Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1010 (OG) |
170523-F/S & Construction of Circular Bypass road Bannu (64.90 Km). |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 22.5 | 30 | 30 | 30 | 30 | 52.5 | 6905.105 | 1% |
1% December - 2018 |
Work order issued for Package-1 and 2. |
No Image |
1010 (OG) |
170523-F/S & Construction of Circular Bypass road Bannu (64.90 Km). |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 22.5 | 30 | 30 | 30 | 30 | 52.5 | 6905.105 | 1% |
1% November - 2018 |
work order issued for Package-1 and 2. |
No Image |
1010 (OG) |
170523-F/S & Construction of Circular Bypass road Bannu (64.90 Km). |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 22.5 | 30 | 30 | 30 | 30 | 52.5 | 6905.105 | 1% |
1% November - 2018 |
work order issued for Package-1 and 2. |
No Image |
1010 (OG) |
170523-F/S & Construction of Circular Bypass road Bannu (64.90 Km). |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 22.5 | 30 | 30 | 30 | 30 | 52.5 | 6905.105 | 1% |
1% April - 2019 |
Work order issued for Package-1 and 2. LOA issued for Package-III. Demand Rs.50 m. |
No Image |
1010 (OG) |
170523-F/S & Construction of Circular Bypass road Bannu (64.90 Km). |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 22.5 | 30 | 30 | 30 | 30 | 52.5 | 6905.105 | 1% |
1% March - 2019 |
Work order issued for Package-1 and 2. LOA issued for Package-III. Demand Rs.50 m. |
No Image |
1010 (OG) |
170523-F/S & Construction of Circular Bypass road Bannu (64.90 Km). |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 22.5 | 30 | 30 | 30 | 30 | 52.5 | 6905.105 | 1% |
1% March - 2019 |
Work order issued for Package-1 and 2. LOA issued for Package-III. Demand Rs.50 m. |
No Image |
1010 (OG) |
170523-F/S & Construction of Circular Bypass road Bannu (64.90 Km). |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 22.5 | 30 | 30 | 30 | 30 | 52.5 | 6905.105 | 1% |
1% February - 2019 |
Work order issued for Package-1 and 2. LOA issued for Package-III. Demand Rs.50 m. |
No Image |
1010 (OG) |
170523-F/S & Construction of Circular Bypass road Bannu (64.90 Km). |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 22.5 | 30 | 30 | 30 | 30 | 52.5 | 6905.105 | 1% |
1% January - 2019 |
Work order issued for Package-1 and 2. Demand Rs.50 m. |
No Image |
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
19-05-15 | 30-06-18 | - | 28-01-15 | - | 120 | 64.655 | 61.345 | 61.345 | 61.344 | 61.2 | 125.855 | 0 | 100% |
100% December - 2017 |
Length 11 Km - 10 Km asphalt completed and on remaining base course completed. |
No Image |
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 64.655 | 61.345 | 61.345 | 61.344 | 54.067 | 118.722 | 0 | 100% |
99% November - 2017 |
Length 11 Km - 10 Km asphalt completed and on remaining base course completed. |
No Image |
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 64.655 | 61.345 | 61.345 | 61.345 | 54.067 | 118.722 | 0 | 100% |
99% October - 2017 |
Length 11 Km - 10 Km asphalt completed and on remaining base course completed. |
No Image |
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
19-05-15 | 30-06-18 | - | 28-01-15 | - | 120 | 64.655 | 61.345 | 61.345 | 30.672 | 30.672 | 95.327 | 0 | 100% |
79% September - 2017 |
Length 11 Km - 5 Km asphalt completed and on remaining base course completed. |
No Image |
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
19-05-15 | 30-06-18 | - | 28-01-15 | - | 120 | 64.655 | 61.345 | 61.345 | 30.672 | 30.672 | 95.327 | 0 | 100% |
79% August - 2017 |
Length 11 Km - 3 Km asphalt completed and on remaining base course completed. |
No Image |
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
19-05-15 | 30-06-18 | - | 28-01-15 | - | 120 | 64.655 | 61.345 | 61.345 | 21.777 | 21.777 | 86.432 | 0 | 100% |
72% July - 2017 |
Length 11 Km - 8 Km base course completed and on remaining sub-base work in progress. |
No Image |
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 64.655 | 61.345 | 61.345 | 61.345 | 61.344 | 125.999 | 0 | 100% |
100% June - 2018 |
Length 11 Km - 10 Km asphalt completed and structure work in progress. |
No Image |
1) Hazrat Baba to Wali Abad road 1.6 Km
2) Mohallah Haya Khel to Rind road 0.70 Km
3) Insaf road to Ghafoor Abad 0.50 Km
4) Insaf road to Gharib Abad 0.50 Km
5) Bazid Khel road
6) Canal road to Merozai raod 3.30 Km | |||||||||||||||||||
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 64.655 | 61.345 | 61.345 | 61.344 | 61.2 | 125.855 | 0 | 100% |
100% May - 2018 |
Length 11 Km - 10 Km asphalt completed and structure work in progress. Rs.6.045 m demanded for completion of scheme above alloaction. |
No Image |
1) Hazrat Baba to Wali Abad road 1.6 Km
2) Mohallah Haya Khel to Rind road 0.70 Km
3) Insaf road to Ghafoor Abad 0.50 Km
4) Insaf road to Gharib Abad 0.50 Km
5) Bazid Khel road
6) Canal road to Merozai raod 3.30 Km | |||||||||||||||||||
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 64.655 | 61.345 | 61.345 | 61.344 | 61.2 | 125.855 | 0 | 100% |
100% April - 2018 |
Length 11 Km - 10 Km asphalt completed and structure work in progress. |
No Image |
