Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 60.388 | 1.781 | 1.781 | 1.781 | 1.781 | 62.169 | 11.831 | 84% |
84% December - 2018 |
Out of 5 units, 4 completed, 1 in progress. |
No Image |
1) GPS Fathe Bandi PK-46
2) GPS Garang PK-45
3) GGPS Tanaki UC Langra PK-47
4) GGPS Guddi PK-44
5) GGPS Bhurangala PK-48 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 60.388 | 1.781 | 1.781 | 1.781 | 1.781 | 62.169 | 11.831 | 84% |
84% November - 2018 |
Out of 5 units, 4 completed, 1 in progress. |
No Image |
1) GPS Fathe Bandi PK-46
2) GPS Garang PK-45
3) GGPS Tanaki UC Langra PK-47
4) GGPS Guddi PK-44
5) GGPS Bhurangala PK-48 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 60.388 | 1.781 | 1.781 | 1.781 | 1.781 | 62.169 | 11.831 | 84% |
84% November - 2018 |
Out of 5 units, 4 completed, 1 in progress. |
No Image |
1) GPS Fathe Bandi PK-46
2) GPS Garang PK-45
3) GGPS Tanaki UC Langra PK-47
4) GGPS Guddi PK-44
5) GGPS Bhurangala PK-48 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- October - 2020 |
SDC Abbottabad- Complted
SDC Havelian -MB plinth beam in progress. |
No Image |
1) SDC abbottabad
2) SDC Havalian | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- September - 2020 |
SDC Abbottabad- Complted
SDC Havelian -MB plinth beam in progress. |
No Image |
1) SDC abbottabad
2) SDC | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- August - 2020 |
SDC Abbottabad- Complted
SDC Havelian - land Pay |
No Image |
1) SDC abbottabad
2) SDC | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- July - 2020 |
SDC Abbottabad- Complted
SDC Havelian - land Pay |
No Image |
1) SDC abbottabad
2) SDC | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.089 | 5.541 | 14.5 | 14.5 | 14.5 | 9.5 | 15.041 | 10.048 | 67% |
50% May - 2021 |
02- Units
1. Complted
2. 1st roof level |
No Image |
1) SDC abbottabad
2) SDC Havalian | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 60.388 | 10.897 | 10.897 | 10.897 | 1.781 | 62.169 | 2.715 | 96% |
84% April - 2019 |
Out of 5 units, 4 completed, 1 in progress. |
No Image |
1) GPS Fathe Bandi PK-46
2) GPS Garang PK-45
3) GGPS Tanaki UC Langra PK-47
4) GGPS Guddi PK-44
5) GGPS Bhurangala PK-48 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.089 | 5.541 | 9.5 | 9.5 | 9.5 | 9.5 | 15.041 | 15.048 | 50% |
50% April - 2021 |
02 units
1 Complted
2 1st roof level |
No Image |
1) SDC abbottabad
2) SDC Havalian | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 60.388 | 10.897 | 10.897 | 10.897 | 1.781 | 62.169 | 2.715 | 96% |
84% March - 2019 |
Out of 5 units, 4 completed, 1 in progress. |
No Image |
1) GPS Fathe Bandi PK-46
2) GPS Garang PK-45
3) GGPS Tanaki UC Langra PK-47
4) GGPS Guddi PK-44
5) GGPS Bhurangala PK-48 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 60.388 | 10.897 | 10.897 | 10.897 | 1.781 | 62.169 | 2.715 | 96% |
84% March - 2019 |
Out of 5 units, 4 completed, 1 in progress. |
No Image |
1) GPS Fathe Bandi PK-46
2) GPS Garang PK-45
3) GGPS Tanaki UC Langra PK-47
4) GGPS Guddi PK-44
5) GGPS Bhurangala PK-48 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.089 | 5.541 | 9.5 | 9.5 | 9.5 | 9.5 | 15.041 | 15.048 | 50% |
50% March - 2021 |
02 units
1 Complted
2 1st roof level |
No Image |
1) SDC abbottabad
2) SDC Havalian | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 60.388 | 10.897 | 10.897 | 10.897 | 1.781 | 62.169 | 2.715 | 96% |
84% February - 2019 |
Out of 5 units, 4 completed, 1 in progress. |
No Image |
1) GPS Fathe Bandi PK-46
2) GPS Garang PK-45
3) GGPS Tanaki UC Langra PK-47
4) GGPS Guddi PK-44
5) GGPS Bhurangala PK-48 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.089 | 5.541 | 9.5 | 9.5 | 9.5 | 9.5 | 15.041 | 15.048 | 50% |
50% February - 2021 |
02 units
1 Complted
2 1st roof level |
No Image |
1) SDC abbottabad
2) SDC Havalian | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 60.388 | 1.781 | 1.781 | 1.781 | 1.781 | 62.169 | 11.831 | 84% |
84% January - 2019 |
Out of 5 units, 4 completed, 1 in progress. |
No Image |
1) GPS Fathe Bandi PK-46
2) GPS Garang PK-45
3) GGPS Tanaki UC Langra PK-47
4) GGPS Guddi PK-44
