Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 0 0 0 13 0
July - 2020
No Image
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
- - - 15-09-17 - 174.85 0 20 15 0 0 0 154.85 11% -
December - 2017
Tender approval under process.
No Image
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
- - - - Line Deptt 160 0 20 20 0 0 0 0 - -
September - 2017
PC-I/DCE submitted Chief Infra. Pre-PDWP held on 07/08/2017.
No Image
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
- - - - Line Deptt 160 0 20 20 0 0 0 0 - -
August - 2017
PC-I/DCE submitted Chief Infra. Pre-PDWP held on 07/08/2017.
No Image
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
- - - - Line Deptt 160 0 20 20 0 0 0 0 - -
July - 2017
PC-I/DCE submitted Chief Infra. Pre-PDWP held on 07/08/2017.
No Image
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.85 0 20 15 0 0 0 154.85 11% -
November - 2017
Financial bids of contractor opened.
No Image
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.85 0 20 20 0 0 0 154.85 11% -
October - 2017
Technical bids of contractor under process.
No Image
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.85 0 20 15 15 15 15 154.85 11% 9%
June - 2018
Sub base, base course, shoulder, earth work in progress.
No Image
1) Bakht Biland road (2 Km)
2) Attack road (2 Km)
3) Nagrai Payeen road (1 Km)
4) Pingal road (2 Km)
5) Shatai road (2 Km)
6) Chinar road (1 Km)
7) Kano Gumbat Kai road (1 Km)
8) Zual Baba road (1 Km)
9) Haji Abad road (0.8 Km)
10) Asilo road (1 Km)
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.85 0 20 15 15 15 15 154.85 11% 9%
May - 2018
Sub base, base course, shoulder, earth work in progress.
No Image
1) Bakht Biland road (2 Km)
2) Attack road (2 Km)
3) Nagrai Payeen road (1 Km)
4) Pingal road (2 Km)
5) Shatai road (2 Km)
6) Chinar road (1 Km)
7) Kano Gumbat Kai road (1 Km)
8) Zual Baba road (1 Km)
9) Haji Abad road (0.8 Km)
10) Asilo road (1 Km)
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.85 0 20 15 15 7.024 7.024 154.85 11% 4%
April - 2018
Sub base, base course, shoulder, earth work in progress.
No Image
1) Bakht Biland road (2 Km)
2) Attack road (2 Km)
3) Nagrai Payeen road (1 Km)
4) Pingal road (2 Km)
5) Shatai road (2 Km)
6) Chinar road (1 Km)
7) Kano Gumbat Kai road (1 Km)
8) Zual Baba road (1 Km)
9) Haji Abad road (0.8 Km)
10) Asilo road (1 Km)
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.85 0 20 15 0 0 0 154.85 11% -
March - 2018
Work order issued.
No Image
1) Bakht Biland road (2 Km)
2) Attack road (2 Km)
3) Nagrai Payeen road (1 Km)
4) Pingal road (2 Km)
5) Shatai road (2 Km)
6) Chinar road (1 Km)
7) Kano Gumbat Kai road (1 Km)
8) Zual Baba road (1 Km)
9) Haji Abad road (0.8 Km)
10) Asilo road (1 Km)
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.85 0 20 15 0 0 0 154.85 11% -
February - 2018
Work order issued.
No Image
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.85 0 20 15 0 0 0 154.85 11% -
January - 2018
Work order issued.
No Image
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 24.2 0 0 13 0 - -
December - 2020
No Image
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 24.2 0 0 13 0 - -
December - 2020
No Image
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 24.2 0 0 13 0 - -
October - 2020
No Image
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 24.2 0 0 13 0 - -
September - 2020
No Image
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 24.2 0 0 13 0 - -
August - 2020
No Image
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 24.2 0 0 13 0 - -
May - 2021
No Image
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 24.2 0 0 13 0 - -
April - 2021
No Image
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 24.2 0 0 13 0 - -
March - 2021
No Image
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 24.2 0 0 13 0 - -
February - 2021
No Image
1248
(OG)
191636-170285-Construction of Water Ponds / Reservoirs in the Mountainous Areas of Sub-Division D.I.Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 37.2 13 24.2 24.2 0 0 13 0 - -
January - 2021
No Image
Pages : 1