Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 27.451 | 4.968 | 4.968 | 4.968 | 4.968 | 32.419 | 27.623 | 54% |
54% December - 2020 |
Out of 4 units, work in progress on all units |
No Image |
1) GGPS Seragran Aliabad.
  | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 27.451 | 4.968 | 4.968 | 4.968 | 4.968 | 32.419 | 27.623 | 54% |
54% December - 2020 |
Out of 4 units, work in progress on all units |
No Image |
1) GGPS Seragran Aliabad.
  | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 0 | 1.471 | 1.471 | 1.471 | 1.471 | 1.471 | 58.571 | 2% |
2% October - 2020 |
Out of 4 units, work in progress on all units |
No Image |
1) GGPS Seragran Aliabad.
  | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 0 | 0 | 0 | 0 | 0 | 0 | 60.042 | - |
- September - 2020 |
Out of 4 units, work in progress on all units |
No Image |
1) GGPS Seragran Aliabad.
  | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 0 | 0 | 0 | 0 | 0 | 0 | 60.042 | - |
- August - 2020 |
Out of 2 units, 1 work order issued, 1 in progress |
No Image |
1) GGPS Seragran Aliabad.
  | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 0 | 0 | 0 | 0 | 0 | 0 | 60.042 | - |
- July - 2020 |
Out of 2 units, 1 work order issued, 1 in progress |
No Image |
1) GGPS Seragran Aliabad.
  | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 27.451 | 24.577 | 24.577 | 24.577 | 14.272 | 41.723 | 8.014 | 87% |
69% May - 2021 |
04- Units
1. Dev: work in pogress, M/B slab laid
2. Dev: work in pogress, G/F slab laid, 1st Floor S/Stru: in progress
3. Dev: work in pogress, G/F slab laid, 1st Floor S/Stru: in progress
4. Dev: work in pogress, M/B layout given |
No Image |
1) GGPS Seragran Aliabad .?. Rs: 21.388 M .?? TS 19.50
2. GGPS Kutla Jandar Bari .?. Rs: 20.836 M
3. GPS Chalhaiter .?. Rs: 18.006 M .?? TS 18.521
4. GGPS Serian Bagh .?. Rs: 20.836 M | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 27.451 | 24.577 | 24.577 | 24.577 | 14.272 | 41.723 | 8.014 | 87% |
69% April - 2021 |
04 units,
1. Dev: work in pogress, M/B slab laid
2. Dev: work in pogress, G/F slab laid, 1st Floor S/Stru: in progress
3. Dev: work in pogress, G/F slab laid, 1st Floor S/Stru: in progress
4. Dev: work in pogress, M/B layout given |
No Image |
1) GGPS Seragran Aliabad .?. Rs: 21.388 M .?? TS 19.50
2. GGPS Kutla Jandar Bari .?. Rs: 20.836 M
3. GPS Chalhaiter .?. Rs: 18.006 M .?? TS 18.521
4. GGPS Serian Bagh .?. Rs: 20.836 M | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 27.451 | 14.577 | 14.577 | 14.577 | 13.997 | 41.448 | 18.014 | 70% |
69% March - 2021 |
04 units,
1. Dev: work in pogress, M/B slab laid
2. Dev: work in pogress, G/F slab laid, 1st Floor S/Stru: in progress
3. Dev: work in pogress, G/F slab laid, 1st Floor S/Stru: in progress
4. Dev: work in pogress, M/B layout given |
No Image |
1) GGPS Seragran Aliabad .?. Rs: 21.388 M .?? TS 19.50
2. GGPS Kutla Jandar Bari .?. Rs: 20.836 M
3. GPS Chalhaiter .?. Rs: 18.006 M .?? TS 18.521
4. GGPS Serian Bagh .?. Rs: 20.836 M | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 27.451 | 14.577 | 14.577 | 14.577 | 13.997 | 41.448 | 18.014 | 70% |
69% February - 2021 |
04 units,
1. Dev: work in pogress, M/B slab laid
