Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
985 (OG) |
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 1.25 | 10 | 9.5 | 4.501 | 4.5 | 5.75 | 138.75 | 8% |
4% December - 2018 |
Spervisiory consultant selected (Spectra Consultants).
Earth work in progress. |
No Image |
Abbottabad | |||||||||||||||||||
985 (OG) |
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 1.25 | 10 | 9.5 | 4.501 | 0 | 1.25 | 138.75 | 8% |
1% November - 2018 |
Spervisiory consultant selected (Spectra Consultants). Work stopped. |
No Image |
Abbottabad | |||||||||||||||||||
985 (OG) |
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 1.25 | 10 | 9.5 | 4.501 | 0 | 1.25 | 138.75 | 8% |
1% November - 2018 |
Spervisiory consultant selected (Spectra Consultants). Work stopped. |
No Image |
Abbottabad | |||||||||||||||||||
985 (OG) |
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 1.25 | 10 | 9.5 | 9.5 | 7.06 | 8.31 | 138.75 | 8% |
6% April - 2019 |
Spervisiory consultant selected (Spectra Consultants). Earth work in progress. |
No Image |
Abbottabad | |||||||||||||||||||
985 (OG) |
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 1.25 | 10 | 9.5 | 7.0005 | 4.5 | 5.75 | 138.75 | 8% |
4% March - 2019 |
Spervisiory consultant selected (Spectra Consultants). Earth work in progress. |
No Image |
Abbottabad | |||||||||||||||||||
985 (OG) |
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 1.25 | 10 | 9.5 | 7.0005 | 4.5 | 5.75 | 138.75 | 8% |
4% March - 2019 |
Spervisiory consultant selected (Spectra Consultants). Earth work in progress. |
No Image |
Abbottabad | |||||||||||||||||||
985 (OG) |
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 1.25 | 10 | 9.5 | 7.0005 | 4.5 | 5.75 | 138.75 | 8% |
4% February - 2019 |
Spervisiory consultant selected (Spectra Consultants). Earth work in progress. |
No Image |
Abbottabad | |||||||||||||||||||
985 (OG) |
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 1.25 | 10 | 9.5 | 4.501 | 4.5 | 5.75 | 138.75 | 8% |
4% January - 2019 |
Spervisiory consultant selected (Spectra Consultants).
Earth work in progress. |
No Image |
Abbottabad | |||||||||||||||||||
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
Scope of work awaited. |
No Image |
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
Scope of work awaited. |
No Image |
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
Scope of work awaited. |
No Image |
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
Scope of work awaited. |
No Image |
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 230 | 0 | 100 | 0 | 0 | 0 | 0 | 130 | 43% |
- May - 2021 |
Scope of work awaited.
DDWP held on 29-03-21
AA. Awiated |
No Image |
1 GPGC Khar
2 GDC Nawagai
3 GCMS Khar | |||||||||||||||||||
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 230 | 0 | 100 | 0 | 0 | 0 | 0 | 130 | 43% |
- April - 2021 |
Scope of work awaited.
DDWP held on 29-03-21
AA. Awiated |
No Image |
1 GPGC Khar
2 GDC Nawagai
3 GCMS Khar | |||||||||||||||||||
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 230 | 0 | 100 | 0 | 0 | 0 | 0 | 130 | 43% |
- March - 2021 |
Scope of work awaited.
DDWP held on 29-03-21
AA. Awiated |
No Image |
1 GPGC Khar
2 GDC Nawagai
3 GCMS Khar | |||||||||||||||||||
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 230 | 0 | 100 | 100 | 0 | 0 | 0 | 130 | 43% |
- February - 2021 |
Scope of work awaited.
DDWP held on 29-03-21
AA. Awiated |
No Image |
1 GPGC Khar
2 GDC Nawagai
3 GCMS Khar | |||||||||||||||||||
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
Scope of work awaited. |
No Image |
1 GPGC Khar
2 GDC Nawagai
3 GCMS Khar | |||||||||||||||||||
985 (OG) |
170523-F/S & Construction of Circular Bypass Road, Bannu (64.90 Km) |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 57.5 | 60 | 57.45 | 57.45 | 57.45 | 114.95 | 6840.105 | 2% |
2% December - 2019 |
Work in progresss for Package-1 and 2.
Package II & III not starting due to contraint funds. |
No Image |
985 (OG) |
170523-F/S & Construction of Circular Bypass Road, Bannu (64.90 Km) |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 57.5 | 60 | 60 | 15 | 15 | 72.5 | 6840.105 | 2% |
1% November - 2019 |
Work in progresss for Package-1 and 2.
Package II & III not starting due to contraint funds. |
No Image |
985 (OG) |
170523-F/S & Construction of Circular Bypass Road, Bannu (64.90 Km) |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 57.5 | 60 | 60 | 15 | 15 | 72.5 | 6840.105 | 2% |
1% October - 2019 |
Work in progresss for Package-1 and 2.
Package II & III not starting due to contraint funds. |
No Image |
985 (OG) |
170523-F/S & Construction of Circular Bypass Road, Bannu (64.90 Km) |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 57.5 | 60 | 60 | 15 | 15 | 72.5 | 6840.105 | 2% |
1% September - 2019 |
Work in progresss for Package-1 and 2.
Package II & III not starting due to contraint funds. |
No Image |
985 (OG) |
170523-F/S & Construction of Circular Bypass Road, Bannu (64.90 Km) |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 57.5 | 60 | 60 | 15 | 15 | 72.5 | 6840.105 | 2% |
1% August - 2019 |
Work in progresss for Package-1 and 2.
Package II & III not starting due to contraint funds. |
No Image |
985 (OG) |
170523-F/S & Construction of Circular Bypass Road, Bannu (64.90 Km) |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 57.5 | 60 | 157.45 | 157.45 | 157.45 | 214.95 | 6840.105 | 2% |
3% May - 2020 |
Pack-1 (10 Km) - in progress. Pack-2 (10 Km) and Pack-7 (Bridges) - not starting due to contraints of funds. |
No Image |
985 (OG) |
170523-F/S & Construction of Circular Bypass Road, Bannu (64.90 Km) |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 57.5 | 60 | 157.45 | 157.45 | 157.45 | 214.95 | 6840.105 | 2% |
3% April - 2020 |
Pack-1 (10 Km) - in progress. Pack-2 (10 Km) and Pack-7 (Bridges) - not starting due to contraints of funds. |
No Image |
985 (OG) |
170523-F/S & Construction of Circular Bypass Road, Bannu (64.90 Km) |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 57.5 | 60 | 157.45 | 157.45 | 157.45 | 214.95 | 6840.105 | 2% |
3% March - 2020 |
Pack-1 (10 Km) - in progress. Pack-2 (10 Km) and Pack-7 (Bridges) - not starting due to contraints of funds. |
No Image |
985 (OG) |
170523-F/S & Construction of Circular Bypass Road, Bannu (64.90 Km) |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 57.5 | 60 | 157.45 | 157.45 | 157.45 | 214.95 | 6840.105 | 2% |
3% February - 2020 |
Pack-1 (10 Km) - in progress. Pack-2 (10 Km) and Pack-7 (Bridges) - not starting due to contraints of funds. |
No Image |
985 (OG) |
170523-F/S & Construction of Circular Bypass Road, Bannu (64.90 Km) |
Bannu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6957.605 | 57.5 | 60 | 57.45 | 57.45 | 57.45 | 114.95 | 6840.105 | 2% |
2% January - 2020 |
Work in progresss for Package-1 and 2.
Package II & III not starting due to contraint funds. |
No Image |
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 100 | 0 | 0 | 0 | 0 | 50 | 67% |
- May - 2021 |
Scope of work awaited.
DDWP held on 29-03-21
AA. Awiated |
No Image |
1. GDC Jandola
2. GGDC Jandola | |||||||||||||||||||
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 100 | 0 | 0 | 0 | 0 | 50 | 67% |
- April - 2021 |
Scope of work awaited.
DDWP held on 29-03-21
AA. Awiated |
No Image |
1. GDC Jandola
2. GGDC Jandola | |||||||||||||||||||
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 100 | 0 | 0 | 0 | 0 | 50 | 67% |
- March - 2021 |
Scope of work awaited.
DDWP held on 29-03-21
AA. Awiated |
No Image |
1. GDC Jandola
2. GGDC Jandola | |||||||||||||||||||
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 100 | 0 | 0 | 0 | 0 | 50 | 67% |
- February - 2021 |
Scope of work awaited.
DDWP held on 29-03-21
AA. Awiated |
No Image |
1. GDC Jandola
2. GGDC Jandola | |||||||||||||||||||
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
20-12-15 | - | - | 28-01-15 | - | 390.218 | 231.545 | 40 | 34.2 | 24.2 | 24.2 | 255.745 | 118.673 | 70% |
66% December - 2017 |
Length 4.225 Km - 3.2 Km both lane BT completed. |
No Image |
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
20-12-15 | - | - | 28-01-15 | - | 390.218 | 231.545 | 40 | 40 | 14.2 | 14.2 | 245.745 | 118.673 | 70% |
63% September - 2017 |
Length 4.225 Km - 3 Km single lane completed. |
No Image |
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
20-12-15 | - | - | 28-01-15 | - | 390.218 | 231.545 | 40 | 40 | 14.2 | 9.518 | 241.063 | 118.673 | 70% |
62% August - 2017 |
Length 4.225 Km - 1 Km asphalt completed. |
No Image |
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
20-12-15 | - | - | 28-01-15 | - | 390.218 | 231.545 | 40 | 40 | 14.2 | 0 | 231.545 | 118.673 | 70% |
59% July - 2017 |
Length 4.225 Km - 1 Km asphalt completed. |
No Image |
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 231.545 | 40 | 34.2 | 24.2 | 24.2 | 255.745 | 118.673 | 70% |
66% November - 2017 |
Length 4.225 Km - 3.2 Km both lane BT completed. |
No Image |
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 231.545 | 40 | 40 | 24.2 | 24.2 | 255.745 | 118.673 | 70% |
66% October - 2017 |
Length 4.225 Km - 3.2 Km both lane BT completed. |
No Image |
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 231.545 | 40 | 47.263 | 47.263 | 47.263 | 278.808 | 118.673 | 70% |
71% June - 2018 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 231.545 | 40 | 47.263 | 47.263 | 47.263 | 278.808 | 118.673 | 70% |
71% May - 2018 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 231.545 | 40 | 47.263 | 47.263 | 47.263 | 278.808 | 118.673 | 70% |
71% April - 2018 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 231.545 | 40 | 47.263 | 47.263 | 47.263 | 278.808 | 118.673 | 70% |
71% March - 2018 |
Length 4.225 Km ( W- 40ft)- 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 231.545 | 40 | 41.883 | 41.883 | 41.883 | 273.428 | 118.673 | 70% |
70% February - 2018 |
Length 4.225 Km ( W- 40ft) Width - 3.2 Km both lane BT completed. |
ADP's Images |
Karak | |||||||||||||||||||
985 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km). |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 231.545 | 40 | 41.883 | 41.883 | 29.2 | 260.745 | 118.673 | 70% |
67% January - 2018 |
Length 4.225 Km - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1700 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1700 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1700 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1700 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1700 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1700 | 0 | 100 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
985 (New) |
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1700 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |