Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1020 (OG) |
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera. |
Nowshera PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1726.703 | 1783.7 | 10 | 10 | 10 | 10 | 1793.7 | 0 | 100% |
100% December - 2018 |
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress. |
No Image |
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel) | |||||||||||||||||||
1020 (OG) |
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera. |
Nowshera PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1726.703 | 1783.7 | 10 | 10 | 10 | 10 | 1793.7 | 0 | 100% |
100% November - 2018 |
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress. |
No Image |
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel) | |||||||||||||||||||
1020 (OG) |
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera. |
Nowshera PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1726.703 | 1783.7 | 10 | 10 | 10 | 10 | 1793.7 | 0 | 100% |
100% November - 2018 |
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress. |
No Image |
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel) | |||||||||||||||||||
1020 (OG) |
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera. |
Nowshera PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1726.703 | 1353.699 | 10 | 10 | 10 | 10 | 1363.699 | 363.004 | 79% |
79% April - 2019 |
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress. |
No Image |
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel) | |||||||||||||||||||
1020 (OG) |
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera. |
Nowshera PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1726.703 | 1353.699 | 10 | 10 | 10 | 10 | 1363.699 | 363.004 | 79% |
79% March - 2019 |
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress. |
No Image |
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel) | |||||||||||||||||||
1020 (OG) |
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera. |
Nowshera PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1726.703 | 1353.699 | 10 | 10 | 10 | 10 | 1363.699 | 363.004 | 79% |
79% March - 2019 |
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress. |
No Image |
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel) | |||||||||||||||||||
1020 (OG) |
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera. |
Nowshera PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1726.703 | 1353.699 | 10 | 10 | 10 | 10 | 1363.699 | 363.004 | 79% |
79% February - 2019 |
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress. |
No Image |
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel) | |||||||||||||||||||
1020 (OG) |
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera. |
Nowshera PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1726.703 | 1783.7 | 10 | 10 | 10 | 10 | 1793.7 | 0 | 100% |
100% January - 2019 |
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress. |
No Image |
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel) | |||||||||||||||||||
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
- December - 2020 |
No Image | |
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
- December - 2020 |
No Image | |
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
- October - 2020 |
No Image | |
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
- September - 2020 |
No Image | |
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
- August - 2020 |
No Image | |
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
July - 2020 |
No Image | |
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
- May - 2021 |
No Image | |
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
- April - 2021 |
No Image | |
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
- March - 2021 |
No Image | |
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
- February - 2021 |
No Image | |
1020 (OG) |
170041-Establishment of Planning and Monitoring Cell at Inspectorate General of Prisons, Khyber Pakhtunkhwa. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.606 | 22 | 0 | 0 | 0 | 0 | 22 | 0 | - |
- January - 2021 |
No Image | |
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
16-03-16 | 30-06-18 | - | 28-08-15 | - | 30 | 10 | 20 | 20 | 15 | 15 | 25 | 0 | 100% |
83% December - 2017 |
Completed (4 Km). |
No Image |
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 10 | 20 | 20 | 15 | 12 | 22 | 0 | 100% |
73% November - 2017 |
Length 4 Km - 4 Km asphalt. |
No Image |
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 10 | 20 | 20 | 15 | 10 | 20 | 0 | 100% |
67% October - 2017 |
Length 3 Km - 2.5 Km asphalt, base course completed. |
No Image |
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
16-03-16 | 30-06-18 | - | 28-08-15 | - | 30 | 10 | 20 | 20 | 10 | 7.1 | 17.1 | 0 | 100% |
57% September - 2017 |
Length 3 Km - 2.5 Km asphalt, base course completed. |
No Image |
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
16-03-16 | 30-06-18 | - | 28-08-15 | - | 30 | 10 | 20 | 20 | 10 | 7.1 | 17.1 | 0 | 100% |
57% August - 2017 |
Length 3 Km - 2.5 Km asphalt, base course completed. |
No Image |
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
16-03-16 | 30-06-18 | - | 28-08-15 | - | 30 | 10 | 20 | 20 | 7.1 | 7.1 | 17.1 | 0 | 100% |
57% July - 2017 |
Length 3 Km - 1.4 Km asphalt, base course completed. |
No Image |
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 10 | 20 | 15.11 | 15.11 | 15.11 | 25.11 | 0 | 100% |
84% June - 2018 |
Completed (4 Km). |
No Image |
1) Garhi Taj Muhammad to Garhi Mir Tayyab road 1.4 Km
2) Tuewell Koroona road, Mamo Khatki Koroona road 350 mtr
3) Mamo Khatki to Bela Baramad Khel Haryana Bala road to Garhi Sher Afzal 1 Km
4) Maqsood Abad Banglow road | |||||||||||||||||||
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 10 | 20 | 20 | 20 | 15 | 25 | 0 | 100% |
83% May - 2018 |
Completed (4 Km). |
No Image |
1) Garhi Taj Muhammad to Garhi Mir Tayyab road 1.4 Km
2) Tuewell Koroona road, Mamo Khatki Koroona road 350 mtr
3) Mamo Khatki to Bela Baramad Khel Haryana Bala road to Garhi Sher Afzal 1 Km
4) Maqsood Abad Banglow road | |||||||||||||||||||
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 10 | 20 | 20 | 20 | 20 | 30 | 0 | 100% |
100% April - 2018 |
Completed (4 Km). |
No Image |
1) Garhi Taj Muhammad to Garhi Mir Tayyab road 1.4 Km
2) Tuewell Koroona road, Mamo Khatki Koroona road 350 mtr
3) Mamo Khatki to Bela Baramad Khel Haryana Bala road to Garhi Sher Afzal 1 Km
4) Maqsood Abad Banglow road | |||||||||||||||||||
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 10 | 20 | 20 | 20 | 20 | 30 | 0 | 100% |
100% March - 2018 |
Completed (4 Km). |
No Image |
1) Garhi Taj Muhammad to Garhi Mir Tayyab road 1.4 Km
2) Tuewell Koroona road, Mamo Khatki Koroona road 350 mtr
3) Mamo Khatki to Bela Baramad Khel Haryana Bala road to Garhi Sher Afzal 1 Km
4) Maqsood Abad Banglow road | |||||||||||||||||||
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 10 | 20 | 20 | 15 | 15 | 25 | 0 | 100% |
83% February - 2018 |
Completed (4 Km). |
No Image |
1) Garhi Taj Muhammad to Garhi Mir Tayyab road 1.4 Km
2) Tuewell Koroona road, Mamo Khatki Koroona road 350 mtr
3) Mamo Khatki to Bela Baramad Khel Haryana Bala road to Garhi Sher Afzal 1 Km
4) Maqsood Abad Banglow road | |||||||||||||||||||
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 10 | 20 | 20 | 15 | 15 | 25 | 0 | 100% |
83% January - 2018 |
Completed (4 Km). |
No Image |
1020 (New) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147 | 0 | 130 | 130 | 0 | 0 | 0 | 17 | 88% |
- December - 2019 |
Work awarded to M/S Amanullah & Co. |
No Image |
1020 (New) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 147 | 0 | 130 | 130 | 0 | 0 | 0 | 17 | 88% |
- November - 2019 |
Evaluation og tech bids in progress. |
No Image |
1020 (New) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 147 | 0 | 130 | 130 | 0 | 0 | 0 | 17 | 88% |
- October - 2019 |
Tender called on 9//12/2019 |
No Image |
1020 (New) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 130 | 0 | 130 | 130 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
PC-I/DCE submitted to Director Construction on 30/07/2019. |
No Image |
1020 (New) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 130 | 0 | 130 | 130 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
PC-I/DCE submitted to Director Construction on 30/07/2019. |
No Image |
1020 (New) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147 | 0 | 130 | 130 | 0 | 0 | 0 | 17 | 88% |
- May - 2020 |
Work awarded to M/S Amanullah & Co. |
No Image |
1020 (New) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147 | 0 | 130 | 130 | 0 | 0 | 0 | 17 | 88% |
- April - 2020 |
Work awarded to M/S Amanullah & Co. |
No Image |
1020 (New) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147 | 0 | 130 | 130 | 0 | 0 | 0 | 17 | 88% |
- March - 2020 |
Work awarded to M/S Amanullah & Co. |
No Image |
1020 (New) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147 | 0 | 130 | 130 | 0 | 0 | 0 | 17 | 88% |
- February - 2020 |
Work awarded to M/S Amanullah & Co. |
No Image |
1020 (New) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147 | 0 | 130 | 130 | 0 | 0 | 0 | 17 | 88% |
- January - 2020 |
Work awarded to M/S Amanullah & Co. |
No Image |