2. Dev: work in pogress, G/F slab laid, 1st Floor S/Stru: in progress
3. Dev: work in pogress, G/F slab laid, 1st Floor S/Stru: in progress
4. Dev: work in pogress, M/B layout given |
No Image |
1) GGPS Seragran Aliabad .?. Rs: 21.388 M .?? TS 19.50
2. GGPS Kutla Jandar Bari .?. Rs: 20.836 M
3. GPS Chalhaiter .?. Rs: 18.006 M .?? TS 18.521
4. GGPS Serian Bagh .?. Rs: 20.836 M | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.042 | 27.451 | 14.577 | 14.577 | 14.577 | 12.108 | 39.559 | 18.014 | 70% |
66% January - 2021 |
04 units,
1. Dev: work in pogress, M/B slab laid
2. Dev: work in pogress, G/F slab laid, 1st Floor S/Stru: in progress
3. Dev: work in pogress, G/F slab laid, 1st Floor S/Stru: in progress
4. Dev: work in pogress, M/B layout given |
No Image |
1) GGPS Seragran Aliabad .?. Rs: 21.388 M
2. GGPS Kutla Jandar Bari .?. Rs: 20.836 M
3. GPS Chalhaiter .?. Rs: 18.006 M
4. GGPS Serian Bagh .?. Rs: 20.836 M | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 71.83 | 6.622 | 6.622 | 6.622 | 6.621 | 78.451 | 60.15 | 57% |
57% December - 2020 |
5 units -
2 in finishing Level,
3 - Work in progress.
TS submitted to SE |
No Image |
1) GGPS Ibrahim Utin Khel PK-71
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 71.83 | 6.622 | 6.622 | 6.622 | 6.621 | 78.451 | 60.15 | 57% |
57% December - 2020 |
5 units -
2 in finishing Level,
3 - Work in progress.
TS submitted to SE |
No Image |
1) GGPS Ibrahim Utin Khel PK-71
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 0 | 2 | 2 | 2 | 2 | 2 | 136.602 | 1% |
1% October - 2020 |
5 units -
2 in finishing Level,
3 - Work in progress. |
No Image |
1) GGPS Ibrahim Utin Khel PK-71
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 0 | 2 | 2 | 2 | 2 | 2 | 136.602 | 1% |
1% September - 2020 |
5 units -
2 in finishing Level,
3 - Work in progress. |
No Image |
1) GGPS Ibrahim Utin Khel PK-71
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 0 | 2 | 2 | 2 | 2 | 2 | 136.602 | 1% |
1% August - 2020 |
5 units -
2 in finishing Level,
3 - Work in progress. |
No Image |
1) GGPS Ibrahim Utin Khel PK-71
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 0 | 0 | 0 | 0 | 0 | 0 | 138.602 | - |
- July - 2020 |
5 units -
2 in finishing Level,
3 - Work in p |
No Image |
1) GGPS Ibrahim Utin Khel PK-71
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 71.83 | 19.286 | 19.286 | 19.286 | 18.69 | 90.52 | 47.486 | 66% |
65% May - 2021 |
08- Units
1 Finihsing
2 Completed & H/O
3 Finihsing
4 Finihsing
5 1st floor column completed
6 G/F roof laid
7 Struture work complted
8 M/B Completed upto DPC level |
No Image |
1 GGPS Ibrahim Utin Khel PK-71
2 GGPS Fares Khan .?.?.. (TS 18.658)
3 GGPS Mir Shafrof Khan S/T GGPS Badshah Alam Aghi Sardi Khel
4 GGPS Bhettani Koroona Sher Adam .?.?.. (TS 16.848)
5 GGPS Ibrahim Utin Khel
6 GPS Malik Yasir Khan .?.?.. (TS 19.00)
7 GPS Irfan Nar Shukar Ullah .?.?.. (TS 18.648)
8 GGPS Sada Khel Nawali Khan .?.?.. (TS 19.008) | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 71.83 | 19.286 | 19.286 | 19.286 | 18.69 | 90.52 | 47.486 | 66% |
65% April - 2021 |
8 units -
1 Finihsing
2 Completed & H/O
3 Finihsing
4 Finihsing
5 1st floor column completed
6 G/F roof laid
7 Struture work complted
8 M/B Completed upto DPC level |
No Image |
1 GGPS Ibrahim Utin Khel PK-71
2 GGPS Fares Khan .?.?.. (TS 18.658)
3 GGPS Mir Shafrof Khan S/T GGPS Badshah Alam Aghi Sardi Khel
4 GGPS Bhettani Koroona Sher Adam .?.?.. (TS 16.848)
5 GGPS Ibrahim Utin Khel
6 GPS Malik Yasir Khan .?.?.. (TS 19.00)
7 GPS Irfan Nar Shukar Ullah .?.?.. (TS 18.648)
8 GGPS Sada Khel Nawali Khan .?.?.. (TS 19.008) | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 71.83 | 19.286 | 19.286 | 19.286 | 12.889 | 84.719 | 47.486 | 66% |
61% March - 2021 |
8 units -
1 Finihsing
2 Completed & H/O
3 Finihsing
4 Finihsing
5 1st floor column completed
6 G/F roof laid
7 Struture work complted
8 M/B Completed upto DPC level |
No Image |
1 GGPS Ibrahim Utin Khel PK-71
2 GGPS Fares Khan .?.?.. (TS 18.658)
3 GGPS Mir Shafrof Khan S/T GGPS Badshah Alam Aghi Sardi Khel
4 GGPS Bhettani Koroona Sher Adam .?.?.. (TS 16.848)
5 GGPS Ibrahim Utin Khel
6 GPS Malik Yasir Khan .?.?.. (TS 19.00)
7 GPS Irfan Nar Shukar Ullah .?.?.. (TS 18.648)
8 GGPS Sada Khel Nawali Khan .?.?.. (TS 19.008) | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 71.83 | 19.286 | 19.286 | 19.286 | 12.889 | 84.719 | 47.486 | 66% |
61% February - 2021 |
8 units -
1 Finihsing
2 Completed & H/O
3 Finihsing
4 Finihsing
5 1st floor column completed
6 G/F roof laid
7 Struture work complted
8 M/B Completed upto DPC level |
No Image |
1 GGPS Ibrahim Utin Khel PK-71
2 GGPS Fares Khan .?.?.. (TS 18.658)
3 GGPS Mir Shafrof Khan S/T GGPS Badshah Alam Aghi Sardi Khel
4 GGPS Bhettani Koroona Sher Adam .?.?.. (TS 16.848)
5 GGPS Ibrahim Utin Khel
6 GPS Malik Yasir Khan .?.?.. (TS 19.00)
7 GPS Irfan Nar Shukar Ullah .?.?.. (TS 18.648)
8 GGPS Sada Khel Nawali Khan .?.?.. (TS 19.008) | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 138.602 | 71.83 | 19.286 | 19.286 | 19.286 | 8.636 | 80.466 | 47.486 | 66% |
58% January - 2021 |
5 units -
2 in finishing Level,
3 - Work in progress.
TS submitted to SE |
No Image |
1) GGPS Ibrahim Utin Khel PK-71
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.565 | 0 | 2.052 | 2.052 | 2.052 | 0 | 0 | 32.513 | 6% |
- October - 2020 |
2 units - 1 in progress, 1 Site preparation in pro |
No Image |
1) GPS Gul Kanda PK-78
2) GPS B | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.565 | 0 | 2.052 | 2.052 | 2.052 | 0 | 0 | 32.513 | 6% |
- September - 2020 |
2 units - 1 in progress, 1 Site preparation in pro |
No Image |
1) GPS Gul Kanda PK-78
2) GPS B | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.565 | 0 | 0 | 0 | 0 | 0 | 0 | 34.565 | - |
- August - 2020 |
2 units - 1 in progress, 1 Site preparation in pro |
No Image |
1) GPS Gul Kanda PK-78
2) GPS B | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.565 | 0 | 0 | 0 | 0 | 0 | 0 | 34.565 | - |
- July - 2020 |
2 units - 1 in progress, 1 Site preparation in pro |
No Image |
1) GPS Gul Kanda PK-78
2) GPS B | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.565 | 13.969 | 11.56 | 11.56 | 11.56 | 9.928 | 23.897 | 9.036 | 74% |
69% May - 2021 |
02- Units
1. Completed Pc-IV sub:
2. F/F column in progress |
No Image |
1) GPS Gul Kanda PK-78 ? Rs: 17.282 M
2) GPS Baba Faiza ? Rs: 18.142 M | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.565 | 2.874 | 11.56 | 11.56 | 11.56 | 9.928 | 12.802 | 20.131 | 42% |
37% April - 2021 |
2 units -
01 completed Pc-IV sub:
02 F/F column in progress |
No Image |
1) GPS Gul Kanda PK-78 ? Rs: 17.282 M
2) GPS Baba Faiza ? Rs: 18.142 M | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.565 | 2.874 | 4.061 | 4.061 | 4.061 | 4.041 | 6.915 | 27.63 | 20% |
20% March - 2021 |
2 units -
01 completed Pc-IV sub:
02 F/F column in progress |
No Image |
1) GPS Gul Kanda PK-78 ? Rs: 17.282 M
2) GPS Baba Faiza ? Rs: 18.142 M | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.565 | 2.874 | 4.061 | 4.061 | 4.061 | 4.041 | 6.915 | 27.63 | 20% |
20% February - 2021 |
2 units -
01 completed Pc-IV sub:
02 F/F column in progress |
No Image |
1) GPS Gul Kanda PK-78 ? Rs: 17.282 M
2) GPS Baba Faiza ? Rs: 18.142 M | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.565 | 2.874 | 4.061 | 4.061 | 4.061 | 4.041 | 6.915 | 27.63 | 20% |
20% January - 2021 |
2 units -
01 completed Pc-IV sub:
02 F/F column in progress |
No Image |
1) GPS Gul Kanda PK-78
2) GPS Baba Faiza | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.636 | 0 | 0.598 | 0.598 | 0.598 | 0.423 | 0.423 | 32.038 | 2% |
1% October - 2020 |
7 units -
1 unit Coimpleted & H/O.
1 unit in progress,
5 units AA awaited. |
No Image |
1) GPS Darwazgai PK-56
2) GPS S | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.636 | 0 | 0.598 | 0.598 | 0.598 | 0.423 | 0.423 | 32.038 | 2% |
1% September - 2020 |
7 units -
1 unit Coimpleted & H/O.
1 unit in progress,
5 units AA awaited. |
No Image |
1) GPS Darwazgai PK-56
2) GPS S | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.636 | 0 | 0.598 | 0.598 | 0.598 | 0 | 0 | 32.038 | 2% |
- August - 2020 |
7 units -
1 unit Coimpleted & H/O.
1 unit in progress,
5 units AA awaited. |
No Image |
1) GPS Darwazgai PK-56
2) GPS S | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.636 | 0 | 0 | 0 | 0 | 0 | 0 | 32.636 | - |
- July - 2020 |
7 units - 2 in progress, 5 AA awaited. |
No Image |
1) GPS Darwazgai PK-56
2) GPS S | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.636 | 25.69 | 0.598 | 0.598 | 0.598 | 0.423 | 26.113 | 6.348 | 81% |
80% May - 2021 |
02- Units
1. Coimpleted & H/O.
2. Finishing |
No Image |
1. GPS Darwazgai u/c Behram Dheri PK-56.?. Rs: 16.318 M
2. GPS Speal Koroona U/C Matta PK-60.?. Rs: 16.318 M
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.636 | 25.69 | 0.598 | 0.598 | 0.598 | 0.423 | 26.113 | 6.348 | 81% |
80% April - 2021 |
02 units -
1 unit Coimpleted & H/O.
1 unit finishing |
No Image |
1. GPS Darwazgai u/c Behram Dheri PK-56.?. Rs: 16.318 M
2. GPS Speal Koroona U/C Matta PK-60.?. Rs: 16.318 M
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.636 | 25.69 | 0.598 | 0.598 | 0.598 | 0.423 | 26.113 | 6.348 | 81% |
80% March - 2021 |
02 units -
1 unit Coimpleted & H/O.
1 unit finishing |
No Image |
1. GPS Darwazgai u/c Behram Dheri PK-56.?. Rs: 16.318 M
2. GPS Speal Koroona U/C Matta PK-60.?. Rs: 16.318 M
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.636 | 25.69 | 0.598 | 0.598 | 0.598 | 0.423 | 26.113 | 6.348 | 81% |
80% February - 2021 |
02 units -
1 unit Coimpleted & H/O.
