Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, January - 2019, January - 2020, February - 2021, February - 2018, February - 2019, February - 2020, March - 2021, March - 2018, March - 2019, March - 2020, April - 2021, April - 2018, April - 2019, April - 2020, May - 2021, May - 2018, May - 2020, June - 2018, July - 2017, July - 2020, August - 2017, August - 2019, August - 2020, September - 2020, September - 2017, September - 2019, October - 2020, October - 2017, October - 2019, November - 2017, November - 2018, November - 2019, December - 2020, December - 2017, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
998
(OG)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG)
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 135 25 23.9375 23.9375 23.9375 158.9375 250.621 39% 39%
December - 2019
Bridge (180 mtr) - 21 Piles complted. Girder launching In progress
No Image
998
(OG)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG)
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 135 25 25 6.25 6.25 141.25 250.621 39% 34%
November - 2019
Bridge (180 mtr) - 21 Piles complted. Girder launching In progress
No Image
998
(OG)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG)
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 135 25 25 6.25 6.25 141.25 250.621 39% 34%
October - 2019
Bridge (180 mtr) - 21 Piles complted. Girder launching In progress
No Image
998
(OG)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG)
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 135 25 25 6.25 6.25 141.25 250.621 39% 34%
September - 2019
Bridge (180 mtr) - 21 Piles complted. Girder launching In proress
No Image
998
(OG)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG)
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 135 25 25 6.25 6.25 141.25 250.621 39% 34%
August - 2019
Bridge (180 mtr) - 16/21 piles completed, 5 in progress.
No Image
998
(OG)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG)
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 135 25 23.9375 23.9375 23.9375 158.9375 250.621 39% 39%
May - 2020
Bridge (180 mtr) - 21 Piles completed. Girder launching completed and approacges of road in progress.
No Image
998
(OG)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG)
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 135 25 23.9375 23.9375 23.9375 158.9375 250.621 39% 39%
April - 2020
Bridge (180 mtr) - 21 Piles completed. Girder launching completed and approacges of road in progress.
No Image
998
(OG)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG)
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 135 25 23.9375 23.9375 23.9375 158.9375 250.621 39% 39%
March - 2020
Bridge (180 mtr) - 21 Piles completed. Girder launching completed and approacges of road in progress.
No Image
998
(OG)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG)
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 135 25 23.9375 23.9375 23.9375 158.9375 250.621 39% 39%
February - 2020
Bridge (180 mtr) - 21 Piles completed. Girder launching completed and approacges of road in progress.
No Image
998
(OG)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG)
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 135 25 23.9375 23.9375 23.9375 158.9375 250.621 39% 39%
January - 2020
Bridge (180 mtr) - 21 Piles complted. Girder launching In progress
No Image
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
08-09-15 30-06-18 - 28-01-15 - 100 56 44 44 22 4.843 60.843 0 100% 61%
December - 2017
Length 6 Km - 4 Km BT completed. 500 m WBM completed. Structure work in progress.
No Image
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
08-09-15 30-06-18 - 28-01-15 - 100 56 44 44 22 0 56 0 100% 56%
September - 2017
Length 6 Km - 4 Km BT completed. 500 m WBM completed. Structure work in progress.
No Image
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
08-09-15 30-06-18 - 28-01-15 - 100 56 44 44 22 0 56 0 100% 56%
August - 2017
Length 6 Km - 4 Km BT completed.
No Image
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
08-09-15 30-06-18 - 28-01-15 - 100 56 44 44 15.62 0 56 0 100% 56%
July - 2017
Length 6 Km - 4 Km BT completed.
No Image
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 56 44 44 22 1.4 57.4 0 100% 57%
November - 2017
Length 6 Km - 4 Km BT completed. 500 m WBM completed. Structure work in progress.
No Image
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 56 44 44 22 1.4 57.4 0 100% 57%
October - 2017
Length 6 Km - 4 Km BT completed. 500 m WBM completed. Structure work in progress.
No Image
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 56 44 24.423 24.423 24.424 80.424 0 100% 80%
June - 2018
Length 6 Km - 4 Km BT completed. 500 m WBM completed. Structure work in progress. Cannot be completed because of default of contractor.
No Image
Hangu
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 56 44 44 44 25.1 81.1 0 100% 81%
May - 2018
Length 6 Km - 4 Km BT completed. 500 m WBM completed. Structure work in progress. Cannot be completed because of default of contractor.
No Image
Hangu
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 56 44 44 22 16.2 72.2 0 100% 72%
April - 2018
Length 6 Km - 4 Km BT completed. 500 m WBM completed. Structure work in progress.
No Image
Hangu
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 56 44 44 22 8.536 64.536 0 100% 65%
March - 2018
Length 6 Km - 4 Km BT completed. 500 m WBM completed. Structure work in progress.
No Image
Hangu
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 56 44 44 22 6.854 62.854 0 100% 63%
February - 2018
Length 6 Km - 4 Km BT completed. 500 m WBM completed. Structure work in progress.
No Image
Hangu
998
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 56 44 44 22 5.643 61.643 0 100% 62%
January - 2018
Length 6 Km - 4 Km BT completed. 500 m WBM completed. Structure work in progress.
No Image
Hangu
998
(OG)
150889-Pavement of roads and streets for UC Saray Saleh, Shah Maqsood, Rehana, Ali Khan, Darwesh, Pind Hasim Khan, UC Sourth and Pandak of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 300 240.568 89.431 89.431 49.716 17.856 258.424 0 100% 86%
December - 2018
48 units (PCC/BT) - earth work, sub base in progress.
No Image
1) Pavement of road/street at village Gheba
2) Construction of road at Shah Maqsood
3) Construction of road/street at Thanda Choa UC Shah Maqsood
4) Pavement of road/streets a village Kholian Kalawan Mohara
5) Construction of road Shah Maqsood Maira to Bandi Sher Khan road UC Shah Maqsood
6) Pavement of road/street at village Akhoon Bandi and Mohallah Toheed Abad
7) Pavement of road/street at village Nikah Pah
8) Pavement of street at village Mohari No.1 UC Shah Maqsood
9) Pavement of road N/H of Master Ashiq Lora Chowk
10) Pavement of roads/street at village Mohari No.2 UC Shah Maqsood
11) Construction of road from Batkh to Mohalla Jalsi
12) Construction of road Soka Changi Bandi UC Sarai Saleh
13) Construction ofroad Saida Abad Sarai Saleh
14) Pavement of street at Mohallah Lehanda
15) Construction of raod at Ghar
16) Pavement of street at Mohallah Gul Bahaar Colony Jandran and Khan Bahadar UC Serai Saleh
17) Pavement of street at Tatreela Ghar
18) Pavement of road/street at Sarai Saleh Maira UC Serai Saleh
19) Pavement of roads/street at Sameer Ayub Colony Sarai Saleh UC Sarai Saleh
20) Construction of road/streets at village Moonan
21) Construction of road/street at village Mohara and Faisal Colony
22) Construction of road/street at Manzoor Colony Nai Abadi and Yasir Colony UC Ali Khan
23) Construction of road/street at Soka Nazir Abad and Maira Ali Khan UC Ali Khan
24) Construction of road/strets at village Muradabad UC Ali Khan
25) Construction of road/street at village Shah Muhammad and Mohallah Tanki UC Ali Khan
26) Construction of road/street at village Kahal UC Ali Khan
27) Construction of main road Pandak
28) Construction of Mairan Ali Khan road
29) Construction of bridge at Pandak Soka UC Pandak
30) Construction of road/streets at Talokar Dheri UC Pandak
31) Construction of road/streets at Gher Khan Maira
32) Construction of road/street at Soka Pandak UC Pandak
33) Pavement of roads/street village Durrnaian and Jamia
34) Pavement of roads/sreet village Nurdi Mohallah Shamali Mohara
35) Pavement fo roads/streets at Mohallah Dharri UC Rehana
36) Pavement of raod/street Kotha Pir Kot
37) Pavement of roads/street at Dolni
38) Pavement of road/street at village Chapra and Pir Kot Maira
39) Pavement of road/street at village Pind Jamal Khan and Kamal Pur
40) Construction of Maira Pandak road
41) Pavement of road/street at village Rehana Pinda Choi UC Rehana
42) Pavement of roads/streets at Mohallah Chitri and Kanat
43) Construction of road a GY Zareen House
44) Pavement of roads/steets at village Koaka Dinga
45) Pavement of road/street at Pind Hashim Khan
46) Construction of road/street at Mohallah Munsafabad
47) Construction of Serai Saleh Maira road
48) Construction of Tanki Ali Khan
49) Construction of road/street at Mirpur UC Pandak
50) Construction of road/steet at Soka Pandak
998
(OG)
150889-Pavement of roads and streets for UC Saray Saleh, Shah Maqsood, Rehana, Ali Khan, Darwesh, Pind Hasim Khan, UC Sourth and Pandak of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 300 240.568 89.431 89.431 49.716 12.027 252.595 0 100% 84%
November - 2018
48 units (PCC/BT) - earth work, sub base in progress.
