Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1253 (New) |
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra. |
Mansehra |
- | - | - | 01-11-17 | - | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
Approved in PDWP on 02/11/2017 for Rs.71 m. AA awaited. |
No Image |
1253 (New) |
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra. |
Mansehra |
- | - | - | - | Line Deptt | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-I/DCE against revised CMD under progress. |
No Image |
1253 (New) |
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra. |
Mansehra |
- | - | - | - | Line Deptt | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-I/DCE for Rs.71.290 m submitted to Chief Infra P&D on 31/07/2017. Pre-PDWP held. |
No Image |
1253 (New) |
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra. |
Mansehra |
- | - | - | - | Line Deptt | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
PC-I/DCE for Rs.71.290 m submitted to Chief Infra P&D on 31/07/2017. Pre-PDWP held. |
No Image |
1253 (New) |
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
Approved in PDWP on 01/11/2017 for Rs.71 m. AA awaited. |
No Image |
1253 (New) |
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
Approved in PDWP on 01/11/2017 for Rs.71 m. AA awaited. |
No Image |
1253 (New) |
170565-Construction/Black Topping of road (a) Dehgri to Moharr UC Sawan Maira (1 Km), (b) Ghazi Kot to Chameri UC Nika Pani (1 Km), (c) Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal UC Pharinha (1 Km) and (e) Saira to Darband UC Shanaya (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.292 | 0 | 5 | 0 | 0 | 0 | 0 | 66.292 | 7% |
- June - 2018 |
Tender Approval in process. |
No Image |
Mansehra | |||||||||||||||||||
1253 (New) |
170565-Construction/Black Topping of road (a) Dehgri to Moharr UC Sawan Maira (1 Km), (b) Ghazi Kot to Chameri UC Nika Pani (1 Km), (c) Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal UC Pharinha (1 Km) and (e) Saira to Darband UC Shanaya (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.292 | 0 | 5 | 5 | 0 | 0 | 0 | 66.292 | 7% |
- May - 2018 |
Approved. |
No Image |
Mansehra | |||||||||||||||||||
1253 (New) |
170565-Construction/Black Topping of road (a) Dehgri to Moharr UC Sawan Maira (1 Km), (b) Ghazi Kot to Chameri UC Nika Pani (1 Km), (c) Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal UC Pharinha (1 Km) and (e) Saira to Darband UC Shanaya (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
Approved in PDWP on 02/11/2017 for Rs.71 m. AA awaited. Summary for inclusion of additional 10 components from savings (Rs.150 m ADP cost) submitted to CA. |
No Image |
Mansehra | |||||||||||||||||||
1253 (New) |
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
Approved in PDWP on 02/11/2017 for Rs.71 m. AA awaited. Summary for inclusion of additional 10 components from savings (Rs.150 m ADP cost) submitted to CA. |
No Image |
Mansehra | |||||||||||||||||||
1253 (New) |
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
Approved in PDWP on 02/11/2017 for Rs.71 m. AA awaited.
Summary for inclusion of additioanl 10 components from savings (150 M ADP cost) submitted to CA. |
No Image |
Mansehra | |||||||||||||||||||
1253 (New) |
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
Approved in PDWP on 02/11/2017 for Rs.71 m. AA awaited. |
No Image |
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 9.218 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 9.218 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 9.218 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 9.218 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 9.218 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 9.218 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 9.218 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 9.218 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 9.218 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1253 (OG) |
191605-180524 - Execution of Rural Works Program in Sub-Division Peshawar. [MA] |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.218 | 0 | 9.218 | 9.218 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |