Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0.525 | 0 | 0 | 0 | 0 | 0.525 | 496.475 | - |
0% December - 2018 |
Abbottabad componenet - Handed over to KITE |
No Image |
Abbottabad | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0.525 | 0 | 0 | 0 | 0 | 0.525 | 496.475 | - |
0% November - 2018 |
Abbottabad componenet - Handed over to KITE |
No Image |
Abbottabad | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0.525 | 0 | 0 | 0 | 0 | 0.525 | 496.475 | - |
0% November - 2018 |
Abbottabad componenet - Handed over to KITE |
No Image |
Abbottabad | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0.525 | 0 | 0 | 0 | 0 | 0.525 | 496.475 | - |
0% April - 2019 |
Abbottabad componenet - Handed over to KITE. |
No Image |
Abbottabad | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0.525 | 5 | 5 | 0 | 0 | 0.525 | 491.475 | 1% |
0% March - 2019 |
Abbottabad componenet - Handed over to KITE. |
No Image |
Abbottabad | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0.525 | 5 | 5 | 0 | 0 | 0.525 | 491.475 | 1% |
0% March - 2019 |
Abbottabad componenet - Handed over to KITE. |
No Image |
Abbottabad | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0.525 | 5 | 5 | 0 | 0 | 0.525 | 491.475 | 1% |
0% February - 2019 |
Abbottabad componenet - Handed over to KITE. |
No Image |
Abbottabad | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0.525 | 0 | 0 | 0 | 0 | 0.525 | 496.475 | - |
0% January - 2019 |
Abbottabad componenet - Handed over to KITE |
No Image |
Abbottabad | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 11.25 | 20 | 20 | 20 | 0 | 11.25 | 138.75 | 18% |
7% December - 2018 |
Earth work completed, road work, structure work in progress. |
No Image |
Haripur | |||||||||||||||||||
983 (New) |
190569-Construction of roads in Tehsil Ghazi (10 Km), Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.423 | 0 | 5 | 5 | 0 | 0 | 0 | 80.423 | 6% |
- December - 2019 |
Approved. AA issued. |
No Image |
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 11.25 | 20 | 20 | 20 | 0 | 11.25 | 138.75 | 18% |
7% November - 2018 |
Work in progress. |
No Image |
Haripur | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 11.25 | 20 | 20 | 20 | 0 | 11.25 | 138.75 | 18% |
7% November - 2018 |
Work in progress. |
No Image |
Haripur | |||||||||||||||||||
983 (New) |
190569-Construction of roads in Tehsil Ghazi (10 Km), Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
DCE submitted to SOR.Deffered in DDWP . Under preparation on new scope. Will be submitted by 22/11/2019. |
No Image |
983 (New) |
190569-Construction of roads in Tehsil Ghazi (10 Km), Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
DCE submitted to SOR.Deffered in DDWP . Under preparation on new scope. Will be submitted by 22/11/2019. |
No Image |
983 (New) |
190569-Construction of roads in Tehsil Ghazi (10 Km), Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
DCE submitted to SOR. |
No Image |
983 (New) |
190569-Construction of roads in Tehsil Ghazi (10 Km), Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
DCE under preparation. Will be submitted within 2 days |
No Image |
983 (New) |
190569-Construction of roads in Tehsil Ghazi (10 Km), Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.423 | 0 | 5 | 5 | 0 | 0 | 0 | 80.423 | 6% |
- May - 2020 |
Procuremnet in Progress. |
No Image |
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 11.25 | 10 | 32.0005 | 32.0005 | 29.5 | 40.75 | 148.75 | 13% |
24% April - 2019 |
Earth work completed, road work, structure work in progress. |
No Image |
Haripur | |||||||||||||||||||
983 (New) |
190569-Construction of roads in Tehsil Ghazi (10 Km), Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.423 | 0 | 5 | 5 | 0 | 0 | 0 | 80.423 | 6% |
- April - 2020 |
Procuremnet in Progress. |
No Image |
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 11.25 | 10 | 29.501 | 29.501 | 20 | 31.25 | 148.75 | 13% |
18% March - 2019 |
Earth work completed, road work, structure work in progress. |
No Image |
Haripur | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 11.25 | 10 | 29.501 | 29.501 | 20 | 31.25 | 148.75 | 13% |
18% March - 2019 |
Earth work completed, road work, structure work in progress. |
No Image |
Haripur | |||||||||||||||||||
983 (New) |
190569-Construction of roads in Tehsil Ghazi (10 Km), Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.423 | 0 | 5 | 5 | 0 | 0 | 0 | 80.423 | 6% |
- March - 2020 |
Procuremnet in Progress. |
No Image |
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 11.25 | 10 | 29.501 | 29.501 | 20 | 31.25 | 148.75 | 13% |
18% February - 2019 |
Earth work completed, road work, structure work in progress. |
No Image |
Haripur | |||||||||||||||||||
983 (New) |
190569-Construction of roads in Tehsil Ghazi (10 Km), Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.423 | 0 | 5 | 5 | 0 | 0 | 0 | 80.423 | 6% |
- February - 2020 |
Procuremnet in Progress. |
No Image |
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 11.25 | 20 | 20 | 20 | 20 | 31.25 | 138.75 | 18% |
18% January - 2019 |
Earth work completed, road work, structure work in progress. |
No Image |
Haripur | |||||||||||||||||||
983 (New) |
190569-Construction of roads in Tehsil Ghazi (10 Km), Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.423 | 0 | 5 | 5 | 0 | 0 | 0 | 80.423 | 6% |
- January - 2020 |
Procuremnet in Progress. |
No Image |
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
19-06-15 | - | - | 28-01-15 | - | 157.738 | 63.239 | 10 | 8.55 | 6.05 | 4.233 | 67.472 | 84.499 | 46% |
43% December - 2017 |
Length 11 Km - sub base 10 Km, WBM 4 Km completed. Revised DCE submitted to P&D for increses in BT width from 12 ft to 18 ft and change of specification from TST to plant Premix as per CM directive. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
19-06-15 | - | - | 28-01-15 | - | 157.738 | 63.239 | 10 | 10 | 3.55 | 0 | 63.239 | 84.499 | 46% |
40% September - 2017 |
Length 11 Km - 1.6 Km completed. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
19-06-15 | - | - | 28-01-15 | - | 157.738 | 63.239 | 10 | 10 | 3.55 | 0 | 63.239 | 84.499 | 46% |
40% August - 2017 |
Length 11 Km - 1.6 Km completed. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
19-06-15 | - | - | 28-01-15 | - | 157.738 | 63.239 | 10 | 10 | 3.55 | 0 | 63.239 | 84.499 | 46% |
40% July - 2017 |
Length 11 Km - 1.6 Km completed. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.738 | 63.239 | 10 | 8.55 | 6.05 | 3.957 | 67.196 | 84.499 | 46% |
43% November - 2017 |
Length 11 Km - sub base 10km - WBM 4 km completed.