No Image
1) Pavement of road/street at village Gheba
2) Construction of road at Shah Maqsood
3) Construction of road/street at Thanda Choa UC Shah Maqsood
4) Pavement of road/streets a village Kholian Kalawan Mohara
5) Construction of road Shah Maqsood Maira to Bandi Sher Khan road UC Shah Maqsood
6) Pavement of road/street at village Akhoon Bandi and Mohallah Toheed Abad
7) Pavement of road/street at village Nikah Pah
8) Pavement of street at village Mohari No.1 UC Shah Maqsood
9) Pavement of road N/H of Master Ashiq Lora Chowk
10) Pavement of roads/street at village Mohari No.2 UC Shah Maqsood
11) Construction of road from Batkh to Mohalla Jalsi
12) Construction of road Soka Changi Bandi UC Sarai Saleh
13) Construction ofroad Saida Abad Sarai Saleh
14) Pavement of street at Mohallah Lehanda
15) Construction of raod at Ghar
16) Pavement of street at Mohallah Gul Bahaar Colony Jandran and Khan Bahadar UC Serai Saleh
17) Pavement of street at Tatreela Ghar
18) Pavement of road/street at Sarai Saleh Maira UC Serai Saleh
19) Pavement of roads/street at Sameer Ayub Colony Sarai Saleh UC Sarai Saleh
20) Construction of road/streets at village Moonan
21) Construction of road/street at village Mohara and Faisal Colony
22) Construction of road/street at Manzoor Colony Nai Abadi and Yasir Colony UC Ali Khan
23) Construction of road/street at Soka Nazir Abad and Maira Ali Khan UC Ali Khan
24) Construction of road/strets at village Muradabad UC Ali Khan
25) Construction of road/street at village Shah Muhammad and Mohallah Tanki UC Ali Khan
26) Construction of road/street at village Kahal UC Ali Khan
27) Construction of main road Pandak
28) Construction of Mairan Ali Khan road
29) Construction of bridge at Pandak Soka UC Pandak
30) Construction of road/streets at Talokar Dheri UC Pandak
31) Construction of road/streets at Gher Khan Maira
32) Construction of road/street at Soka Pandak UC Pandak
33) Pavement of roads/street village Durrnaian and Jamia
34) Pavement of roads/sreet village Nurdi Mohallah Shamali Mohara
35) Pavement fo roads/streets at Mohallah Dharri UC Rehana
36) Pavement of raod/street Kotha Pir Kot
37) Pavement of roads/street at Dolni
38) Pavement of road/street at village Chapra and Pir Kot Maira
39) Pavement of road/street at village Pind Jamal Khan and Kamal Pur
40) Construction of Maira Pandak road
41) Pavement of road/street at village Rehana Pinda Choi UC Rehana
42) Pavement of roads/streets at Mohallah Chitri and Kanat
43) Construction of road a GY Zareen House
44) Pavement of roads/steets at village Koaka Dinga
45) Pavement of road/street at Pind Hashim Khan
46) Construction of road/street at Mohallah Munsafabad
47) Construction of Serai Saleh Maira road
48) Construction of Tanki Ali Khan
49) Construction of road/street at Mirpur UC Pandak
50) Construction of road/steet at Soka Pandak
998
(OG)
150889-Pavement of roads and streets for UC Saray Saleh, Shah Maqsood, Rehana, Ali Khan, Darwesh, Pind Hasim Khan, UC Sourth and Pandak of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 300 240.568 89.431 89.431 49.716 12.027 252.595 0 100% 84%
November - 2018
48 units (PCC/BT) - earth work, sub base in progress.
