Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
999 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1708.287 | 20 | 19.15 | 19.15 | 19.15 | 1727.437 | 70.234 | 96% |
96% December - 2019 |
Length 32 Km - subtantially completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
999 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1708.287 | 20 | 20 | 5 | 5 | 1713.287 | 70.234 | 96% |
95% November - 2019 |
Length 32 Km - subtantially completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
999 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1708.287 | 20 | 20 | 5 | 5 | 1713.287 | 70.234 | 96% |
95% October - 2019 |
Length 32 Km - subtantially completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
999 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1708.287 | 20 | 20 | 5 | 5 | 1713.287 | 70.234 | 96% |
95% September - 2019 |
Length 32 Km - subtantially completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
999 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1708.287 | 20 | 20 | 5 | 5 | 1713.287 | 70.234 | 96% |
95% August - 2019 |
Length 32 Km - subtantially completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
999 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1708.287 | 20 | 19.15 | 19.15 | 19.15 | 1727.437 | 70.234 | 96% |
96% May - 2020 |
Length 32 Km - subtantially completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
999 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1708.287 | 20 | 19.15 | 19.15 | 19.15 | 1727.437 | 70.234 | 96% |
96% April - 2020 |
Length 32 Km - subtantially completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
999 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1708.287 | 20 | 19.15 | 19.15 | 19.15 | 1727.437 | 70.234 | 96% |
96% March - 2020 |
Length 32 Km - subtantially completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
999 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1708.287 | 20 | 19.15 | 19.15 | 19.15 | 1727.437 | 70.234 | 96% |
96% February - 2020 |
Length 32 Km - subtantially completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
999 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1708.287 | 20 | 19.15 | 19.15 | 19.15 | 1727.437 | 70.234 | 96% |
96% January - 2020 |
Length 32 Km - subtantially completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
16-06-15 | 30-06-18 | - | 30-12-14 | - | 50.614 | 37.195 | 5 | 5 | 3.75 | 3.75 | 40.945 | 8.419 | 83% |
81% December - 2017 |
Length 4.5 Km - 4.5 Km BT completed. Liabiilty of contractor Rs.19.16 m. |
No Image |
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
16-06-15 | 30-06-18 | - | 30-12-14 | - | 50.614 | 37.195 | 5 | 5 | 2.5 | 2.5 | 39.695 | 8.419 | 83% |
78% September - 2017 |
Length 4.5 Km - 3 Km BT completed, 1.5 Km WBM completed. |
No Image |
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
16-06-15 | 30-06-18 | - | 30-12-14 | - | 50.614 | 37.195 | 5 | 5 | 2.5 | 0 | 37.195 | 8.419 | 83% |
73% August - 2017 |
Length 4.5 Km - 2 Km BT completed, 4.5 Km WBM completed. |
No Image |
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
16-06-15 | 30-06-18 | - | 30-12-14 | - | 50.614 | 37.195 | 5 | 5 | 1.775 | 0 | 37.195 | 8.419 | 83% |
73% July - 2017 |
Length 4.5 Km - 2 Km BT completed, 4.5 Km WBM completed. |
No Image |
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50.614 | 37.195 | 5 | 5 | 3.75 | 3.75 | 40.945 | 8.419 | 83% |
81% November - 2017 |
Length 4.5 Km - 4.5 Km BT completed. Liabilty of contractor 19.16 M |
No Image |
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50.614 | 37.195 | 5 | 5 | 3.75 | 2.5 | 39.695 | 8.419 | 83% |
78% October - 2017 |
Length 4.5 Km - 4.5 Km BT completed. |
No Image |
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50.614 | 32.195 | 5 | 5 | 5 | 5 | 37.195 | 13.419 | 73% |
73% June - 2018 |
Length 4.5 Km - 4.5 Km BT completed. |
No Image |
Hangu | |||||||||||||||||||
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50.614 | 32.195 | 5 | 5 | 5 | 5 | 37.195 | 13.419 | 73% |
73% May - 2018 |
Length 4.5 Km - 4.5 Km BT completed.
Funds to the tune of Rs. 13.6 M above alloaction required for completion. |
No Image |
Hangu | |||||||||||||||||||
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50.614 | 32.195 | 5 | 5 | 5 | 5 | 37.195 | 13.419 | 73% |
73% April - 2018 |
Length 4.5 Km - 4.5 Km BT completed. |
No Image |
Hangu | |||||||||||||||||||
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50.614 | 32.195 | 5 | 5 | 3.75 | 3.75 | 35.945 | 13.419 | 73% |
71% March - 2018 |
Length 4.5 Km - 4.5 Km BT completed.
Liabiilty of contractor Rs. 13.5 m. |
No Image |
Hangu | |||||||||||||||||||
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50.614 | 32.195 | 5 | 5 | 3.75 | 3.75 | 35.945 | 13.419 | 73% |
71% February - 2018 |
Length 4.5 Km - 4.5 Km BT completed. Liabiilty of contractor Rs.19.16 m. |
No Image |
Hangu | |||||||||||||||||||
999 (OG) |
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50.614 | 37.195 | 5 | 5 | 3.75 | 3.75 | 40.945 | 8.419 | 83% |
81% January - 2018 |
Length 4.5 Km - 4.5 Km BT completed. Liabiilty of contractor Rs.19.16 m. |
No Image |
Hangu | |||||||||||||||||||
999 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 44.2 | 10 | 20 | 15.0005 | 5 | 49.2 | 62.336 | 47% |
42% December - 2018 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
999 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 44.2 | 10 | 20 | 15.001 | 5 | 49.2 | 62.336 | 47% |
42% November - 2018 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
999 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 44.2 | 10 | 20 | 15.001 | 5 | 49.2 | 62.336 | 47% |
42% November - 2018 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
999 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 44.2 | 10 | 25 | 25.0005 | 22.495 | 66.695 | 62.336 | 47% |
57% April - 2019 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
999 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 44.2 | 10 | 25 | 22.5005 | 15 | 59.2 | 62.336 | 47% |
51% March - 2019 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
999 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 44.2 | 10 | 25 | 22.5005 | 15 | 59.2 | 62.336 | 47% |
51% March - 2019 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
999 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 44.2 | 10 | 25 | 22.5005 | 15 | 59.2 | 62.336 | 47% |
51% February - 2019 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
999 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 44.2 | 10 | 20 | 15.0005 | 9.387 | 53.587 | 62.336 | 47% |
46% January - 2019 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
- December - 2020 |
No Image | |
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
- December - 2020 |
No Image | |
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
- October - 2020 |
No Image | |
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
- September - 2020 |
No Image | |
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
- August - 2020 |
No Image | |
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
July - 2020 |
No Image | |
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
- May - 2021 |
No Image | |
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
- April - 2021 |
No Image | |
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
- March - 2021 |
No Image | |
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
- February - 2021 |
No Image | |
999 (OG) |
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 142.608 | 75 | 0 | 0 | 0 | 0 | 75 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |