Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2019, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2019, December - 2020, December - 2017, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
984
(OG)
160628-F/S, Design & Construction & Supervision of Bypass road from Ayub Bridge Havellian (N-35) to Dhmatour at Abbottabad (18.325 Km).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1470.041 4.6 140 140 100 100 104.6 1325.441 10% 7%
December - 2018
LOA issued to FWO. Contractor mobilized. Revised DCE under preprataion.
No Image
Abbottabad
984
(OG)
160628-F/S, Design & Construction & Supervision of Bypass road from Ayub Bridge Havellian (N-35) to Dhmatour at Abbottabad (18.325 Km).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1470.041 4.6 140 140 100 100 104.6 1325.441 10% 7%
November - 2018
LOA issued to FWO. Contractor mobilized.
No Image
Abbottabad
984
(OG)
160628-F/S, Design & Construction & Supervision of Bypass road from Ayub Bridge Havellian (N-35) to Dhmatour at Abbottabad (18.325 Km).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1470.041 4.6 140 140 100 100 104.6 1325.441 10% 7%
November - 2018
LOA issued to FWO. Contractor mobilized.
No Image
Abbottabad
984
(OG)
160628-F/S, Design & Construction & Supervision of Bypass road from Ayub Bridge Havellian (N-35) to Dhmatour at Abbottabad (18.325 Km).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1470.041 4.6 140 390 350 180 184.6 1325.441 10% 13%
April - 2019
12 km earh work completed.
No Image
Abbottabad
984
(OG)
160628-F/S, Design & Construction & Supervision of Bypass road from Ayub Bridge Havellian (N-35) to Dhmatour at Abbottabad (18.325 Km).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1470.041 4.6 140 390 350 180 184.6 1325.441 10% 13%
March - 2019
3 Km earth work completed.
No Image
Abbottabad
984
(OG)
160628-F/S, Design & Construction & Supervision of Bypass road from Ayub Bridge Havellian (N-35) to Dhmatour at Abbottabad (18.325 Km).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1470.041 4.6 140 390 350 180 184.6 1325.441 10% 13%
March - 2019
3 Km earth work completed.
No Image
Abbottabad
984
(OG)
160628-F/S, Design & Construction & Supervision of Bypass road from Ayub Bridge Havellian (N-35) to Dhmatour at Abbottabad (18.325 Km).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1470.041 4.6 140 390 350 180 184.6 1325.441 10% 13%
February - 2019
3 Km earth work completed.
No Image
Abbottabad
984
(OG)
160628-F/S, Design & Construction & Supervision of Bypass road from Ayub Bridge Havellian (N-35) to Dhmatour at Abbottabad (18.325 Km).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1470.041 4.6 140 140 100 100 104.6 1325.441 10% 7%
January - 2019
3 km earth work complted.
No Image
Abbottabad
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
19-06-15 30-06-18 - 28-01-15 - 84 67.779 8.721 8.721 6.541 6.541 74.32 7.5 91% 88%
December - 2017
Length 6 Km - 6 Km BT completed. Structure work in progress.
No Image
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
19-06-15 30-06-18 - 28-01-15 - 84 67.779 8.721 8.721 4.361 3.096 70.875 7.5 91% 84%
September - 2017
Length 6 Km - 1.5 Km BT completed. Earth work, sub-base, WBM completed. TST, structure work in progress.
No Image
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
19-06-15 30-06-18 - 28-01-15 - 84 67.779 8.721 8.721 4.361 3.095 70.874 7.5 91% 84%
August - 2017
Length 6 Km - 1.5 Km BT completed. Earth work, sub-base, WBM completed. TST, structure work in progress.
No Image
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
19-06-15 30-06-18 - 28-01-15 - 84 67.779 8.721 8.721 3.096 0 67.779 7.5 91% 81%
July - 2017
Length 6 Km - 1.5 Km BT completed. Earth work, sub-base, WBM completed. TST, structure work in progress.
No Image
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 84 67.779 8.721 8.721 6.541 4.084 71.863 7.5 91% 86%
November - 2017
Length 6 Km - 6 Km BT completed. Work order issued for balance work.
No Image
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 84 67.779 8.721 8.721 6.521 4.084 71.863 7.5 91% 86%
October - 2017
Length 6 Km - 6 Km BT completed. Financial bids opened and under approval.
No Image
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 84 67.779 6.541 6.541 8.721 6.541 74.32 9.68 88% 88%
June - 2018
Length 6 Km (width 20 ft) - 6 Km BT completed. Structure work in progress.
No Image
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 84 67.779 8.721 8.721 8.721 8.721 76.5 7.5 91% 91%
May - 2018
Length 6 Km (width 20 ft) - 6 Km BT completed. Structure work in progress.
No Image
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 84 67.779 8.721 8.721 8.721 8.721 76.5 7.5 91% 91%
April - 2018
Length 6 Km (width 20 ft) - 6 Km BT completed. Structure work in progress.
No Image
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 84 67.779 8.721 8.721 8.721 8.721 76.5 7.5 91% 91%
March - 2018
Length 6 Km (width -20 ft) - 6 Km BT completed. Structure work in progress.
No Image
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 84 67.779 8.721 8.721 6.541 6.541 74.32 7.5 91% 88%
February - 2018
Length 6 Km (width -20 ft) - 6 Km BT completed. Structure work in progress.
No Image
PK-40, Karak
984
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 84 67.779 8.721 8.721 6.541 6.541 74.32 7.5 91% 88%
January - 2018
Length 6 Km - 6 Km BT completed. Structure work in progress.
No Image
PK-40 Karak
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
December - 2020
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
December - 2020
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
October - 2020
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
September - 2020
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
August - 2020
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 0 0 0 0 0 -
July - 2020
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
May - 2021
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
April - 2021
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
March - 2021
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
February - 2021
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
January - 2021
No Image
984
(New)
190593-Const: road Kacha a)Planr Basi Khel b)Seri Kandao-Gigiani Basi Khel,c)Mori Basi Khel,d)Shatal-Karizan Saidan,e)Pakbund-Mori Nusrat Khel,f)Cherah Basi Khel,g)Mera Mada Khel-Qabristan,h)Guizer paty-TT Madakhel,i)Shahbat Madrasa,Mera Mada Khel, Torghar.
Tor Ghar
30-11--1 30-11--1 - 30-11--1 Line Deptt 90 0 5 5 0 0 0 0 - -
December - 2019
DCE for Rs. 208 M submitted to P&D . PDWP on 09/1/20.
No Image
984
(New)
190593-Const: road Kacha a)Planr Basi Khel b)Seri Kandao-Gigiani Basi Khel,c)Mori Basi Khel,d)Shatal-Karizan Saidan,e)Pakbund-Mori Nusrat Khel,f)Cherah Basi Khel,g)Mera Mada Khel-Qabristan,h)Guizer paty-TT Madakhel,i)Shahbat Madrasa,Mera Mada Khel, Torghar.
Tor Ghar
30-11--1 30-11--1 - 30-11--1 Line Deptt 90 0 5 5 0 0 0 0 - -
November - 2019
DCE for Rs. 208 M submitted to P&D .
No Image
984
(New)
190593-Const: road Kacha a)Planr Basi Khel b)Seri Kandao-Gigiani Basi Khel,c)Mori Basi Khel,d)Shatal-Karizan Saidan,e)Pakbund-Mori Nusrat Khel,f)Cherah Basi Khel,g)Mera Mada Khel-Qabristan,h)Guizer paty-TT Madakhel,i)Shahbat Madrasa,Mera Mada Khel, Torghar.
Tor Ghar
30-11--1 30-11--1 - 30-11--1 Line Deptt 90 0 5 5 0 0 0 0 - -
October - 2019
Dispute on b) and c) component.
No Image
984
(New)
190593-Const: road Kacha a)Planr Basi Khel b)Seri Kandao-Gigiani Basi Khel,c)Mori Basi Khel,d)Shatal-Karizan Saidan,e)Pakbund-Mori Nusrat Khel,f)Cherah Basi Khel,g)Mera Mada Khel-Qabristan,h)Guizer paty-TT Madakhel,i)Shahbat Madrasa,Mera Mada Khel, Torghar.