Revised DCE Submitted to P&D for increses in BT width from 12 ft to 18 ft and change of specification from TST to plant Premix as per CM directive. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.738 | 63.239 | 10 | 10 | 7.1 | 5.1 | 68.339 | 84.499 | 46% |
43% October - 2017 |
Length 11 Km - 1.6 Km completed. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 187.416 | 63.239 | 10 | 11.111 | 11.111 | 11.111 | 74.35 | 114.177 | 39% |
40% June - 2018 |
Length 11 Km - sub base 10 Km, WBM 4 Km completed. Rev approval accorded. Minutes issued. AA awaited. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 187.416 | 63.239 | 10 | 11.111 | 11.111 | 11.111 | 74.35 | 114.177 | 39% |
40% May - 2018 |
Length 11 Km - sub base 10 Km, WBM 4 Km completed. Rev approval accorded. Minutes issued. AA awaited. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.738 | 63.239 | 10 | 11.111 | 11.111 | 11.111 | 74.35 | 84.499 | 46% |
47% April - 2018 |
Length 11 Km - sub base 10 Km, WBM 4 Km completed. Revised PC-I/DCE for Rs.221.823 m submitted to Chief Infra P&D on 30/04/2018. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.738 | 63.239 | 10 | 11.111 | 11.111 | 11.111 | 74.35 | 84.499 | 46% |
47% March - 2018 |
Length 11 Km - sub base 10 Km, WBM 4 Km completed.
Revised DCE submitted to P&D for increses in BT width from 12 ft to 18 ft and change of specification from TST to plant Premix as per CM directive. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.738 | 63.239 | 10 | 11.111 | 11.111 | 11.111 | 74.35 | 84.499 | 46% |
47% February - 2018 |
Length 11 Km - sub base 10 Km, WBM 4 Km completed. Revised DCE submitted to P&D for increses in BT width from 12 ft to 18 ft and change of specification from TST to plant Premix as per CM directive. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.738 | 63.239 | 10 | 11.111 | 11.111 | 4.584 | 67.823 | 84.499 | 46% |
43% January - 2018 |
Length 11 Km - sub base 10 Km, WBM 4 Km completed. Revised DCE submitted to P&D for increses in BT width from 12 ft to 18 ft and change of specification from TST to plant Premix as per CM directive. |
No Image |
1) BTR from Odin Shah Killa to Jarasi (2 Km)
2) BTR from Takhti Nasratti to Sarki Lawaghar via Poya (2 Km)
3) BTR from Latambar to Kamali Banda road (3 Km)
4) BTR from Latamber to Indus Highway road via Warana (4 Km) | |||||||||||||||||||
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 10 | 25 | 20.001 | 0 | 0 | 657 | 1% |
- December - 2018 |
No Image | |
983 (New) |
195138-Provision of staff to existing colleges (Commerce + General) (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1728 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
983 (New) |
195138-Provision of staff to existing colleges (Commerce + General) (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1728 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 10 | 25 | 20.001 | 0 | 0 | 657 | 1% |
- November - 2018 |
No Image | |
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 10 | 25 | 20.001 | 0 | 0 | 657 | 1% |
- November - 2018 |
No Image | |
983 (New) |
195138-Provision of staff to existing colleges (Commerce + General) (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1728 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
983 (New) |
195138-Provision of staff to existing colleges (Commerce + General) (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1728 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
983 (New) |
195138-Provision of staff to existing colleges (Commerce + General) (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1728 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
983 (New) |
195138-Provision of staff to existing colleges (Commerce + General) (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1728 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
983 (New) |
195138-Provision of staff to existing colleges (Commerce + General) (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1728 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
983 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 10 | 32 | 29.5005 | 0 | 0 | 657 | 1% |
- April - 2019 |
No Image | |
983 (New) |
195138-Provision of staff to existing colleges (Commerce + General) (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1728 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
Pages : 1 2 |