Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
520 (OG) |
150278-Feasibility Study & Construction of central prison Malakand.(PC-II approved on 18-04-2018) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
PC-II for Rs.25 m approved in DDWP on 18/04/2018. LOA issued to M/S Structural Engineering Solution on 19/03/2019 IG Prison visited on site 10/12/2019.Master plan discussed with I.G prisons. Modification is under process. |
No Image |
District Jail Malakand | |||||||||||||||||||
520 (OG) |
150278-Feasibility Study & Construction of central prison Malakand.(PC-II approved on 18-04-2018) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
PC-II for Rs.25 m approved in DDWP on 18/04/2018. LOA issued to M/S Structural Engineering Solution on 19/03/2019 IG Prison vsisited on site 10/12/2019. DCE under preparation. |
No Image |
District Jail Malakand | |||||||||||||||||||
520 (OG) |
150278-Feasibility Study & Construction of central prison Malakand.(PC-II approved on 18-04-2018) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
PC-II for Rs.25 m approved in DDWP on 18/04/2018. LOA issued to M/S Structural Engineering Solution on 19/03/2019. |
No Image |
District Jail Malakand | |||||||||||||||||||
520 (OG) |
150278-Feasibility Study & Construction of central prison Malakand.(PC-II approved on 18-04-2018) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
PC-II for Rs.25 m approved in DDWP on 18/04/2018. LOA issued to M/S Structural Engineering Solution on 19/03/2019. |
No Image |
District Jail Malakand | |||||||||||||||||||
520 (OG) |
150278-Feasibility Study & Construction of central prison Malakand.(PC-II approved on 18-04-2018) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
PC-II for Rs.25 m approved in DDWP on 18/04/2018. LOA issued to M/S Structural Engineering Solution on 19/03/2019. |
No Image |
District Jail Malakand | |||||||||||||||||||
520 (OG) |
150278-Feasibility Study & Construction of central prison Malakand.(PC-II approved on 18-04-2018) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
PC-II for Rs.25 m approved in DDWP on 18/04/2018. LOA issued to M/S Structural Engineering Solution on 19/03/2019 IG Prison visited on site 10/12/2019.Master plan discussed with I.G prisons. Modification is under process.
Dce will be submitted by 20/2/20 |
No Image |
District Jail Malakand | |||||||||||||||||||
520 (OG) |
150278-Feasibility Study & Construction of central prison Malakand.(PC-II approved on 18-04-2018) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
PC-II for Rs.25 m approved in DDWP on 18/04/2018. LOA issued to M/S Structural Engineering Solution on 19/03/2019 IG Prison visited on site 10/12/2019.Master plan discussed with I.G prisons. Modification is under process.
Dce will be submitted by 20/2/20 |
No Image |
District Jail Malakand | |||||||||||||||||||
520 (OG) |
150278-Feasibility Study & Construction of central prison Malakand.(PC-II approved on 18-04-2018) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
PC-II for Rs.25 m approved in DDWP on 18/04/2018. LOA issued to M/S Structural Engineering Solution on 19/03/2019 IG Prison visited on site 10/12/2019.Master plan discussed with I.G prisons. Modification is under process.
Dce will be submitted by 20/2/20 |
No Image |
District Jail Malakand | |||||||||||||||||||
520 (OG) |
150278-Feasibility Study & Construction of central prison Malakand.(PC-II approved on 18-04-2018) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
PC-II for Rs.25 m approved in DDWP on 18/04/2018. LOA issued to M/S Structural Engineering Solution on 19/03/2019 IG Prison visited on site 10/12/2019.Master plan discussed with I.G prisons. Modification is under process.
Dce will be submitted by 20/2/20 |
No Image |
District Jail Malakand | |||||||||||||||||||
520 (OG) |
150278-Feasibility Study & Construction of central prison Malakand.(PC-II approved on 18-04-2018) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
PC-II for Rs.25 m approved in DDWP on 18/04/2018. LOA issued to M/S Structural Engineering Solution on 19/03/2019 IG Prison visited on site 10/12/2019.Master plan discussed with I.G prisons. Modification is under process.
Dce will be submitted by 20/2/20 |
No Image |
District Jail Malakand | |||||||||||||||||||
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 30.347 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
DCE is under preparation process. |
No Image |
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 30.347 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
DCE is under preparation process. |
No Image |
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 30.347 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
DCE is under preparation process. |
No Image |
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 30.347 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
DCE is under preparation process. |
No Image |
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 30.347 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
DCE is under preparation process. |
No Image |
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 30.347 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
DCE is under preparation process. |
No Image |
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 30.347 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
DCE is under preparation process. |
No Image |
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 30.347 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
DCE is under preparation process. |
No Image |
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 30.347 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
DCE is under preparation process. |
No Image |
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 30.347 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
DCE is under preparation process. |
No Image |
520 (New) |
191378- Construction of Buildings for 9 Community Schools, Up-gradation of 3 P.S to M.S (2 Girls & 1 Boys) & Upgradation of 9 P.S to M.S in District South Waziristan. (Umbrella) (AIP) |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 180 | 0 | 30.347 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
Pages : 1 |