Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2020, September - 2017, October - 2020, October - 2017, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
- - - 18-07-17 - 50 0 5 5 1.25 0 0 45 10% -
December - 2017
Tender approval under process.
No Image
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
- - - 18-07-17 - 50 0 5 5 0 0 0 45 10% -
September - 2017
Pre-qualification under process.
No Image
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
- - - 18-07-17 - 50 0 5 5 0 0 0 45 10% -
August - 2017
Procurement under process.
No Image
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
- - - - Line Deptt 50 0 5 5 0 0 0 45 10% -
July - 2017
PC-I for Rs.50 m approved.
No Image
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 0 5 5 1.25 0 0 45 10% -
November - 2017
Tender under process.
No Image
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 0 5 5 0 0 0 45 10% -
October - 2017
Tender under process.
No Image
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 0 5 5 5 5 5 45 10% 10%
June - 2018
Length 5 Km (width 18 ft) - earth work in progress.
No Image
Mansehra
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 0 5 5 5 5 5 45 10% 10%
May - 2018
Length 5 Km (width 18 ft) - earth work in progress.
No Image
Mansehra
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 0 5 5 5 5 5 45 10% 10%
April - 2018
Length 5 Km (width 18 ft) - earth work in progress.
No Image
Mansehra
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 0 5 5 5 5 5 45 10% 10%
March - 2018
Length 5 Km (width 18 ft) - earth work in progress.
No Image
Mansehra
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 0 5 5 1.25 1.25 1.25 45 10% 3%
February - 2018
Length 5 km ( width 18 ft) Earth work in progress.
No Image
Mansehra
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 0 5 5 1.25 1.25 1.25 45 10% 3%
January - 2018
Work started.
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 17.099 0 0 38.499 0 - -
December - 2020
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 17.099 0 0 38.499 0 - -
December - 2020
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 17.099 0 0 38.499 0 - -
October - 2020
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 17.099 0 0 38.499 0 - -
September - 2020
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 17.099 0 0 38.499 0 - -
August - 2020
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 0 0 0 38.499 0
July - 2020
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 17.099 0 0 38.499 0 - -
May - 2021
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 17.099 0 0 38.499 0 - -
April - 2021
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 17.099 0 0 38.499 0 - -
March - 2021
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 17.099 0 0 38.499 0 - -
February - 2021
No Image
1254
(OG)
191624-150293-Execution of Rural Works in FR Peshawar (Low Cost DWSS & Sanitation) [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 55.598 38.499 17.099 17.099 0 0 38.499 0 - -
January - 2021
No Image