Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
670 (OG) |
140936-F/S, Design and BT of internal roads Pirpiai - Azakhel Bala - Payan - Dagai - Banda Nabi, Badrashi, Nowshera. SH: Const of internal road in UCs Dagai-Banda Nabi, Pirpiai, Badrashi, Azakhel Bala & Payan, District Nowshera (Phase-II). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1050 | 606.584 | 20 | 20 | 20 | 20 | 626.584 | 423.416 | 60% |
60% September - 2018 |
Original scope + 1st Revised scope completed (35 Km). 2nd and 3rd revised scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
670 (OG) |
140936-F/S, Design and BT of internal roads Pirpiai - Azakhel Bala - Payan - Dagai - Banda Nabi, Badrashi, Nowshera. SH: Const of internal road in UCs Dagai-Banda Nabi, Pirpiai, Badrashi, Azakhel Bala & Payan, District Nowshera (Phase-II). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1050 | 606.584 | 20 | 20 | 10 | 0 | 606.584 | 423.416 | 60% |
58% July - 2018 |
Original scope + 1st Revised scope completed (35 Km). 2nd and 3rd revised scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
- December - 2020 |
No Image | |
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
- December - 2020 |
No Image | |
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
- October - 2020 |
No Image | |
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
- September - 2020 |
No Image | |
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
- August - 2020 |
No Image | |
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
July - 2020 |
No Image | |
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
- May - 2021 |
No Image | |
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
- April - 2021 |
No Image | |
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
- March - 2021 |
No Image | |
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
- February - 2021 |
No Image | |
670 (OG) |
170102-Billion Tree Afforestation Project in Khyber Pakhtunkhwa Phase-III |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7709.79 | 5164.897 | 0 | 0 | 0 | 0 | 5164.897 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |