Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.937 | 0 | 2.505 | 2.505 | 2.505 | 1.005 | 1.005 | 19.432 | 11% |
5% October - 2020 |
Developmental work in progress. MB = G/Floor,Ist floor roof laid. Plastering & flooring in progress. |
No Image |
GMPS Barrian PK-48 | |||||||||||||||||||
391 (OG) |
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.088 | 35.869 | 5 | 5 | 5 | 0 | 35.869 | 131.219 | 24% |
21% September - 2018 |
Out of 2 units,1 in progress, 1 financial bid opened on 12/03/2018. |
No Image |
1) GDC Rajoya, Abbottabad | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.927 | 0 | 0 | 0 | 0 | 0 | 0 | 20.927 | - |
- September - 2020 |
Developmental work in progress. MB = G/Floor,Ist floor roof laid. Plastering & flooring in progress. |
No Image |
GMPS Barrian PK-48 | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.927 | 0 | 0 | 0 | 0 | 0 | 0 | 20.927 | - |
- August - 2020 |
MB Plinth beam laid. |
No Image |
GMPS Barrian PK-48 | |||||||||||||||||||
391 (OG) |
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.088 | 35.869 | 0 | 0 | 0 | 0 | 35.869 | 136.219 | - |
21% July - 2018 |
Out of 2 units,1 in progress, 1 financial bid opened on 12/03/2018. |
No Image |
1) GDC Rajoya, Abbottabad | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.927 | 0 | 0 | 0 | 0 | 0 | 0 | 20.927 | - |
- July - 2020 |
MB Plinth beam laid. |
No Image |
GMPS Barrian PK-48 | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.937 | 13.795 | 7.168 | 7.168 | 7.168 | 2.619 | 16.414 | 0.974 | 96% |
75% May - 2021 |
01- Unit
Developmental work in progress. MB = G/Floor,Ist floor roof laid. Plastering & flooring in progress. |
No Image |
GMPS Barrian PK-48 | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.937 | 13.795 | 7.168 | 7.168 | 7.168 | 2.619 | 16.414 | 0.974 | 96% |
75% April - 2021 |
Developmental work in progress. MB = G/Floor,Ist floor roof laid. Plastering & flooring in progress. |
No Image |
GMPS Barrian PK-48 | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.937 | 13.795 | 7.168 | 7.168 | 7.168 | 2.619 | 16.414 | 0.974 | 96% |
75% March - 2021 |
Developmental work in progress. MB = G/Floor,Ist floor roof laid. Plastering & flooring in progress. |
No Image |
GMPS Barrian PK-48 | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.937 | 13.795 | 7.168 | 7.168 | 7.168 | 2.619 | 16.414 | 0.974 | 96% |
75% February - 2021 |
Developmental work in progress. MB = G/Floor,Ist floor roof laid. Plastering & flooring in progress. |
No Image |
GMPS Barrian PK-48 | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.937 | 13.795 | 7.168 | 7.168 | 7.168 | 2.505 | 16.3 | 0.974 | 96% |
74% January - 2021 |
Developmental work in progress. MB = G/Floor,Ist floor roof laid. Plastering & flooring in progress. |
No Image |
GMPS Barrian PK-48 | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 47.87 | 18.143 | 18.143 | 18.143 | 17.642 | 65.512 | 42.142 | 61% |
61% December - 2020 |
6 - Units
1- finishing stage.
2. Ist floor roop
TS submitted to SE |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 47.87 | 18.143 | 18.143 | 18.143 | 17.642 | 65.512 | 42.142 | 61% |
61% December - 2020 |
6 - Units
1- finishing stage.
2. Ist floor roop
TS submitted to SE |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 0 | 15.467 | 15.467 | 15.467 | 15.467 | 15.467 | 92.688 | 14% |
14% October - 2020 |
6 - Units
1- finishing stage.
2. Ist floor roop |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 0 | 15.467 | 15.467 | 15.467 | 15.467 | 15.467 | 92.688 | 14% |
14% September - 2020 |
6 - Units
1- finishing stage.
2. Ist floor roop |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 0 | 15.467 | 15.467 | 15.467 | 4.5 | 4.5 | 92.688 | 14% |
4% August - 2020 |
6 - Units
1- finishing stage.
2. Ist floor roop |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 0 | 0 | 0 | 0 | 0 | 0 | 108.155 | - |
- July - 2020 |
6 - Units
1- finishing stage.
2. Ist floor roop |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 47.87 | 26.093 | 26.093 | 26.093 | 26.092 | 73.962 | 34.192 | 68% |
68% May - 2021 |
06- Units
1- Finishing stage.