1) Hazrat Baba to Wali Abad road 1.6 Km
2) Mohallah Haya Khel to Rind road 0.70 Km
3) Insaf road to Ghafoor Abad 0.50 Km
4) Insaf road to Gharib Abad 0.50 Km
5) Bazid Khel road
6) Canal road to Merozai raod 3.30 Km | |||||||||||||||||||
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 64.655 | 61.345 | 61.345 | 61.344 | 61.2 | 125.855 | 0 | 100% |
100% March - 2018 |
Length 11 Km - 10 Km asphalt completed and structure work in progress. Rs.6.045 m demanded for completion. |
No Image |
1) Hazrat Baba to Wali Abad road 1.6 Km
2) Mohallah Haya Khel to Rind road 0.70 Km
3) Insaf road to Ghafoor Abad 0.50 Km
4) Insaf road to Gharib Abad 0.50 Km
5) Bazid Khel road
6) Canal road to Merozai raod 3.30 Km | |||||||||||||||||||
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 64.655 | 61.345 | 61.345 | 61.344 | 61.2 | 125.855 | 0 | 100% |
100% February - 2018 |
Length 11 Km - 10 Km asphalt completed and structure work in progress. Rs.6.045 m demanded for completion. |
No Image |
1) Hazrat Baba to Wali Abad road 1.6 Km
2) Mohallah Haya Khel to Rind road 0.70 Km
3) Insaf road to Ghafoor Abad 0.50 Km
4) Insaf road to Gharib Abad 0.50 Km
5) Bazid Khel road
6) Canal road to Merozai raod 3.30 Km | |||||||||||||||||||
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 64.655 | 61.345 | 61.345 | 61.344 | 61.2 | 125.855 | 0 | 100% |
100% January - 2018 |
Length 11 Km - 10 Km asphalt completed and structure work in progress. Rs.6.045 m demanded for completion. |
No Image |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 40.066 | 0 | 0 | 139.934 | 0 | - |
- December - 2020 |
No Image | |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 40.066 | 0 | 0 | 139.934 | 0 | - |
- December - 2020 |
No Image | |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 40.066 | 0 | 0 | 139.934 | 0 | - |
- October - 2020 |
No Image | |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 40.066 | 0 | 0 | 139.934 | 0 | - |
- September - 2020 |
No Image | |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 40.066 | 0 | 0 | 139.934 | 0 | - |
- August - 2020 |
No Image | |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 0 | 0 | 0 | 139.934 | 0 | - |
- July - 2020 |
No Image | |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 40.066 | 0 | 0 | 139.934 | 0 | - |
- May - 2021 |
No Image | |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 40.066 | 0 | 0 | 139.934 | 0 | - |
- April - 2021 |
No Image | |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 40.066 | 0 | 0 | 139.934 | 0 | - |
- March - 2021 |
No Image | |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 40.066 | 0 | 0 | 139.934 | 0 | - |
- February - 2021 |
No Image | |
1010 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 139.934 | 40.066 | 40.066 | 0 | 0 | 139.934 | 0 | - |
- January - 2021 |
No Image | |
1010 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.611 | 73.14 | 10 | 9.575 | 9.575 | 9.575 | 82.715 | 40.471 | 67% |
67% December - 2019 |
Project directorate setup. |
No Image |
1010 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.611 | 73.14 | 10 | 10 | 2.5 | 2.5 | 75.64 | 40.471 | 67% |
61% November - 2019 |
Project directorate setup. |
No Image |
1010 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.611 | 73.14 | 10 | 10 | 2.5 | 2.5 | 75.64 | 40.471 | 67% |
61% October - 2019 |
Project directorate setup. |
No Image |
1010 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.611 | 73.14 | 10 | 10 | 2.5 | 2.5 | 75.64 | 40.471 | 67% |
61% September - 2019 |
Project directorate setup. |
No Image |
1010 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.611 | 73.14 | 10 | 10 | 2.5 | 2.5 | 75.64 | 40.471 | 67% |
61% August - 2019 |
Project directorate setup. |
No Image |
1010 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 161.686 | 73.14 | 10 | 46.806 | 46.806 | 46.806 | 119.946 | 78.546 | 51% |
74% May - 2020 |
Project directorate setup.
2nd revised PC-1 to the tune of Rs. 123.611 M approved by PDWP approved in PDWP meetig held on 02/02/2018. |
No Image |
1010 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 161.686 | 73.14 | 10 | 9.575 | 9.575 | 9.575 | 82.715 | 78.546 | 51% |
51% April - 2020 |
Project directorate setup.
2nd revised PC-1 to the tune of Rs. 123.611 M approved by PDWP approved in PDWP meetig held on 02/02/2018. |
No Image |
1010 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 161.686 | 73.14 | 10 | 9.575 | 9.575 | 9.575 | 82.715 | 78.546 | 51% |
51% March - 2020 |
Project directorate setup.
2nd revised PC-1 to the tune of Rs. 123.611 M approved by PDWP approved in PDWP meetig held on 02/02/2018. |
No Image |
1010 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 161.686 | 73.14 | 10 | 9.575 | 9.575 | 9.575 | 82.715 | 78.546 | 51% |
51% February - 2020 |
Project directorate setup.
2nd revised PC-1 to the tune of Rs. 123.611 M approved by PDWP approved in PDWP meetig held on 02/02/2018. |
No Image |
1010 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 161.686 | 73.14 | 10 | 9.575 | 9.575 | 9.575 | 82.715 | 78.546 | 51% |
51% January - 2020 |
Project directorate setup. |
No Image |
Pages : 1 |