1 unit finishing |
No Image |
1. GPS Darwazgai u/c Behram Dheri PK-56.?. Rs: 16.318 M
2. GPS Speal Koroona U/C Matta PK-60.?. Rs: 16.318 M
| |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.636 | 25.69 | 0.598 | 0.598 | 0.598 | 0.423 | 26.113 | 6.348 | 81% |
80% January - 2021 |
02 units -
1 unit Coimpleted & H/O.
1 unit finishing |
No Image |
1. GPS Darwazgai u/c Behram Dheri PK-56.?. Rs: 16.318 M
2. GPS Speal Koroona U/C Matta PK-60.?. Rs: 16.318 M
| |||||||||||||||||||
392 (OG) |
140763-Strengthening of THQ Hospital Drosh, Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112 | 45.634 | 66.366 | 70.091 | 70.091 | 23.24 | 68.874 | 0 | 100% |
61% December - 2018 |
Main building - SS (Gyne/Children) in progress. BW in progress. |
No Image |
Drosh, Chitral | |||||||||||||||||||
392 (OG) |
140763-Strengthening of THQ Hospital Drosh, Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112 | 45.634 | 66.366 | 66.366 | 47.168 | 16.66 | 62.294 | 0 | 100% |
56% November - 2018 |
Main building - SS (Gyne/Children) in progress. BW in progress. |
No Image |
Drosh, Chitral | |||||||||||||||||||
392 (OG) |
140763-Strengthening of THQ Hospital Drosh, Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112 | 45.634 | 66.366 | 66.366 | 47.168 | 16.66 | 62.294 | 0 | 100% |
56% November - 2018 |
Main building - SS (Gyne/Children) in progress. BW in progress. |
No Image |
Drosh, Chitral | |||||||||||||||||||
392 (OG) |
140763-Strengthening of THQ Hospital Drosh, Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112 | 45.634 | 66.366 | 66.366 | 66.366 | 31.117 | 76.751 | 0 | 100% |
69% April - 2019 |
Main building - SS (Gyne/Children) in progress. BW in progress. |
No Image |
Drosh, Chitral | |||||||||||||||||||
392 (OG) |
140763-Strengthening of THQ Hospital Drosh, Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112 | 45.634 | 66.366 | 66.366 | 66.366 | 31.117 | 76.751 | 0 | 100% |
69% March - 2019 |
Main building - SS (Gyne/Children) in progress. BW in progress. |
No Image |
Drosh, Chitral | |||||||||||||||||||
392 (OG) |
140763-Strengthening of THQ Hospital Drosh, Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112 | 45.634 | 66.366 | 66.366 | 66.366 | 31.117 | 76.751 | 0 | 100% |
69% March - 2019 |
Main building - SS (Gyne/Children) in progress. BW in progress. |
No Image |
Drosh, Chitral | |||||||||||||||||||
392 (OG) |
140763-Strengthening of THQ Hospital Drosh, Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112 | 45.634 | 66.366 | 70.091 | 70.091 | 23.24 | 68.874 | 0 | 100% |
61% February - 2019 |
Main building - SS (Gyne/Children) in progress. BW in progress. |
No Image |
Drosh, Chitral | |||||||||||||||||||
392 (OG) |
140763-Strengthening of THQ Hospital Drosh, Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112 | 45.634 | 66.366 | 70.091 | 70.091 | 23.24 | 68.874 | 0 | 100% |
61% January - 2019 |
Main building - SS (Gyne/Children) in progress. BW in progress. |
No Image |
Drosh, Chitral | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.262 | 0 | 0.997 | 0.997 | 0.997 | 0.997 | 0.997 | 54.265 | 2% |
2% October - 2020 |
2 units - all in progress. |
No Image |
1) GPS Domelnisar PK-90
2) GGPS | |||||||||||||||||||
392 (OG) |
170207-Establishment of 100 Primary Schools (B&G 30:70) on need basis in Khyber Pakhtunkhwa. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.262 | 0 | 0.997 | 0.997 | 0.997 | 0.997 | 0.997 | 54.265 | 2% |
2% September - 2020 |
2 units - all in progress. |
No Image |
1) GPS Domelnisar PK-90
2) GGPS | |||||||||||||||||||