2. Finishing stage.
3 Finishing
4 Tender cancelled & Revised DCE under preparatoin site Shift to Baka Khel
5 1st floor roof liad6 finishing stage |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72 .?.?.. (TS 17.872)
2 GMPS Sardar Zaman .?.?.. (TS 16.349)
3 GMPS Takhti Khel Mir Ali
4 GMPS Nek Muhammad
5 GMPS Kotka Umer Jan Guli Khel Baka Khel .?.?.. (TS 18.340)
6 GMPS Jani Khel | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 47.87 | 26.093 | 26.093 | 26.093 | 26.092 | 73.962 | 34.192 | 68% |
68% April - 2021 |
6 - Units
1- finishing stage.
2. Ist floor roop
3 Finishing
4 1st floor roof liad
5 completed
6 finishing stage |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72 .?.?.. (TS 17.872)
2 GMPS Sardar Zaman .?.?.. (TS 16.349)
3 GMPS Takhti Khel Mir Ali
4 GMPS Nek Muhammad
5 GMPS Kotka Umer Jan Guli Khel Baka Khel .?.?.. (TS 18.340)
6 GMPS Jani Khel | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 47.87 | 26.093 | 26.093 | 26.093 | 22.486 | 70.356 | 34.192 | 68% |
65% March - 2021 |
6 - Units
1- finishing stage.
2. Ist floor roop
3 Finishing
4 1st floor roof liad
5 completed
6 finishing stage |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72 .?.?.. (TS 17.872)
2 GMPS Sardar Zaman .?.?.. (TS 16.349)
3 GMPS Takhti Khel Mir Ali
4 GMPS Nek Muhammad
5 GMPS Kotka Umer Jan Guli Khel Baka Khel .?.?.. (TS 18.340)
6 GMPS Jani Khel | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 47.87 | 26.093 | 26.093 | 26.093 | 22.486 | 70.356 | 34.192 | 68% |
65% February - 2021 |
6 - Units
1- finishing stage.
2. Ist floor roop
3 Finishing
4 1st floor roof liad
5 completed
6 finishing stage |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72 .?.?.. (TS 17.872)
2 GMPS Sardar Zaman .?.?.. (TS 16.349)
3 GMPS Takhti Khel Mir Ali
4 GMPS Nek Muhammad
5 GMPS Kotka Umer Jan Guli Khel Baka Khel .?.?.. (TS 18.340)
6 GMPS Jani Khel | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 108.155 | 47.87 | 26.093 | 26.093 | 26.093 | 17.642 | 65.512 | 34.192 | 68% |
61% January - 2021 |
6 - Units
1- finishing stage.
2. Ist floor roop
TS submitted to SE |
No Image |
1) GMPS Laka Showye Bakka Khel PK-72
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
PC-I/DCE for Rs.17.312 m submitted to DEO |
No Image |
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
PC-I/DCE for Rs.17.312 m submitted to DEO |
No Image |
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
PC-I/DCE for Rs.17.312 m submitted to DEO |
No Image |
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
PC-I/DCE for Rs.17.312 m submitted to DEO on 10/04 |
No Image |
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-I/DCE for Rs.17.312 m submitted to DEO |
No Image |
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
PC-I/DCE for Rs.17.312 m submitted to DEO |
No Image |
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
PC-I/DCE for Rs.17.312 m submitted to DEO |
No Image |
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
PC-I/DCE for Rs.17.312 m submitted to DEO |
No Image |
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
PC-I/DCE for Rs.17.312 m submitted to DEO |
No Image |
391 (OG) |
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 219.129 | 33.635 | 0 | 0 | 0 | 0 | 33.635 | 185.494 | - |
15% September - 2018 |
Land payment made to DC Buner in 06/2017. Section-V under process. Site preparation under process. |
No Image |
GGDC at UC Shal Bandai | |||||||||||||||||||
391 (OG) |
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 219.129 | 33.635 | 0 | 0 | 0 | 0 | 33.635 | 185.494 | - |
15% July - 2018 |
Land payment made to DC Buner in 06/2017. Section-V under process. Site preparation under process. |
No Image |
GGDC at UC Shal Bandai | |||||||||||||||||||
391 (OG) |
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 271.771 | 46.638 | 10 | 10 | 10 | 9.132 | 55.77 | 215.133 | 21% |
21% September - 2018 |
Work order issued (GDC Umarzai PK-19 and GGDC Mandani PK-20). |
No Image |
1) GDC Umarzai PK-19
2) GGDC Mandani PK-20 | |||||||||||||||||||
391 (OG) |
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 271.771 | 46.638 | 0 | 0 | 0 | 0 | 46.638 | 225.133 | - |
17% July - 2018 |
Work order issued (GDC Umarzai PK-19 and GGDC Mandani PK-20). |
No Image |
1) GDC Umarzai PK-19
2) GGDC Mandani PK-20 | |||||||||||||||||||
391 (OG) |
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 238.77 | 47.971 | 0 | 0 | 0 | 0 | 47.971 | 190.799 | - |
20% September - 2018 |
Prequalification of contractor under process. BOQ submitted to quarter concerned for vetting. Land payment of Rs.47.971 m made to DC. |
No Image |
GDC Ayun, Chitral | |||||||||||||||||||
391 (OG) |
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 238.77 | 47.971 | 0 | 0 | 0 | 0 | 47.971 | 190.799 | - |
20% July - 2018 |
Prequalification of contractor under process. BOQ submitted to quarter concerned for vetting. Land payment of Rs.47.971 m made to DC. |
No Image |
GDC Ayun, Chitral | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.881 | 0 | 0 | 0 | 0 | 0 | 0 | 25.881 | - |
- October - 2020 |
Work in progress |
No Image |
2) GMPS Mirash Pattai PK-91
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.881 | 0 | 0 | 0 | 0 | 0 | 0 | 25.881 | - |
- September - 2020 |
Work in progress |
No Image |
2) GMPS Mirash Pattai PK-91
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.881 | 0 | 0 | 0 | 0 | 0 | 0 | 25.881 | - |
- August - 2020 |
Work in progress |
No Image |
2) GMPS Mirash Pattai PK-91
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.881 | 0 | 0 | 0 | 0 | 0 | 0 | 25.881 | - |
- July - 2020 |
Work in progress |
No Image |
2) GMPS Mirash Pattai PK-91
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.881 | 3 | 15.443 | 15.443 | 15.443 | 14.313 | 17.313 | 7.438 | 71% |
67% May - 2021 |
01- Unit
B/wall Completed, M/Build: F/F upto slab level
Cannot be complted due
to late land handed over |
No Image |
2) GMPS Mirash Pattai PK-91
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.881 | 3 | 9.272 | 9.272 | 9.272 | 4.931 | 7.931 | 13.609 | 47% |
31% April - 2021 |
Roof level slab
Cannot be complted due to late land handed over |
No Image |
2) GMPS Mirash Pattai PK-91
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.881 | 3 | 8.007 | 8.007 | 8.007 | 4.931 | 7.931 | 14.874 | 43% |
31% March - 2021 |
Roof level slab |
No Image |
2) GMPS Mirash Pattai PK-91
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.881 | 3 | 8.007 | 8.007 | 8.007 | 3.101 | 6.101 | 14.874 | 43% |
24% February - 2021 |
Roof level slab |
No Image |
2) GMPS Mirash Pattai PK-91
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.881 | 3 | 8.007 | 8.007 | 8.007 | 3.101 | 6.101 | 14.874 | 43% |
24% January - 2021 |
Roof level slab |
No Image |
2) GMPS Mirash Pattai PK-91
| |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 5 | 5.453 | 5.453 | 5.453 | 1.728 | 6.728 | 3.547 | 75% |
48% December - 2020 |
Funds to the tune of Rs. 8.000 m is required dt..28/08/2020. |
No Image |
GMPS Awal Khan Koroona | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 5 | 5.453 | 5.453 | 5.453 | 1.728 | 6.728 | 3.547 | 75% |
48% December - 2020 |
Funds to the tune of Rs. 8.000 m is required dt..28/08/2020. |
No Image |
GMPS Awal Khan Koroona | |||||||||||||||||||
391 (OG) |
170205-Conversion of 100 Mosque Schools into Primary schools in Khyber Pakhtunkhwa (less 69 units) |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14 | 0 | 5 | 5 | 5 | 1.306 | 1.306 | 9 | 36% |
9% October - 2020 |
Funds to the tune of Rs. 8.000 m is required dt..28/08/2020. |
No Image |
GMPS Awal Khan Koroona | |||||||||||||||||||
391 (OG) |
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2018 |
PC-II for Rs.26.082 m submitted to CPO HE Deptt on 16/11/2015. Purchase of land under process by HE Deptt. PC-I/DCE for Rs.163.367 m submittedto CPO on 25/10/2017 by C&W. Not yet approved. |
No Image |
GDC Boys UC Mandhra/Dhap Shumali | |||||||||||||||||||