Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.27 | 28.484 | 7.379 | 7.379 | 7.379 | 7.379 | 35.863 | 55.407 | 39% |
39% December - 2019 |
2 Units - 1 Main building - roof laid, 1 Main Building - DPC level. B/W in progress. |
No Image |
1) GHS Adnan Sardi Khel PK-72
2) GHS Ghazi PK-72 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.27 | 28.484 | 7.379 | 7.379 | 7.379 | 7.379 | 35.863 | 55.407 | 39% |
39% November - 2019 |
2 Units - 1 Main building - roof laid, 1 Main Building - DPC level. B/W in progress. |
No Image |
1) GHS Adnan Sardi Khel PK-72
2) GHS Ghazi PK-72 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.27 | 28.484 | 7.379 | 7.379 | 7.379 | 3.402 | 31.886 | 55.407 | 39% |
35% October - 2019 |
2 Units - 1 Main building - roof laid, 1 Main Building - DPC level. |
No Image |
1) GHS Adnan Sardi Khel PK-72
2) GHS Ghazi PK-72 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.27 | 28.484 | 0 | 0 | 0 | 0 | 28.484 | 62.786 | - |
31% September - 2019 |
2 Units - 1 Main building - roof laid, 1 Main Building - DPC level. |
No Image |
1) GHS Adnan Sardi Khel PK-72
2) GHS Ghazi PK-72 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.27 | 28.484 | 0 | 0 | 0 | 0 | 28.484 | 62.786 | - |
31% August - 2019 |
2 Units - 1 Main building - roof laid, 1 Main Building - DPC level. |
No Image |
1) GHS Adnan Sardi Khel PK-72
2) GHS Ghazi PK-72 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.27 | 28.484 | 48.005 | 48.005 | 48.005 | 38.004 | 66.488 | 14.781 | 84% |
73% May - 2020 |
2 Units - 1 Main building - roof laid, 1 Main Building - DPC level. B/W in progress. |
No Image |
1) GHS Adnan Sardi Khel PK-72
2) GHS Ghazi PK-72 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.27 | 28.484 | 11.065 | 11.065 | 11.065 | 11.065 | 39.549 | 51.721 | 43% |
43% April - 2020 |
2 Units - 1 Main building - roof laid, 1 Main Building - DPC level. B/W in progress. |
No Image |
1) GHS Adnan Sardi Khel PK-72
2) GHS Ghazi PK-72 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.27 | 28.484 | 11.065 | 11.065 | 11.065 | 11.065 | 39.549 | 51.721 | 43% |
43% March - 2020 |
2 Units - 1 Main building - roof laid, 1 Main Building - DPC level. B/W in progress. |
No Image |
1) GHS Adnan Sardi Khel PK-72
2) GHS Ghazi PK-72 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.27 | 28.484 | 11.065 | 11.065 | 11.065 | 11.065 | 39.549 | 51.721 | 43% |
43% February - 2020 |
2 Units - 1 Main building - roof laid, 1 Main Building - DPC level. B/W in progress. |
No Image |
1) GHS Adnan Sardi Khel PK-72
2) GHS Ghazi PK-72 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.27 | 28.484 | 11.065 | 11.065 | 11.065 | 11.065 | 39.549 | 51.721 | 43% |
43% January - 2020 |
2 Units - 1 Main building - roof laid, 1 Main Building - DPC level. B/W in progress. |
No Image |
1) GHS Adnan Sardi Khel PK-72
2) GHS Ghazi PK-72 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
PC-I/DCE for Rs.46.85 m sumbitted to DEO M on 18/04/2018. |
No Image |
GHS Band Kurai (PK-65) | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
PC-I/DCE for Rs.46.85 m sumbitted to DEO M on 18/04/2018. |
No Image |
GHS Band Kurai (PK-65) | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
PC-I/DCE for Rs.46.85 m sumbitted to DEO M on 18/04/2018. |
No Image |
GHS Band Kurai (PK-65) | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
PC-I/DCE for Rs.46.85 m sumbitted to DEO M on 18/04/2018. |
No Image |
GHS Band Kurai (PK-65) | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
PC-I/DCE for Rs.46.85 m sumbitted to DEO M on 18/04/2018. |
No Image |
GHS Band Kurai (PK-65) | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
PC-I/DCE for Rs.46.85 m sumbitted to DEO M on 18/04/2018. |
No Image |
GHS Band Kurai (PK-65) | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
PC-I/DCE for Rs.46.85 m sumbitted to DEO M on 18/04/2018. |
No Image |
GHS Band Kurai (PK-65) | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
PC-I/DCE for Rs.46.85 m sumbitted to DEO M on 18/04/2018. |
No Image |
GHS Band Kurai (PK-65) | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
PC-I/DCE for Rs.46.85 m sumbitted to DEO M on 18/04/2018. |
No Image |
GHS Band Kurai (PK-65) | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
PC-I/DCE for Rs.46.85 m sumbitted to DEO M on 18/04/2018. |
No Image |
GHS Band Kurai (PK-65) | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.142 | 2.995 | 6.708 | 6.708 | 6.708 | 6.707 | 9.702 | 92.439 | 9% |
9% December - 2019 |
3 units - work order issued. |
No Image |
1) GHS Paito Dara PK-94 2) GHS Makhai PK-95 3) GHs Kad PK-96 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.142 | 2.995 | 6.708 | 6.708 | 6.708 | 6.707 | 9.702 | 92.439 | 9% |
9% November - 2019 |
3 units - work order issued. |
No Image |
1) GHS Paito Dara PK-94 2) GHS Makhai PK-95 3) GHs Kad PK-96 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.142 | 2.995 | 6.708 | 6.708 | 6.708 | 6.708 | 9.703 | 92.439 | 9% |
9% October - 2019 |
3 units - work order issued. |
No Image |
1) GHS Paito Dara PK-94 2) GHS Makhai PK-95 3) GHs Kad PK-96 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.142 | 2.995 | 6.708 | 6.708 | 6.708 | 0 | 2.995 | 92.439 | 9% |
3% September - 2019 |
3 units - work order issued. |
No Image |
1) GHS Paito Dara PK-94 2) GHS Makhai PK-95 3) GHs Kad PK-96 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.142 | 2.995 | 0 | 0 | 0 | 0 | 2.995 | 99.147 | - |
3% August - 2019 |
3 units - work order issued. |
No Image |
1) GHS Paito Dara PK-94 2) GHS Makhai PK-95 3) GHs Kad PK-96 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.142 | 2.995 | 35.35 | 35.35 | 35.35 | 24.654 | 27.649 | 63.797 | 38% |
27% May - 2020 |
3 units - finishing in progress. |
No Image |
1) GHS Paito Dara PK-94 2) GHS Makhai PK-95 3) GHs Kad PK-96 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.142 | 2.995 | 35.35 | 35.35 | 35.35 | 24.654 | 27.649 | 63.797 | 38% |
27% April - 2020 |
3 units - finishing in progress. |
No Image |
1) GHS Paito Dara PK-94 2) GHS Makhai PK-95 3) GHs Kad PK-96 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.142 | 2.995 | 35.35 | 35.35 | 35.35 | 24.654 | 27.649 | 63.797 | 38% |
27% March - 2020 |
3 units - finishing in progress. |
No Image |
1) GHS Paito Dara PK-94 2) GHS Makhai PK-95 3) GHs Kad PK-96 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.142 | 2.995 | 35.35 | 35.35 | 35.35 | 24.654 | 27.649 | 63.797 | 38% |
27% February - 2020 |
3 units - finishing in progress. |
No Image |
1) GHS Paito Dara PK-94 2) GHS Makhai PK-95 3) GHs Kad PK-96 | |||||||||||||||||||
208 (OG) |
170206-Reconstruction of 100 High Schools (B&G) on need basis in Khyber Pakhtunkhwa (less 79 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.142 | 2.995 | 19.353 | 19.353 | 19.353 | 19.353 | 22.348 | 79.794 | 22% |
22% January - 2020 |
3 units - work order issued. |
No Image |
1) GHS Paito Dara PK-94 2) GHS Makhai PK-95 3) GHs Kad PK-96 | |||||||||||||||||||
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.516 | 45.54 | 0 | 0 | 0 | 0 | 45.54 | 0 | - |
100% December - 2020 |
02- Units
Work order issued. |
No Image |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.516 | 45.54 | 0 | 0 | 0 | 0 | 45.54 | 0 | - |
100% December - 2020 |
02- Units
Work order issued. |
No Image |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.516 | 45.54 | 0 | 0 | 0 | 0 | 45.54 | 0 | - |
100% October - 2020 |
02- Units
Work order issued. |
No Image |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.516 | 45.54 | 0 | 0 | 0 | 0 | 45.54 | 0 | - |
100% September - 2020 |
02- Units
Work order issued. |
No Image |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.516 | 45.54 | 0 | 0 | 0 | 0 | 45.54 | 0 | - |
100% August - 2020 |
02- Units
Tender under process. |
No Image |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 227.451 | 45.54 | 20.362 | 0 | 0 | 0 | 45.54 | 0 |
July - 2020 |
No Image | ||
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.516 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
May - 2021 |
02- Units
1 Completed upto lintel level
2 Foundation in progress |
No Image |
1 Division Office Bittani Wazir at Bannu
2 Residentail Accomodation for SE (S) & Divisional Office Wazir Bittani | |||||||||||||||||||
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.516 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
April - 2021 |
02- Units
1 Completed upto lintel level
2 Foundation in progress |
No Image |
1 Division Office Bittani Wazir at Bannu
2 Residentail Accomodation for SE (S) & Divisional Office Wazir Bittani | |||||||||||||||||||
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.516 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
March - 2021 |
02- Units
1 Completed upto lintel level
2 Foundation in progress |
No Image |
1 Division Office Bittani Wazir at Bannu
2 Residentail Accomodation for SE (S) & Divisional Office Wazir Bittani | |||||||||||||||||||
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.516 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
February - 2021 |
02- Units
1 Completed upto lintel level
2 Foundation in progress |
No Image |
1 Division Office Bittani Wazir at Bannu
2 Residentail Accomodation for SE (S) & Divisional Office Wazir Bittani | |||||||||||||||||||
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.516 | 45.54 | 0 | 0 | 0 | 0 | 45.54 | 0 | - |
100% January - 2021 |
02- Units
Work order issued. |
No Image |
1 Division Office Bittani Wazir at Bannu
2 Residentail Accomodation for SE (S) & Divisional Office Wazir Bittani | |||||||||||||||||||
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.332 | 2.492 | 0 | 0 | 0 | 0 | 2.492 | 4.84 | - |
34% December - 2020 |
04- Units
1 to 3 in progress & S.No.4 completed. |
No Image |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.332 | 2.492 | 0 | 0 | 0 | 0 | 2.492 | 4.84 | - |
34% December - 2020 |
04- Units
1 to 3 in progress & S.No.4 completed. |
No Image |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.332 | 2.492 | 0 | 0 | 0 | 0 | 2.492 | 4.84 | - |
34% October - 2020 |
04- Units
1 to 3 in progress & S.No.4 completed. |
No Image |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.332 | 2.492 | 0 | 0 | 0 | 0 | 2.492 | 4.84 | - |
34% September - 2020 |
04- Units
1 to 3 in progress & S.No.4 completed. |
No Image |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.332 | 2.492 | 0 | 0 | 0 | 0 | 2.492 | 4.84 | - |
34% August - 2020 |
04- Units
1 to 3 in progress & S.No.4 completed. |
No Image |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.332 | 2.492 | 20.362 | 0 | 0 | 0 | 2.492 | 0 | 100% |
34% July - 2020 |
No Image | |
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.332 | 2.492 | 0 | 0 | 0 | 0 | 2.492 | 4.84 | - |
34% May - 2021 |
04- Units
1 to 3 in progress & S.No.4 completed. |
No Image |
1 A.C Darzinda House
2 C&W Rest House near Aman Mela Check Post
3 Adminstraton Rest House Khoi Bahara
4 SDO C&W HOuse | |||||||||||||||||||
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.332 | 2.492 | 0 | 0 | 0 | 0 | 2.492 | 4.84 | - |
34% April - 2021 |
04- Units
1 to 3 in progress & S.No.4 completed. |
No Image |
1 A.C Darzinda House
2 C&W Rest House near Aman Mela Check Post
3 Adminstraton Rest House Khoi Bahara
4 SDO C&W HOuse | |||||||||||||||||||
208 (OG) |
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA] |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.332 | 2.492 | 0 | 0 | 0 | 0 | 2.492 | 4.84 | - |
34% March - 2021 |
04- Units
1 to 3 in progress & S.No.4 completed. |
No Image |
1 A.C Darzinda House
2 C&W Rest House near Aman Mela Check Post
3 Adminstraton Rest House Khoi Bahara
4 SDO C&W HOuse | |||||||||||||||||||