5) GGPS Bhurangala PK-48 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.089 | 5.541 | 4.5 | 4.5 | 4.5 | 4.5 | 10.041 | 20.048 | 33% |
33% January - 2021 |
SDC Abbottabad- Complted
SDC Havelian -MB plinth beam in progress. |
No Image |
1) SDC abbottabad
2) SDC Havalian | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.295 | 48.835 | 1.467 | 1.467 | 1.467 | 0.874 | 49.709 | 2.993 | 94% |
93% December - 2018 |
Completed (4 units). |
No Image |
1) GGPS Shaukat Ayaz Khan Naseer Fateh Khel PK-73
2) GGPS Narmi Khel Musa Khel PK-72
3) GGPS Kotka Sarwar Waligai Jamal PK-71
4) GGPS Sokari PK-70 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.295 | 48.835 | 1.467 | 1.467 | 1.467 | 0.368 | 49.203 | 2.993 | 94% |
92% November - 2018 |
Completed (4 units). |
No Image |
1) GGPS Shaukat Ayaz Khan Naseer Fateh Khel PK-73
2) GGPS Narmi Khel Musa Khel PK-72
3) GGPS Kotka Sarwar Waligai Jamal PK-71
4) GGPS Sokari PK-70 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.295 | 48.835 | 1.467 | 1.467 | 1.467 | 0.368 | 49.203 | 2.993 | 94% |
92% November - 2018 |
Completed (4 units). |
No Image |
1) GGPS Shaukat Ayaz Khan Naseer Fateh Khel PK-73
2) GGPS Narmi Khel Musa Khel PK-72
3) GGPS Kotka Sarwar Waligai Jamal PK-71
4) GGPS Sokari PK-70 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 1 | 1 | 1 | 1 | 1 | 35.677 | 3% |
3% October - 2020 |
Foundation complted
DPC and Boundary wall in progress. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 1 | 1 | 1 | 1 | 1 | 35.677 | 3% |
3% September - 2020 |
Foundation complted
DPC and Boundary wall in progress. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 1 | 1 | 1 | 1 | 1 | 35.677 | 3% |
3% August - 2020 |
Foundation complted
DPC and Boundary wall in progress. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- July - 2020 |
1 units, Bannu - demolition icompleted . Work star |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 6.057 | 10.71 | 10.71 | 10.71 | 10.71 | 16.767 | 19.91 | 46% |
46% May - 2021 |
Roof laid and Main Gate in progress |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.295 | 48.835 | 6.467 | 6.467 | 6.467 | 1.239 | 50.074 | 0 | 100% |
94% April - 2019 |
Completed (4 units). |
No Image |
1) GGPS Shaukat Ayaz Khan Naseer Fateh Khel PK-73
2) GGPS Narmi Khel Musa Khel PK-72
3) GGPS Kotka Sarwar Waligai Jamal PK-71
4) GGPS Sokari PK-70 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 6.057 | 10.71 | 10.71 | 10.71 | 10.71 | 16.767 | 19.91 | 46% |
46% April - 2021 |
Roofing in progress |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.295 | 48.835 | 2.061 | 2.061 | 2.061 | 1.239 | 50.074 | 2.399 | 95% |
94% March - 2019 |
Completed (4 units). |
No Image |
1) GGPS Shaukat Ayaz Khan Naseer Fateh Khel PK-73
2) GGPS Narmi Khel Musa Khel PK-72
3) GGPS Kotka Sarwar Waligai Jamal PK-71
4) GGPS Sokari PK-70 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.295 | 48.835 | 2.061 | 2.061 | 2.061 | 1.239 | 50.074 | 2.399 | 95% |
94% March - 2019 |
Completed (4 units). |
No Image |
1) GGPS Shaukat Ayaz Khan Naseer Fateh Khel PK-73
2) GGPS Narmi Khel Musa Khel PK-72
3) GGPS Kotka Sarwar Waligai Jamal PK-71
4) GGPS Sokari PK-70 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 6.057 | 10.71 | 10.71 | 10.71 | 7.992 | 14.049 | 19.91 | 46% |
38% March - 2021 |
Roofing in progress |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.295 | 48.835 | 2.061 | 2.061 | 2.061 | 1.239 | 50.074 | 2.399 | 95% |
94% February - 2019 |
Completed (4 units). |
No Image |
1) GGPS Shaukat Ayaz Khan Naseer Fateh Khel PK-73
2) GGPS Narmi Khel Musa Khel PK-72
3) GGPS Kotka Sarwar Waligai Jamal PK-71
4) GGPS Sokari PK-70 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 6.057 | 7.6 | 7.6 | 7.6 | 7.6 | 13.657 | 23.02 | 37% |
37% February - 2021 |
Roofing in progress |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.295 | 48.835 | 2.061 | 2.061 | 2.061 | 1.239 | 50.074 | 2.399 | 95% |
94% January - 2019 |
Completed (4 units). |
No Image |
1) GGPS Shaukat Ayaz Khan Naseer Fateh Khel PK-73
2) GGPS Narmi Khel Musa Khel PK-72
3) GGPS Kotka Sarwar Waligai Jamal PK-71