Tor Ghar
30-11--1 30-11--1 - 30-11--1 Line Deptt 90 0 5 5 0 0 0 0 - -
September - 2019
Dispute arrises on b) and c).
No Image
984
(New)
190593-Const: road Kacha a)Planr Basi Khel b)Seri Kandao-Gigiani Basi Khel,c)Mori Basi Khel,d)Shatal-Karizan Saidan,e)Pakbund-Mori Nusrat Khel,f)Cherah Basi Khel,g)Mera Mada Khel-Qabristan,h)Guizer paty-TT Madakhel,i)Shahbat Madrasa,Mera Mada Khel, Torghar.
Tor Ghar
30-11--1 30-11--1 - 30-11--1 Line Deptt 90 0 5 5 0 0 0 0 - -
August - 2019
DCE under preparation. Will be submitted within wereks days
No Image
984
(New)
190593-Const: road Kacha a)Planr Basi Khel b)Seri Kandao-Gigiani Basi Khel,c)Mori Basi Khel,d)Shatal-Karizan Saidan,e)Pakbund-Mori Nusrat Khel,f)Cherah Basi Khel,g)Mera Mada Khel-Qabristan,h)Guizer paty-TT Madakhel,i)Shahbat Madrasa,Mera Mada Khel, Torghar.
Tor Ghar
30-11--1 30-11--1 - 30-11--1 Line Deptt 217.53 0 5 5 0 0 0 212.53 2% -
May - 2020
work order issued for 9 sub uits
No Image
984
(New)
190593-Const: road Kacha a)Planr Basi Khel b)Seri Kandao-Gigiani Basi Khel,c)Mori Basi Khel,d)Shatal-Karizan Saidan,e)Pakbund-Mori Nusrat Khel,f)Cherah Basi Khel,g)Mera Mada Khel-Qabristan,h)Guizer paty-TT Madakhel,i)Shahbat Madrasa,Mera Mada Khel, Torghar.
Tor Ghar
30-11--1 30-11--1 - 30-11--1 Line Deptt 217.53 0 5 5 0 0 0 212.53 2% -
April - 2020
work order issued for 9 sub uits
No Image
984
(New)
190593-Const: road Kacha a)Planr Basi Khel b)Seri Kandao-Gigiani Basi Khel,c)Mori Basi Khel,d)Shatal-Karizan Saidan,e)Pakbund-Mori Nusrat Khel,f)Cherah Basi Khel,g)Mera Mada Khel-Qabristan,h)Guizer paty-TT Madakhel,i)Shahbat Madrasa,Mera Mada Khel, Torghar.
Tor Ghar
30-11--1 30-11--1 - 30-11--1 Line Deptt 217.53 0 5 5 0 0 0 212.53 2% -
March - 2020
work order issued for 9 sub uits
No Image
984
(New)
190593-Const: road Kacha a)Planr Basi Khel b)Seri Kandao-Gigiani Basi Khel,c)Mori Basi Khel,d)Shatal-Karizan Saidan,e)Pakbund-Mori Nusrat Khel,f)Cherah Basi Khel,g)Mera Mada Khel-Qabristan,h)Guizer paty-TT Madakhel,i)Shahbat Madrasa,Mera Mada Khel, Torghar.
Tor Ghar
30-11--1 30-11--1 - 30-11--1 Line Deptt 217.53 0 5 5 0 0 0 212.53 2% -
February - 2020
work order issued for 9 sub uits
No Image
984
(New)
190593-Const: road Kacha a)Planr Basi Khel b)Seri Kandao-Gigiani Basi Khel,c)Mori Basi Khel,d)Shatal-Karizan Saidan,e)Pakbund-Mori Nusrat Khel,f)Cherah Basi Khel,g)Mera Mada Khel-Qabristan,h)Guizer paty-TT Madakhel,i)Shahbat Madrasa,Mera Mada Khel, Torghar.
Tor Ghar
30-11--1 30-11--1 - 30-11--1 Line Deptt 217.53 0 5 5 0 0 0 212.53 2% -
January - 2020
\Procuremnet in Progress.
No Image