No Image
1) Pavement of road/street at village Gheba
2) Construction of road at Shah Maqsood
3) Construction of road/street at Thanda Choa UC Shah Maqsood
4) Pavement of road/streets a village Kholian Kalawan Mohara
5) Construction of road Shah Maqsood Maira to Bandi Sher Khan road UC Shah Maqsood
6) Pavement of road/street at village Akhoon Bandi and Mohallah Toheed Abad
7) Pavement of road/street at village Nikah Pah
8) Pavement of street at village Mohari No.1 UC Shah Maqsood
9) Pavement of road N/H of Master Ashiq Lora Chowk
10) Pavement of roads/street at village Mohari No.2 UC Shah Maqsood
11) Construction of road from Batkh to Mohalla Jalsi
12) Construction of road Soka Changi Bandi UC Sarai Saleh
13) Construction ofroad Saida Abad Sarai Saleh
14) Pavement of street at Mohallah Lehanda
15) Construction of raod at Ghar
16) Pavement of street at Mohallah Gul Bahaar Colony Jandran and Khan Bahadar UC Serai Saleh
17) Pavement of street at Tatreela Ghar
18) Pavement of road/street at Sarai Saleh Maira UC Serai Saleh
19) Pavement of roads/street at Sameer Ayub Colony Sarai Saleh UC Sarai Saleh
20) Construction of road/streets at village Moonan
21) Construction of road/street at village Mohara and Faisal Colony
22) Construction of road/street at Manzoor Colony Nai Abadi and Yasir Colony UC Ali Khan
23) Construction of road/street at Soka Nazir Abad and Maira Ali Khan UC Ali Khan
24) Construction of road/strets at village Muradabad UC Ali Khan
25) Construction of road/street at village Shah Muhammad and Mohallah Tanki UC Ali Khan
26) Construction of road/street at village Kahal UC Ali Khan
27) Construction of main road Pandak
28) Construction of Mairan Ali Khan road
29) Construction of bridge at Pandak Soka UC Pandak
30) Construction of road/streets at Talokar Dheri UC Pandak
31) Construction of road/streets at Gher Khan Maira
32) Construction of road/street at Soka Pandak UC Pandak
33) Pavement of roads/street village Durrnaian and Jamia
34) Pavement of roads/sreet village Nurdi Mohallah Shamali Mohara
35) Pavement fo roads/streets at Mohallah Dharri UC Rehana
36) Pavement of raod/street Kotha Pir Kot
37) Pavement of roads/street at Dolni
38) Pavement of road/street at village Chapra and Pir Kot Maira
39) Pavement of road/street at village Pind Jamal Khan and Kamal Pur
40) Construction of Maira Pandak road
41) Pavement of road/street at village Rehana Pinda Choi UC Rehana
42) Pavement of roads/streets at Mohallah Chitri and Kanat
43) Construction of road a GY Zareen House
44) Pavement of roads/steets at village Koaka Dinga
45) Pavement of road/street at Pind Hashim Khan
46) Construction of road/street at Mohallah Munsafabad
47) Construction of Serai Saleh Maira road
48) Construction of Tanki Ali Khan
49) Construction of road/street at Mirpur UC Pandak
50) Construction of road/steet at Soka Pandak
998
(OG)
150889-Pavement of roads and streets for UC Saray Saleh, Shah Maqsood, Rehana, Ali Khan, Darwesh, Pind Hasim Khan, UC Sourth and Pandak of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 300 240.568 89.431 89.431 89.431 38.279 278.847 0 100% 93%
April - 2019
48 units (PCC/BT) - earth work, sub base in progress.
No Image
1) Pavement of road/street at village Gheba
2) Construction of road at Shah Maqsood
3) Construction of road/street at Thanda Choa UC Shah Maqsood
4) Pavement of road/streets a village Kholian Kalawan Mohara
5) Construction of road Shah Maqsood Maira to Bandi Sher Khan road UC Shah Maqsood
6) Pavement of road/street at village Akhoon Bandi and Mohallah Toheed Abad
7) Pavement of road/street at village Nikah Pah
8) Pavement of street at village Mohari No.1 UC Shah Maqsood
9) Pavement of road N/H of Master Ashiq Lora Chowk
10) Pavement of roads/street at village Mohari No.2 UC Shah Maqsood
11) Construction of road from Batkh to Mohalla Jalsi
12) Construction of road Soka Changi Bandi UC Sarai Saleh
13) Construction ofroad Saida Abad Sarai Saleh
14) Pavement of street at Mohallah Lehanda
15) Construction of raod at Ghar
16) Pavement of street at Mohallah Gul Bahaar Colony Jandran and Khan Bahadar UC Serai Saleh
17) Pavement of street at Tatreela Ghar
18) Pavement of road/street at Sarai Saleh Maira UC Serai Saleh
19) Pavement of roads/street at Sameer Ayub Colony Sarai Saleh UC Sarai Saleh
20) Construction of road/streets at village Moonan
21) Construction of road/street at village Mohara and Faisal Colony
22) Construction of road/street at Manzoor Colony Nai Abadi and Yasir Colony UC Ali Khan
23) Construction of road/street at Soka Nazir Abad and Maira Ali Khan UC Ali Khan
24) Construction of road/strets at village Muradabad UC Ali Khan
25) Construction of road/street at village Shah Muhammad and Mohallah Tanki UC Ali Khan
26) Construction of road/street at village Kahal UC Ali Khan
