - 2019 |
SS in progress. |
No Image |
Construction of the Sereatriat Tehsil Building, Pattan Lower Kohistan | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 10 | 10.705 | 10.705 | 10.705 | 0 | 10 | 21.77 | 49% |
24% September - 2019 |
SS in progress. |
No Image |
Construction of the Sereatriat Tehsil Building, Pattan Lower Kohistan | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 10 | 0 | 0 | 0 | 0 | 10 | 32.475 | - |
24% August - 2019 |
Work in progress. |
No Image |
Construction of the Sereatriat Tehsil Building, Pattan Lower Kohistan | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 10 | 10.705 | 10.705 | 10.705 | 3.516 | 13.516 | 21.77 | 49% |
32% May - 2020 |
Super Structure in progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building, Pattan Lower Kohistan | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 10 | 10.705 | 10.705 | 10.705 | 3.516 | 13.516 | 21.77 | 49% |
32% April - 2020 |
Super Structure in progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building, Pattan Lower Kohistan | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 10 | 10.705 | 10.705 | 10.705 | 3.516 | 13.516 | 21.77 | 49% |
32% March - 2020 |
Super Structure in progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building, Pattan Lower Kohistan | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 10 | 10.705 | 10.705 | 10.705 | 3.516 | 13.516 | 21.77 | 49% |
32% February - 2020 |
Super Structure in progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building, Pattan Lower Kohistan | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 10 | 10.705 | 10.705 | 10.705 | 3.516 | 13.516 | 21.77 | 49% |
32% January - 2020 |
Roofing in progress.
Court Case on partial site |
No Image |
Construction of the Sereatriat Tehsil Building, Pattan Lower Kohistan | |||||||||||||||||||
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
15-01-15 | 30-06-18 | - | 14-04-15 | - | 114.225 | 70.255 | 48.75 | 48.75 | 36.563 | 34.926 | 105.181 | 0 | 100% |
92% December - 2017 |
Block-A, B and C - finishing in progress. Balance funds required for completion. |
No Image |
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.225 | 70.255 | 48.75 | 48.75 | 36.563 | 30.891 | 101.146 | 0 | 100% |
89% November - 2017 |
Block-A, B and C - finishing in progress. |
No Image |
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.225 | 70.255 | 48.75 | 48.75 | 26.563 | 21.938 | 92.193 | 0 | 100% |
81% October - 2017 |
Block-A, B and C - finishing in progress. |
No Image |
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
15-01-15 | 30-06-18 | - | 14-04-15 | - | 114.225 | 70.255 | 48.75 | 48.75 | 21.938 | 17.875 | 88.13 | 0 | 100% |
77% September - 2017 |
Block-A, B and C - finishing in progress. |
No Image |
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
15-01-15 | 30-06-18 | - | 14-04-15 | - | 114.225 | 70.255 | 48.75 | 48.75 | 21.938 | 17.875 | 88.13 | 0 | 100% |
77% August - 2017 |
Block-A, B and C - finishing in progress. |
No Image |
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
15-01-15 | 30-06-18 | - | 14-04-15 | - | 114.225 | 70.255 | 48.75 | 48.75 | 21.938 | 0 | 70.255 | 0 | 100% |
62% July - 2017 |
Block-A, B and C - finishing in progress. |
No Image |
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.225 | 70.255 | 48.75 | 41.929 | 41.929 | 41.929 | 112.184 | 0 | 100% |
98% June - 2018 |
Block-A, B and C - finishing in progress. |
No Image |
Peshawar | |||||||||||||||||||
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.225 | 70.255 | 48.75 | 48.75 | 48.75 | 39.899 | 110.154 | 0 | 100% |
96% May - 2018 |
Block-A, B and C - finishing in progress. |
No Image |
Peshawar | |||||||||||||||||||
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.225 | 70.255 | 48.75 | 48.75 | 48.75 | 39.899 | 110.154 | 0 | 100% |
96% April - 2018 |
Block-A, B and C - finishing in progress. Balance funds required for completion. |
No Image |
Peshawar | |||||||||||||||||||
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.225 | 70.255 | 48.75 | 48.75 | 48.75 | 36.563 | 106.818 | 0 | 100% |
94% March - 2018 |
Block-A, B and C - finishing in progress. Balance funds required for completion. |
No Image |
Peshawar | |||||||||||||||||||
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.225 | 70.255 | 48.75 | 48.75 | 36.563 | 36.563 | 106.818 | 0 | 100% |
94% February - 2018 |
Block-A, B and C - finishing in progress. Balance funds required for completion. |
No Image |
Peshawar | |||||||||||||||||||
105 (OG) |
140780-Additional Accommodation for Khyber Pakhtunkhwa Public Service Commission. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.225 | 70.255 | 48.75 | 48.75 | 36.563 | 34.926 | 105.181 | 0 | 100% |
92% January - 2018 |
Block-A, B and C - finishing in progress. Balance funds required for completion. |
No Image |
Peshawar | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.346 | 0 | 0 | 0 | 0 | 0 | 0 | 30.346 | - |
- December - 2019 |
NOC from Admin Deptt awaited for demolishing of old building. |
No Image |
Re-construction of Mosque | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.346 | 0 | 0 | 0 | 0 | 0 | 0 | 30.346 | - |
- November - 2019 |
NOC from Admin Deptt awaited for demolishing of old building. |
No Image |
Re-construction of Mosque | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.346 | 0 | 0 | 0 | 0 | 0 | 0 | 30.346 | - |
- October - 2019 |
NOC from Admin Deptt awaited for demolishing of old building. |
No Image |
Re-construction of Mosque | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.346 | 0 | 0 | 0 | 0 | 0 | 0 | 30.346 | - |
- September - 2019 |
NOC from Admin Deptt awaited for demolishing of old building. |
No Image |
Re-construction of Mosque | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.346 | 0 | 0 | 0 | 0 | 0 | 0 | 30.346 | - |
- August - 2019 |
NOC from Admin Deptt awaited for demolishing of old building. |
No Image |
Re-construction of Mosque | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.346 | 0 | 0 | 0 | 0 | 0 | 0 | 30.346 | - |
- May - 2020 |
NOC from Admin Deptt awaited for demolishing of old building. |
No Image |
Re-construction of Mosque | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.346 | 0 | 0 | 0 | 0 | 0 | 0 | 30.346 | - |
- April - 2020 |
NOC from Admin Deptt awaited for demolishing of old building. |
No Image |
Re-construction of Mosque | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.346 | 0 | 0 | 0 | 0 | 0 | 0 | 30.346 | - |
- March - 2020 |
NOC from Admin Deptt awaited for demolishing of old building. |
No Image |
Re-construction of Mosque | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.346 | 0 | 0 | 0 | 0 | 0 | 0 | 30.346 | - |
- February - 2020 |
NOC from Admin Deptt awaited for demolishing of old building. |
No Image |
Re-construction of Mosque | |||||||||||||||||||
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.346 | 0 | 0 | 0 | 0 | 0 | 0 | 30.346 | - |
- January - 2020 |
NOC from Admin Deptt awaited for demolishing of old building. |
No Image |
Re-construction of Mosque | |||||||||||||||||||
105 (OG) |
150538-Strengthening/Capacity Building of Directorate of Anti-Corruption Establishment. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 25.697 | 40.466 | 40.466 | 15.233 | 0 | 25.697 | 33.837 | 66% |
26% December - 2018 |
Work in progress. |
No Image |
105 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.821 | 20 | 42.821 | 42.821 | 10.705 | 0 | 20 | 0 | - |
- December - 2019 |
Kohitan: Work started. Redesigning of foundation /structure based on secretary CWD instructions. Cannot be completed. |
No Image |
Pages : 1 2 |