Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.6 | 18 | 0 | 0 | 0 | 0 | 18 | 2.6 | - |
87% September - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundian PK-46 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.6 | 18 | 0 | 0 | 0 | 0 | 18 | 2.6 | - |
87% July - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundian PK-46 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.264 | 17.367 | 0 | 0 | 0 | 0 | 17.367 | 1.897 | - |
90% September - 2018 |
Out of 2 units, 1 completed, 1 in progress. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Tughel Khel PK-73 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.264 | 17.367 | 0 | 0 | 0 | 0 | 17.367 | 1.897 | - |
90% July - 2018 |
Out of 2 units, 1 completed, 1 in progress. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Tughel Khel PK-73 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2018 |
PC-I/DCE for Rs.9.430 m on MRS-2017 submitted to DEO M on 09/04/2018. |
No Image |
GHSS Thakot | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2018 |
PC-I/DCE for Rs.9.430 m on MRS-2017 submitted to DEO M on 09/04/2018. |
No Image |
GHSS Thakot | |||||||||||||||||||
182 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 0 | 30 | 30 | 7.5 | 0 | 0 | 63.712 | 32% |
- December - 2019 |
Work order issued.
Demoilition completed. |
No Image |
182 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 0 | 30 | 30 | 7.5 | 0 | 0 | 63.712 | 32% |
- November - 2019 |
Work order issued.
Demoilition completed. |
No Image |
182 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 0 | 30 | 30 | 7.5 | 0 | 0 | 63.712 | 32% |
- October - 2019 |
Work order issued.
Demoilition completed. |
No Image |
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.8 | 34.006 | 0 | 0 | 0 | 0 | 34.006 | 2.794 | - |
92% September - 2018 |
Completed (4 units). |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
182 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 0 | 30 | 30 | 7.5 | 0 | 0 | 63.712 | 32% |
- September - 2019 |
Work order issued. Site owkr handed over. |
No Image |
182 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 0 | 30 | 30 | 0 | 0 | 0 | 63.712 | 32% |
- August - 2019 |
Work order issued. Site owkr handed over. |
No Image |
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.8 | 34.006 | 0 | 0 | 0 | 0 | 34.006 | 2.794 | - |
92% July - 2018 |
Completed (4 units). |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
182 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 0 | 30 | 30 | 7.5 | 6.461 | 6.461 | 63.712 | 32% |
7% May - 2020 |
Foundation in progress. |
No Image |
182 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 0 | 30 | 30 | 7.5 | 6.461 | 6.461 | 63.712 | 32% |
7% April - 2020 |
Foundation in progress. |
No Image |
182 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 0 | 30 | 30 | 7.5 | 6.461 | 6.461 | 63.712 | 32% |
7% March - 2020 |
Foundation in progress. |
No Image |
182 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 0 | 30 | 30 | 7.5 | 6.461 | 6.461 | 63.712 | 32% |
7% February - 2020 |
Foundation in progress. |
No Image |
182 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 0 | 30 | 30 | 7.5 | 1.536 | 1.536 | 63.712 | 32% |
2% January - 2020 |
Foundation in progress. |
No Image |
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 13.124 | 13.656 | 0 | 0 | 0 | 0 | 13.656 | 0 | - |
100% September - 2018 |
2 units - finishing in progress. |
No Image |
1) GHS Garum Chashma
2) GGHS Warijun | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 13.124 | 13.656 | 0 | 0 | 0 | 0 | 13.656 | 0 | - |
100% July - 2018 |
2 units - finishing in progress. |
No Image |
1) GHS Garum Chashma
2) GGHS Warijun | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.914 | 8.146 | 0 | 0 | 0 | 0 | 8.146 | 0.768 | - |
91% September - 2018 |
Completed & H/O (1 unit). |
No Image |
1) GGHSS No.9 Din Pur PK-64 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.914 | 8.146 | 0 | 0 | 0 | 0 | 8.146 | 0.768 | - |
91% July - 2018 |
Completed & H/O (1 unit). |
No Image |
1) GGHSS No.9 Din Pur PK-64 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.4 | 13.484 | 0 | 0 | 0 | 0 | 13.484 | 3.916 | - |
77% September - 2018 |
Out of 2 units, 1 completed, 1 in progress. |
No Image |
1) GGHS Damtai PK-95
2) GGHS Zaimdara shifted to GHS Bandai PK-96 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.4 | 13.484 | 0 | 0 | 0 | 0 | 13.484 | 3.916 | - |
77% July - 2018 |
Out of 2 units, 1 completed, 1 in progress. |
No Image |
1) GGHS Damtai PK-95
2) GGHS Zaimdara shifted to GHS Bandai PK-96 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.5 | 34.562 | 0 | 0 | 0 | 0 | 34.562 | 8.938 | - |
79% September - 2018 |
5 units:
S# 1&2: Completed.
S# 3: Roof level
S# 4: DPC completed
S# 5: Finishing in progress. |
No Image |
1) GHSS Gandigar PK-91
2) GHS Sheringal PK-92
3) GGHS Wari PK-93
4) GGHSS Barawal PK-91
5) GGMHS Kass Dir PK-91 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.5 | 34.562 | 0 | 0 | 0 | 0 | 34.562 | 8.938 | - |
79% July - 2018 |
5 units:
S# 1&2: Completed.
S# 3: Roof level
S# 4: DPC completed
S# 5: Finishing in progress. |
No Image |
1) GHSS Gandigar PK-91
2) GHS Sheringal PK-92
3) GGHS Wari PK-93
4) GGHSS Barawal PK-91
5) GGMHS Kass Dir PK-91 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.936 | 14.025 | 0 | 0 | 0 | 0 | 14.025 | 3.911 | - |
78% September - 2018 |
GHS Muhammad Khawaja PK-42 - roof laid. GHSS Dallan PK-43 - in progress. |
No Image |
1) GHS Muhammad Khawaja PK-42
2) GHSS Dallan PK-43 shifted to Mianji Khel | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.936 | 14.025 | 0 | 0 | 0 | 0 | 14.025 | 3.911 | - |
78% July - 2018 |
GHS Muhammad Khawaja PK-42 - roof laid. GHSS Dallan PK-43 - in progress. |
No Image |
1) GHS Muhammad Khawaja PK-42
2) GHSS Dallan PK-43 shifted to Mianji Khel | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 95.702 | 49.986 | 0 | 0 | 0 | 0 | 49.986 | 45.716 | - |
52% September - 2018 |
Out of 8 units, 1 completed, 7 in progress. |
No Image |
1) GHS Khanpur PK-49
2) GHS Halli shifted to GHS Jabri PK-49
3) GHS Laban Bandi PK-50
4) GHS Nurdi PK-50
5) GHS KTS Sector No.2 PK-51
6) GHS Kundi PK-52
7) GHS Ghazi Hamlet PK-52
8) GHS Rehana PK-50
9) GHS Darwesh PK-50 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 95.702 | 49.986 | 0 | 0 | 0 | 0 | 49.986 | 45.716 | - |
52% July - 2018 |
Out of 8 units, 1 completed, 7 in progress. |
No Image |
1) GHS Khanpur PK-49
2) GHS Halli shifted to GHS Jabri PK-49
3) GHS Laban Bandi PK-50
4) GHS Nurdi PK-50
5) GHS KTS Sector No.2 PK-51
6) GHS Kundi PK-52
7) GHS Ghazi Hamlet PK-52
8) GHS Rehana PK-50
9) GHS Darwesh PK-50 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 56.658 | 46.794 | 0 | 0 | 0 | 0 | 46.794 | 9.864 | - |
83% September - 2018 |
Out of 6 units, 5 completed, 1 in progress. |
No Image |
1) GHS Ghundi Killa
2) GHS Khojaki Killa (shifted to GHS Paloski)
3) GHS Town Committee PK-40
4) GHS Sabir Abad PK-40
5) GHS Zarki Nasratti
6) GHS Kohjaki Killa | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 56.658 | 46.794 | 0 | 0 | 0 | 0 | 46.794 | 9.864 | - |
83% July - 2018 |
Out of 6 units, 5 completed, 1 in progress. |
No Image |
1) GHS Ghundi Killa
2) GHS Khojaki Killa (shifted to GHS Paloski)
3) GHS Town Committee PK-40
4) GHS Sabir Abad PK-40
5) GHS Zarki Nasratti
6) GHS Kohjaki Killa | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.591 | 10.33 | 1.659 | 1.659 | 1.659 | 0 | 10.33 | 0.602 | 95% |
82% September - 2018 |
Finishing in progress. |
No Image |
GGHSS Behzadi Chiker Kot PK-38 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.591 | 10.33 | 0 | 0 | 0 | 0 | 10.33 | 2.261 | - |
82% July - 2018 |
Finishing in progress. |
No Image |
GGHSS Behzadi Chiker Kot PK-38 | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 17.641 | 0 | 0 | 0 | 0 | 17.641 | 24.834 | - |
42% December - 2020 |
Plaster progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 17.641 | 0 | 0 | 0 | 0 | 17.641 | 24.834 | - |
42% December - 2020 |
Plaster progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 0 | 0 | 0 | 0 | 17.641 | 17.641 | 42.475 | - |
42% October - 2020 |
Plaster progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 0 | 0 | 0 | 0 | 17.641 | 17.641 | 42.475 | - |
42% September - 2020 |
Plaster progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Buildin | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 0 | 0 | 0 | 0 | 0 | 0 | 42.475 | - |
- August - 2020 |
Plaster progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Buildin | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 0 | 0 | 0 | 0 | 0 | 0 | 42.475 | - |
- July - 2020 |
Super Structure in progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Buildin | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 17.641 | 0 | 0 | 0 | 0 | 17.641 | 24.834 | - |
42% May - 2021 |
Plaster progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 17.641 | 0 | 0 | 0 | 0 | 17.641 | 24.834 | - |
42% April - 2021 |
Plaster progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 17.641 | 0 | 0 | 0 | 0 | 17.641 | 24.834 | - |
42% March - 2021 |
Plaster progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 17.641 | 0 | 0 | 0 | 0 | 17.641 | 24.834 | - |
42% February - 2021 |
Plaster progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building | |||||||||||||||||||
182 (OG) |
160499-Provision for Rehabilitation of Disaster Affected Government Buildings |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.475 | 17.641 | 0 | 0 | 0 | 0 | 17.641 | 24.834 | - |
42% January - 2021 |
Plaster progress.
Roofing in progress. |
No Image |
Construction of the Sereatriat Tehsil Building | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 52.2 | 51.647 | 0 | 0 | 0 | 0 | 51.647 | 0.553 | - |
99% September - 2018 |
Out of 6 units, 3 completed, 3 in progress. |
No Image |
1) GHS Masha Mansoor PK-75
2) GGHS Taja Zai PK-75 shifted to GHS Azghar Khel PK-75
3) GHSS Taja Zai PK-75
4) GGHS Khoidad Khel PK-76
5) GHS Ahmad Khel PK-76
6) GHSS Landiwah PK-76 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 52.2 | 51.647 | 0 | 0 | 0 | 0 | 51.647 | 0.553 | - |
99% July - 2018 |
Out of 6 units, 3 completed, 3 in progress. |
No Image |
1) GHS Masha Mansoor PK-75
2) GGHS Taja Zai PK-75 shifted to GHS Azghar Khel PK-75
3) GHSS Taja Zai PK-75
4) GGHS Khoidad Khel PK-76
5) GHS Ahmad Khel PK-76
6) GHSS Landiwah PK-76 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.062 | 44.397 | 0 | 0 | 0 | 0 | 44.397 | 14.665 | - |
75% September - 2018 |
Out of 6 units, 3 completed, 3 in progress. |
No Image |
1) GHS No.1 Dargai PK-98
2) GCMHS Thana PK-99
3) GHS Khar PK-99
4) GHS Pir Khel PK-99
5) GHS College Colony Thana PK-99
6) GCMHS Batkhela PK-99 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.062 | 44.397 | 0 | 0 | 0 | 0 | 44.397 | 14.665 | - |
75% July - 2018 |
Out of 6 units, 3 completed, 3 in progress. |
No Image |
1) GHS No.1 Dargai PK-98
2) GCMHS Thana PK-99
3) GHS Khar PK-99
4) GHS Pir Khel PK-99
5) GHS College Colony Thana PK-99
6) GCMHS Batkhela PK-99 | |||||||||||||||||||
182 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48 | 20.777 | 0 | 0 | 0 | 0 | 20.777 | 27.223 | - |
43% September - 2018 |
Out of 5 units, 4 in progress, 1 site not H/O (GGHS Phulra PK-57). |
No Image |
1) GGHS No.1 Mansehra PK-53
2) GHS Talhatta PK-54
3) GHS Gandian PK-55
4) GHS Kolika shifted to GHS Shamdara PK-56
5) GGHS Phulra PK-57
6) GCMS Dadar PK-56
7) GHS Chitta Batta PK-53 | |||||||||||||||||||
Pages : 1 2 |