27) Construction of main road Pandak
28) Construction of Mairan Ali Khan road
29) Construction of bridge at Pandak Soka UC Pandak
30) Construction of road/streets at Talokar Dheri UC Pandak
31) Construction of road/streets at Gher Khan Maira
32) Construction of road/street at Soka Pandak UC Pandak
33) Pavement of roads/street village Durrnaian and Jamia
34) Pavement of roads/sreet village Nurdi Mohallah Shamali Mohara
35) Pavement fo roads/streets at Mohallah Dharri UC Rehana
36) Pavement of raod/street Kotha Pir Kot
37) Pavement of roads/street at Dolni
38) Pavement of road/street at village Chapra and Pir Kot Maira
39) Pavement of road/street at village Pind Jamal Khan and Kamal Pur
40) Construction of Maira Pandak road
41) Pavement of road/street at village Rehana Pinda Choi UC Rehana
42) Pavement of roads/streets at Mohallah Chitri and Kanat
43) Construction of road a GY Zareen House
44) Pavement of roads/steets at village Koaka Dinga
45) Pavement of road/street at Pind Hashim Khan
46) Construction of road/street at Mohallah Munsafabad
47) Construction of Serai Saleh Maira road
48) Construction of Tanki Ali Khan
49) Construction of road/street at Mirpur UC Pandak
50) Construction of road/steet at Soka Pandak
998
(OG)
150889-Pavement of roads and streets for UC Saray Saleh, Shah Maqsood, Rehana, Ali Khan, Darwesh, Pind Hasim Khan, UC Sourth and Pandak of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 300 240.568 89.431 89.431 89.431 33.73 274.298 0 100% 91%
March - 2019
48 units (PCC/BT) - earth work, sub base in progress.
No Image
1) Pavement of road/street at village Gheba
2) Construction of road at Shah Maqsood
3) Construction of road/street at Thanda Choa UC Shah Maqsood
4) Pavement of road/streets a village Kholian Kalawan Mohara
5) Construction of road Shah Maqsood Maira to Bandi Sher Khan road UC Shah Maqsood
6) Pavement of road/street at village Akhoon Bandi and Mohallah Toheed Abad
7) Pavement of road/street at village Nikah Pah
8) Pavement of street at village Mohari No.1 UC Shah Maqsood
9) Pavement of road N/H of Master Ashiq Lora Chowk
10) Pavement of roads/street at village Mohari No.2 UC Shah Maqsood
11) Construction of road from Batkh to Mohalla Jalsi
12) Construction of road Soka Changi Bandi UC Sarai Saleh
13) Construction ofroad Saida Abad Sarai Saleh
14) Pavement of street at Mohallah Lehanda
15) Construction of raod at Ghar
16) Pavement of street at Mohallah Gul Bahaar Colony Jandran and Khan Bahadar UC Serai Saleh
17) Pavement of street at Tatreela Ghar
18) Pavement of road/street at Sarai Saleh Maira UC Serai Saleh
19) Pavement of roads/street at Sameer Ayub Colony Sarai Saleh UC Sarai Saleh
20) Construction of road/streets at village Moonan
21) Construction of road/street at village Mohara and Faisal Colony
22) Construction of road/street at Manzoor Colony Nai Abadi and Yasir Colony UC Ali Khan
23) Construction of road/street at Soka Nazir Abad and Maira Ali Khan UC Ali Khan
24) Construction of road/strets at village Muradabad UC Ali Khan
25) Construction of road/street at village Shah Muhammad and Mohallah Tanki UC Ali Khan
26) Construction of road/street at village Kahal UC Ali Khan
27) Construction of main road Pandak
28) Construction of Mairan Ali Khan road
29) Construction of bridge at Pandak Soka UC Pandak
30) Construction of road/streets at Talokar Dheri UC Pandak
31) Construction of road/streets at Gher Khan Maira
32) Construction of road/street at Soka Pandak UC Pandak
33) Pavement of roads/street village Durrnaian and Jamia
34) Pavement of roads/sreet village Nurdi Mohallah Shamali Mohara
35) Pavement fo roads/streets at Mohallah Dharri UC Rehana
36) Pavement of raod/street Kotha Pir Kot
37) Pavement of roads/street at Dolni
38) Pavement of road/street at village Chapra and Pir Kot Maira
39) Pavement of road/street at village Pind Jamal Khan and Kamal Pur
40) Construction of Maira Pandak road
41) Pavement of road/street at village Rehana Pinda Choi UC Rehana
42) Pavement of roads/streets at Mohallah Chitri and Kanat
43) Construction of road a GY Zareen House
44) Pavement of roads/steets at village Koaka Dinga
45) Pavement of road/street at Pind Hashim Khan
46) Construction of road/street at Mohallah Munsafabad
47) Construction of Serai Saleh Maira road
48) Construction of Tanki Ali Khan
49) Construction of road/street at Mirpur UC Pandak
50) Construction of road/steet at Soka Pandak
998
(OG)
150889-Pavement of roads and streets for UC Saray Saleh, Shah Maqsood, Rehana, Ali Khan, Darwesh, Pind Hasim Khan, UC Sourth and Pandak of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 300 240.568 89.431 89.431 89.431 33.73 274.298 0 100% 91%
March - 2019
48 units (PCC/BT) - earth work, sub base in progress.
No Image
1) Pavement of road/street at village Gheba
2) Construction of road at Shah Maqsood
3) Construction of road/street at Thanda Choa UC Shah Maqsood
4) Pavement of road/streets a village Kholian Kalawan Mohara
5) Construction of road Shah Maqsood Maira to Bandi Sher Khan road UC Shah Maqsood
6) Pavement of road/street at village Akhoon Bandi and Mohallah Toheed Abad
7) Pavement of road/street at village Nikah Pah
8) Pavement of street at village Mohari No.1 UC Shah Maqsood
9) Pavement of road N/H of Master Ashiq Lora Chowk
10) Pavement of roads/street at village Mohari No.2 UC Shah Maqsood
11) Construction of road from Batkh to Mohalla Jalsi
12) Construction of road Soka Changi Bandi UC Sarai Saleh
13) Construction ofroad Saida Abad Sarai Saleh
14) Pavement of street at Mohallah Lehanda
15) Construction of raod at Ghar
16) Pavement of street at Mohallah Gul Bahaar Colony Jandran and Khan Bahadar UC Serai Saleh
17) Pavement of street at Tatreela Ghar
18) Pavement of road/street at Sarai Saleh Maira UC Serai Saleh
19) Pavement of roads/street at Sameer Ayub Colony Sarai Saleh UC Sarai Saleh
20) Construction of road/streets at village Moonan
21) Construction of road/street at village Mohara and Faisal Colony
22) Construction of road/street at Manzoor Colony Nai Abadi and Yasir Colony UC Ali Khan
23) Construction of road/street at Soka Nazir Abad and Maira Ali Khan UC Ali Khan
24) Construction of road/strets at village Muradabad UC Ali Khan
25) Construction of road/street at village Shah Muhammad and Mohallah Tanki UC Ali Khan
26) Construction of road/street at village Kahal UC Ali Khan
27) Construction of main road Pandak
28) Construction of Mairan Ali Khan road
29) Construction of bridge at Pandak Soka UC Pandak
30) Construction of road/streets at Talokar Dheri UC Pandak
31) Construction of road/streets at Gher Khan Maira
32) Construction of road/street at Soka Pandak UC Pandak
33) Pavement of roads/street village Durrnaian and Jamia
34) Pavement of roads/sreet village Nurdi Mohallah Shamali Mohara
35) Pavement fo roads/streets at Mohallah Dharri UC Rehana
36) Pavement of raod/street Kotha Pir Kot
37) Pavement of roads/street at Dolni
38) Pavement of road/street at village Chapra and Pir Kot Maira
39) Pavement of road/street at village Pind Jamal Khan and Kamal Pur
40) Construction of Maira Pandak road
41) Pavement of road/street at village Rehana Pinda Choi UC Rehana
42) Pavement of roads/streets at Mohallah Chitri and Kanat
43) Construction of road a GY Zareen House
44) Pavement of roads/steets at village Koaka Dinga
45) Pavement of road/street at Pind Hashim Khan
46) Construction of road/street at Mohallah Munsafabad
47) Construction of Serai Saleh Maira road
48) Construction of Tanki Ali Khan
49) Construction of road/street at Mirpur UC Pandak
50) Construction of road/steet at Soka Pandak
998
(OG)
150889-Pavement of roads and streets for UC Saray Saleh, Shah Maqsood, Rehana, Ali Khan, Darwesh, Pind Hasim Khan, UC Sourth and Pandak of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 300 240.568 89.431 89.431 89.431 28.419 268.987 0 100% 90%
February - 2019
48 units (PCC/BT) - earth work, sub base in progress.
No Image
1) Pavement of road/street at village Gheba
2) Construction of road at Shah Maqsood
3) Construction of road/street at Thanda Choa UC Shah Maqsood
4) Pavement of road/streets a village Kholian Kalawan Mohara
5) Construction of road Shah Maqsood Maira to Bandi Sher Khan road UC Shah Maqsood
6) Pavement of road/street at village Akhoon Bandi and Mohallah Toheed Abad
7) Pavement of road/street at village Nikah Pah
8) Pavement of street at village Mohari No.1 UC Shah Maqsood
9) Pavement of road N/H of Master Ashiq Lora Chowk
10) Pavement of roads/street at village Mohari No.2 UC Shah Maqsood
11) Construction of road from Batkh to Mohalla Jalsi
12) Construction of road Soka Changi Bandi UC Sarai Saleh
13) Construction ofroad Saida Abad Sarai Saleh
14) Pavement of street at Mohallah Lehanda
15) Construction of raod at Ghar
16) Pavement of street at Mohallah Gul Bahaar Colony Jandran and Khan Bahadar UC Serai Saleh
17) Pavement of street at Tatreela Ghar
18) Pavement of road/street at Sarai Saleh Maira UC Serai Saleh
19) Pavement of roads/street at Sameer Ayub Colony Sarai Saleh UC Sarai Saleh
20) Construction of road/streets at village Moonan
21) Construction of road/street at village Mohara and Faisal Colony
22) Construction of road/street at Manzoor Colony Nai Abadi and Yasir Colony UC Ali Khan
23) Construction of road/street at Soka Nazir Abad and Maira Ali Khan UC Ali Khan
24) Construction of road/strets at village Muradabad UC Ali Khan
25) Construction of road/street at village Shah Muhammad and Mohallah Tanki UC Ali Khan
26) Construction of road/street at village Kahal UC Ali Khan
27) Construction of main road Pandak
28) Construction of Mairan Ali Khan road
29) Construction of bridge at Pandak Soka UC Pandak
30) Construction of road/streets at Talokar Dheri UC Pandak
31) Construction of road/streets at Gher Khan Maira
32) Construction of road/street at Soka Pandak UC Pandak
33) Pavement of roads/street village Durrnaian and Jamia
34) Pavement of roads/sreet village Nurdi Mohallah Shamali Mohara
35) Pavement fo roads/streets at Mohallah Dharri UC Rehana
36) Pavement of raod/street Kotha Pir Kot
37) Pavement of roads/street at Dolni
38) Pavement of road/street at village Chapra and Pir Kot Maira
39) Pavement of road/street at village Pind Jamal Khan and Kamal Pur
40) Construction of Maira Pandak road
41) Pavement of road/street at village Rehana Pinda Choi UC Rehana
42) Pavement of roads/streets at Mohallah Chitri and Kanat
43) Construction of road a GY Zareen House
44) Pavement of roads/steets at village Koaka Dinga
45) Pavement of road/street at Pind Hashim Khan
46) Construction of road/street at Mohallah Munsafabad
47) Construction of Serai Saleh Maira road
48) Construction of Tanki Ali Khan
49) Construction of road/street at Mirpur UC Pandak
50) Construction of road/steet at Soka Pandak
998
(OG)
150889-Pavement of roads and streets for UC Saray Saleh, Shah Maqsood, Rehana, Ali Khan, Darwesh, Pind Hasim Khan, UC Sourth and Pandak of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 300 240.568 89.431 89.431 49.716 24.166 264.734 0 100% 88%
January - 2019
48 units (PCC/BT) - earth work, sub base in progress.
No Image
1) Pavement of road/street at village Gheba
2) Construction of road at Shah Maqsood
3) Construction of road/street at Thanda Choa UC Shah Maqsood
4) Pavement of road/streets a village Kholian Kalawan Mohara
5) Construction of road Shah Maqsood Maira to Bandi Sher Khan road UC Shah Maqsood
6) Pavement of road/street at village Akhoon Bandi and Mohallah Toheed Abad
7) Pavement of road/street at village Nikah Pah
8) Pavement of street at village Mohari No.1 UC Shah Maqsood
9) Pavement of road N/H of Master Ashiq Lora Chowk
10) Pavement of roads/street at village Mohari No.2 UC Shah Maqsood
11) Construction of road from Batkh to Mohalla Jalsi
12) Construction of road Soka Changi Bandi UC Sarai Saleh
13) Construction ofroad Saida Abad Sarai Saleh
14) Pavement of street at Mohallah Lehanda
15) Construction of raod at Ghar
16) Pavement of street at Mohallah Gul Bahaar Colony Jandran and Khan Bahadar UC Serai Saleh
17) Pavement of street at Tatreela Ghar
18) Pavement of road/street at Sarai Saleh Maira UC Serai Saleh
19) Pavement of roads/street at Sameer Ayub Colony Sarai Saleh UC Sarai Saleh
20) Construction of road/streets at village Moonan
21) Construction of road/street at village Mohara and Faisal Colony
22) Construction of road/street at Manzoor Colony Nai Abadi and Yasir Colony UC Ali Khan
23) Construction of road/street at Soka Nazir Abad and Maira Ali Khan UC Ali Khan
24) Construction of road/strets at village Muradabad UC Ali Khan
25) Construction of road/street at village Shah Muhammad and Mohallah Tanki UC Ali Khan
26) Construction of road/street at village Kahal UC Ali Khan
27) Construction of main road Pandak
28) Construction of Mairan Ali Khan road
29) Construction of bridge at Pandak Soka UC Pandak
30) Construction of road/streets at Talokar Dheri UC Pandak
31) Construction of road/streets at Gher Khan Maira
32) Construction of road/street at Soka Pandak UC Pandak
33) Pavement of roads/street village Durrnaian and Jamia
34) Pavement of roads/sreet village Nurdi Mohallah Shamali Mohara
35) Pavement fo roads/streets at Mohallah Dharri UC Rehana
36) Pavement of raod/street Kotha Pir Kot
37) Pavement of roads/street at Dolni
38) Pavement of road/street at village Chapra and Pir Kot Maira
39) Pavement of road/street at village Pind Jamal Khan and Kamal Pur
40) Construction of Maira Pandak road
41) Pavement of road/street at village Rehana Pinda Choi UC Rehana
42) Pavement of roads/streets at Mohallah Chitri and Kanat
43) Construction of road a GY Zareen House
44) Pavement of roads/steets at village Koaka Dinga
45) Pavement of road/street at Pind Hashim Khan
46) Construction of road/street at Mohallah Munsafabad
47) Construction of Serai Saleh Maira road
48) Construction of Tanki Ali Khan
49) Construction of road/street at Mirpur UC Pandak
50) Construction of road/steet at Soka Pandak
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
30-11--1 30-11--1 - 30-11--1 - 658.831 0 100 71 71 67.851 0 0
May - 2021
Finishing in progress.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
30-11--1 30-11--1 - 30-11--1 - 658.831 0 100 100 100 58.776 0 0
April - 2021
Finishing in progress.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 658.831 467.282 100 100 50 18.905 486.187 91.549 86% 74%
December - 2020
Finishing in progress.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 658.831 467.282 100 100 50 18.905 486.187 91.549 86% 74%
December - 2020
Finishing in progress.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 658.831 467.282 100 100 25 18.905 486.187 91.549 86% 74%
October - 2020
Finishing in progress.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 658.831 467.282 100 100 25 16.107 483.389 91.549 86% 73%
September - 2020
Pack-I Joinery, Flooring, Electrification in progress. Tube Well completed. Pack-III completed & occupied. Pack-II completed except remaining portion.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 658.831 467.282 100 100 25 16.107 483.389 91.549 86% 73%
August - 2020
Pack-I Joinery, Flooring, Electrification in progress. Tube Well completed. Pack-III completed & occupied. Pack-II completed except remaining portion.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 658.831 467.282 100 0 0 0 467.282 91.549 86% 71%
July - 2020
Pack-II completed except remaining portion. OHT in
No Image
Peshawar (Package-III (a) Main Building (b) T
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 658.831 0 100 75 75 32.215 0 0
March - 2021
Finishing in progress.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 658.831 0 100 75 75 32.215 0 0
February - 2021
Finishing in progress.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 658.831 467.282 100 50 50 18.905 486.187 91.549 86% 74%
January - 2021
Finishing in progress.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
Pages : 1