Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2019, February - 2020, February - 2021, February - 2018, March - 2019, March - 2020, March - 2021, March - 2018, April - 2019, April - 2020, April - 2021, April - 2018, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
994
(OG)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 545.879 20 10 9.575 9.575 9.575 29.575 515.879 5% 5%
December - 2019
Work order issued to contractor. Contractor mobilized at site. Joint survey completed.
No Image
994
(OG)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 545.879 20 10 10 2.5 2.5 22.5 515.879 5% 4%
November - 2019
Work order issued to contractor. Contractor mobilized at site. Joint survey completed.
No Image
994
(OG)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 545.879 20 10 10 2.5 2.5 22.5 515.879 5% 4%
October - 2019
Work order issued to contractor. Contractor mobilized at site. Joint survey completed.
No Image
994
(OG)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 545.879 20 10 10 2.5 2.5 22.5 515.879 5% 4%
September - 2019
Work order issued to contractor. Contractor mobilized at site. Joint survey in progress.
No Image
994
(OG)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 545.879 20 10 10 2.5 2.5 22.5 515.879 5% 4%
August - 2019
Work order issued to contractor. Contractor mobilized at site. Joint survey in progress.
No Image
994
(OG)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 545.879 20 10 9.575 9.575 9.575 29.575 515.879 5% 5%
May - 2020
Work order issued to contractor. Contractor mobilized at site. Joint survey completed.
No Image
994
(OG)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 545.879 20 10 9.575 9.575 9.575 29.575 515.879 5% 5%
April - 2020
Work order issued to contractor. Contractor mobilized at site. Joint survey completed.
No Image
994
(OG)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 545.879 20 10 9.575 9.575 9.575 29.575 515.879 5% 5%
March - 2020
Work order issued to contractor. Contractor mobilized at site. Joint survey completed.
No Image
994
(OG)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 545.879 20 10 9.575 9.575 9.575 29.575 515.879 5% 5%
February - 2020
Work order issued to contractor. Contractor mobilized at site. Joint survey completed.
No Image
994
(OG)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 545.879 20 10 9.575 9.575 9.575 29.575 515.879 5% 5%
January - 2020
Work order issued to contractor. Contractor mobilized at site. Joint survey completed.
No Image
994
(OG)
150867-Construction / improvement / rehabilitation of Karwala Road District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 60 52.315 4.828 4.828 3.621 0 52.315 2.857 95% 87%
December - 2018
Length 6 Km (width 12 ft) - 6 BT completed. Structure work in progress.
No Image
6 Km, Haripur
994
(OG)
150867-Construction / improvement / rehabilitation of Karwala Road District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 60 52.315 4.828 4.828 3.621 0 52.315 2.857 95% 87%
November - 2018
Length 6 Km (width 12 ft) - 6 BT completed. Structure work in progress. Tender opening on 26/9/2018.
No Image
6 Km, Haripur
994
(OG)
150867-Construction / improvement / rehabilitation of Karwala Road District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 60 52.315 4.828 4.828 3.621 0 52.315 2.857 95% 87%
November - 2018
Length 6 Km (width 12 ft) - 6 BT completed. Structure work in progress. Tender opening on 26/9/2018.
No Image
6 Km, Haripur
994
(OG)
150867-Construction / improvement / rehabilitation of Karwala Road District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 60 52.315 4.828 4.828 4.828 4.828 57.143 2.857 95% 95%
April - 2019
Length 6 Km (width 12 ft) - 6 BT completed. Structure work in progress. Demand Rs.2.857 m over TS.
No Image
6 Km, Haripur
994
(OG)
150867-Construction / improvement / rehabilitation of Karwala Road District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 60 52.315 4.828 4.828 4.828 4.828 57.143 2.857 95% 95%
March - 2019
Length 6 Km (width 12 ft) - 6 BT completed. Structure work in progress. Demand Rs.2.857 m over TS.
No Image
6 Km, Haripur
994
(OG)
150867-Construction / improvement / rehabilitation of Karwala Road District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 60 52.315 4.828 4.828 4.828 4.828 57.143 2.857 95% 95%
March - 2019
Length 6 Km (width 12 ft) - 6 BT completed. Structure work in progress. Demand Rs.2.857 m over TS.
No Image
6 Km, Haripur
994
(OG)
150867-Construction / improvement / rehabilitation of Karwala Road District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 60 52.315 4.828 4.828 4.828 3.621 55.936 2.857 95% 93%
February - 2019
Length 6 Km (width 12 ft) - 6 BT completed. Structure work in progress. Demand 2.857 m over TS
No Image
6 Km, Haripur
994
(OG)
150867-Construction / improvement / rehabilitation of Karwala Road District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 60 52.315 4.828 4.828 3.621 3.621 55.936 2.857 95% 93%
January - 2019
Length 6 Km (width 12 ft) - 6 BT completed. Structure work in progress.
No Image
6 Km, Haripur
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
14-01-16 30-06-18 - 28-08-15 - 40 39.414 12.261 5.288 2.223 2.222 41.636 0 100% 100%
December - 2017
Completed (6.31 Km).
No Image
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
14-01-16 30-06-18 - 28-08-15 - 40 39.414 12.261 12.261 6.131 2.222 41.636 0 100% 100%
September - 2017
Completed (5 units).
No Image
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
14-01-16 30-06-18 - 28-08-15 - 40 39.414 12.261 12.261 6.131 2.222 41.636 0 100% 100%
August - 2017
Completed (5 units).
No Image
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
14-01-16 30-06-18 - 28-08-15 - 40 39.414 12.261 12.261 4.353 0 39.414 0 100% 99%
July - 2017
Completed (5 units).
No Image
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 40 39.414 12.261 5.288 2.223 2.222 41.636 0 100% 100%
November - 2017
Length 6.31 km- Completed
No Image
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 40 39.414 12.261 12.261 5.28 2.222 41.636 0 100% 100%
October - 2017
Completed (5 units).
No Image
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 40 39.414 12.261 2.223 2.223 2.223 41.637 0 100% 100%
June - 2018
Completed (6.31 Km/7 units BT).
No Image
1) Urban-6 Mir Ahmad Khel (3500 rft)
2) UC Muhammadzai Ublan Camp to Naway Kalay (3000 rft)
3) Maway Kaly to Lal Mela Ghari (3000 rft)
4) Muhammadzai to Mian Ghari (3000 rft)
5) Kaghazai to Ambar Banda (3000 rft)
6) Nasrat Khel (2500 rft)
7) Police ChowkitoShahpur road (2500 rft)
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 40 39.414 12.261 5.288 5.288 2.222 41.636 0 100% 100%
May - 2018
Completed (6.31 Km/7 units BT).
No Image
1) Urban-6 Mir Ahmad Khel (3500 rft)
2) UC Muhammadzai Ublan Camp to Naway Kalay (3000 rft)
3) Maway Kaly to Lal Mela Ghari (3000 rft)
4) Muhammadzai to Mian Ghari (3000 rft)
5) Kaghazai to Ambar Banda (3000 rft)
6) Nasrat Khel (2500 rft)
7) Police ChowkitoShahpur road (2500 rft)
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 40 39.414 12.261 5.288 5.288 2.222 41.636 0 100% 100%
April - 2018
Completed (6.31 Km/7 units BT).
No Image
1) Urban-6 Mir Ahmad Khel (3500 rft)
2) UC Muhammadzai Ublan Camp to Naway Kalay (3000 rft)
3) Maway Kaly to Lal Mela Ghari (3000 rft)
4) Muhammadzai to Mian Ghari (3000 rft)
5) Kaghazai to Ambar Banda (3000 rft)
6) Nasrat Khel (2500 rft)
7) Police ChowkitoShahpur road (2500 rft)
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 40 39.414 12.261 5.288 2.223 2.222 41.636 0 100% 100%
March - 2018
Completed (6.31 Km). (all 7 units BT).
No Image
1) Urban-6 Mir Ahmad Khel (3500 rft)
2) UC Muhammadzai Ublan Camp to Naway Kalay (3000 rft)
3) Maway Kaly to Lal Mela Ghari (3000 rft)
4) Muhammadzai to Mian Ghari (3000 rft)
5) Kaghazai to Ambar Banda (3000 rft)
6) Nasrat Khel (2500 rft)
7) Police ChowkitoShahpur road (2500 rft)
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 40 39.414 12.261 5.288 2.223 2.222 41.636 0 100% 100%
February - 2018
Completed (6.31 Km). (all 7 units BT )
No Image
1) Urban-6 Mir Ahmad Khel (3500 rft)
2) UC Muhammadzai Ublan Camp to Naway Kalay (3000 rft)
3) Maway Kaly to Lal Mela Ghari (3000 rft)
4) Muhammadzai to Mian Ghari (3000 rft)
5) Kaghazai to Ambar Banda (3000 rft)
6) Nasrat Khel (2500 rft)
7) Police ChowkitoShahpur road (2500 rft)
994
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 40 39.414 12.261 5.288 2.223 2.222 41.636 0 100% 100%
January - 2018
Completed (6.31 Km).
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
December - 2020
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
December - 2020
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
October - 2020
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
September - 2020
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
August - 2020
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0 0 0 0 0 - -
July - 2020
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
May - 2021
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
April - 2021
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
March - 2021
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
February - 2021
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
January - 2021
No Image
Pages : 1