4) GGPS Sokari PK-70 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 6.057 | 4 | 4 | 4 | 4 | 10.057 | 26.62 | 27% |
27% January - 2021 |
Foundation complted
DPC and Boundary wall in progress. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 27.677 | 0.323 | 0.323 | 0.323 | 0 | 27.677 | 0 | 100% |
99% December - 2018 |
Completed & H/O (2 units). |
No Image |
1) GPS Rakban PK-59
2) GPS Sokar Zojan PK-60 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 27.677 | 0 | 0 | 0 | 0 | 27.677 | 0.323 | - |
99% November - 2018 |
Completed & H/O (2 units). |
No Image |
1) GPS Rakban PK-59
2) GPS Sokar Zojan PK-60 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 27.677 | 0 | 0 | 0 | 0 | 27.677 | 0.323 | - |
99% November - 2018 |
Completed & H/O (2 units). |
No Image |
1) GPS Rakban PK-59
2) GPS Sokar Zojan PK-60 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 1.4 | 1.4 | 1.4 | 1.4 | 1.4 | 29.731 | 4% |
4% October - 2020 |
2 units,
Battagram - Deffered
Allai - Work order issued. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai | |||||||||||||||||||
171 (OG) |
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.387 | 47.96 | 0 | 0 | 0 | 0 | 47.96 | 136.427 | - |
26% September - 2018 |
Main building - SS in progress. BW 80% completed. |
No Image |
Construction of Model School at Moza Chappergram, Battagram | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 1.4 | 1.4 | 1.4 | 1.4 | 1.4 | 29.731 | 4% |
4% September - 2020 |
2 units,
Battagram - Deffered
Allai - Work order issued. |
No Image |
1) Tehsil Battagram PK-59
2) Te | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 0 | 0 | 0 | 0 | 0 | 31.131 | - |
- August - 2020 |
2 units,
Battagram - Deffered
Allai - Work order issued. |
No Image |
1) Tehsil Battagram PK-59
2) Te | |||||||||||||||||||
171 (OG) |
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.387 | 47.96 | 0 | 0 | 0 | 0 | 47.96 | 136.427 | - |
26% July - 2018 |
Main building - SS in progress. BW 80% completed. |
No Image |
Construction of Model School at Moza Chappergram, Battagram | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 0 | 0 | 0 | 0 | 0 | 31.131 | - |
- July - 2020 |
2 units,
Battagram - Deffered
Allai - Work orde |
No Image |
1) Tehsil Battagram PK-59
2) Te | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 5.295 | 7.4 | 7.4 | 7.4 | 7.144 | 12.439 | 18.436 | 41% |
40% May - 2021 |
02- Units
1. Battagram - Deffered
2. Super Strcuture in progress |
No Image |
1) Tehsil Battagram PK-59 .?. Rs: 44.404
2) Tehsil Allai .?. Rs: 31.231
Scope of work:
| |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 27.677 | 0 | 0 | 0 | 0 | 27.677 | 0.323 | - |
99% April - 2019 |
Completed & H/O (2 units). |
No Image |
1) GPS Rakban PK-59
2) GPS Sokar Zojan PK-60 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 5.295 | 7.4 | 7.4 | 7.4 | 7.144 | 12.439 | 18.436 | 41% |
40% April - 2021 |
2 units - 01 in porgress
1 Battagram - Deffered
2 Super Strcuture in progress |
No Image |
1) Tehsil Battagram PK-59 .?. Rs: 44.404
2) Tehsil Allai .?. Rs: 31.231 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 27.677 | 0.323 | 0.323 | 0.323 | 0 | 27.677 | 0 | 100% |
99% March - 2019 |
Completed & H/O (2 units). |
No Image |
1) GPS Rakban PK-59
2) GPS Sokar Zojan PK-60 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 27.677 | 0.323 | 0.323 | 0.323 | 0 | 27.677 | 0 | 100% |
99% March - 2019 |
Completed & H/O (2 units). |
No Image |
1) GPS Rakban PK-59
2) GPS Sokar Zojan PK-60 | |||||||||||||||||||
171 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 5.295 | 7.4 | 7.4 | 7.4 | 7.144 | 12.439 | 18.436 | 41% |
40% March - 2021 |
2 units - 01 in porgress
1 Battagram - Deffered
2 Super Strcuture in progress |
No Image |
1) Tehsil Battagram PK-59 .?. Rs: 44.404
2) Tehsil Allai .?. Rs: 31.231 | |||||||||||||||||||
171 (OG) |
130334-Establishment of 100 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-III). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 27.677 | 0.323 | 0.323 | 0.323 | 0 | 27.677 | 0 | 100% |
99% February - 2019 |
Completed & H/O (2 units). |
No Image |
1) GPS Rakban PK-59
2) GPS Sokar Zojan PK-60 | |||||||||||||||||||
Pages : 1 2 3 4 5 6 7 8 9 |