Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
981 (OG) |
150953-Imp & Reconstn of road from Sherwan to Thathi UC Sherwan & road from Civil Hospital to Ratian via Thandara with link to Sari Sher Shah and Bandi Nikian U/C Pind Kargoo Distt Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 42.817 | 54.499 | 51.774 | 24.525 | 0 | 42.817 | 2.684 | 97% |
43% December - 2018 |
WBM in progress. |
No Image |
PC-46, Abbottabad | |||||||||||||||||||
981 (OG) |
150953-Imp & Reconstn of road from Sherwan to Thathi UC Sherwan & road from Civil Hospital to Ratian via Thandara with link to Sari Sher Shah and Bandi Nikian U/C Pind Kargoo Distt Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 42.817 | 54.499 | 51.774 | 24.525 | 0 | 42.817 | 2.684 | 97% |
43% November - 2018 |
Earth work in progress (2 units). |
No Image |
PC-46, Abbottabad | |||||||||||||||||||
981 (OG) |
150953-Imp & Reconstn of road from Sherwan to Thathi UC Sherwan & road from Civil Hospital to Ratian via Thandara with link to Sari Sher Shah and Bandi Nikian U/C Pind Kargoo Distt Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 42.817 | 54.499 | 51.774 | 24.525 | 0 | 42.817 | 2.684 | 97% |
43% November - 2018 |
Earth work in progress (2 units). |
No Image |
PC-46, Abbottabad | |||||||||||||||||||
981 (OG) |
150953-Imp & Reconstn of road from Sherwan to Thathi UC Sherwan & road from Civil Hospital to Ratian via Thandara with link to Sari Sher Shah and Bandi Nikian U/C Pind Kargoo Distt Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 42.817 | 54.499 | 51.7741 | 51.7746 | 10.652 | 53.469 | 2.684 | 97% |
53% April - 2019 |
WBM in progress. |
No Image |
PC-46, Abbottabad | |||||||||||||||||||
981 (OG) |
150953-Imp & Reconstn of road from Sherwan to Thathi UC Sherwan & road from Civil Hospital to Ratian via Thandara with link to Sari Sher Shah and Bandi Nikian U/C Pind Kargoo Distt Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 42.817 | 54.499 | 51.7741 | 51.7746 | 10.652 | 53.469 | 2.684 | 97% |
53% March - 2019 |
WBM in progress. |
No Image |
PC-46, Abbottabad | |||||||||||||||||||
981 (OG) |
150953-Imp & Reconstn of road from Sherwan to Thathi UC Sherwan & road from Civil Hospital to Ratian via Thandara with link to Sari Sher Shah and Bandi Nikian U/C Pind Kargoo Distt Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 42.817 | 54.499 | 51.7741 | 51.7746 | 10.652 | 53.469 | 2.684 | 97% |
53% March - 2019 |
WBM in progress. |
No Image |
PC-46, Abbottabad | |||||||||||||||||||
981 (OG) |
150953-Imp & Reconstn of road from Sherwan to Thathi UC Sherwan & road from Civil Hospital to Ratian via Thandara with link to Sari Sher Shah and Bandi Nikian U/C Pind Kargoo Distt Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 42.817 | 54.499 | 51.7741 | 51.7746 | 10.652 | 53.469 | 2.684 | 97% |
53% February - 2019 |
WBM in progress. |
No Image |
PC-46, Abbottabad | |||||||||||||||||||
981 (OG) |
150953-Imp & Reconstn of road from Sherwan to Thathi UC Sherwan & road from Civil Hospital to Ratian via Thandara with link to Sari Sher Shah and Bandi Nikian U/C Pind Kargoo Distt Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 42.817 | 54.499 | 51.774 | 24.525 | 0 | 42.817 | 2.684 | 97% |
43% January - 2019 |
WBM in progress. |
No Image |
PC-46, Abbottabad | |||||||||||||||||||
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
- | - | - | 02-11-15 | - | 150.1 | 0.073 | 10 | 5.05 | 0.0499999999999998 | 0 | 0.073 | 140.027 | 7% |
0% December - 2017 |
Delay due to stay order by court. Work started. |
No Image |
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
- | - | - | 02-11-15 | - | 150.1 | 0.073 | 10 | 10 | 0 | 0 | 0.073 | 140.027 | 7% |
0% September - 2017 |
Financial bid called. Delay due to P&D direction for conversion from TST to Pre-mix - PC-I submitted but deffered. With the direction to execute TST. |
No Image |
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
- | - | - | 02-11-15 | - | 150.1 | 0.073 | 10 | 10 | 0 | 0 | 0.073 | 140.027 | 7% |
0% August - 2017 |
Financial bid called. Delay due to P&D direction for conversion from TST to Pre-mix - PC-I submitted but deffered. With the direction to execute TST. |
No Image |
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
- | - | - | 02-11-15 | - | 150.1 | 0.073 | 10 | 10 | 3.55 | 0 | 0.073 | 140.027 | 7% |
0% July - 2017 |
Financial bid called. Delay due to P&D direction for conversion from TST to Pre-mix - PC-I submitted but deffered. With the direction to execute TST. |
No Image |
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 0.073 | 10 | 5.05 | 0.05 | 0 | 0.073 | 140.027 | 7% |
0% November - 2017 |
Finnacial bid of contractor opened and Sumitted to CE on 30/11/17. Delay due to stay order by court |
No Image |
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 0.073 | 10 | 10 | 0 | 0 | 0.073 | 140.027 | 7% |
0% October - 2017 |
Financial bid called. Delay due to P&D direction for conversion from TST to Pre-mix - PC-I submitted but deffered. With the direction to execute TST. Stay order on procurement. |
No Image |
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 0.073 | 10 | 4.862 | 4.862 | 2.081 | 2.154 | 140.027 | 7% |
1% June - 2018 |
Delay due to stay order by court (vacated) Work in Progress on 21 units. |
No Image |
Bannu | |||||||||||||||||||
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 0.073 | 10 | 12.862 | 12.862 | 2.081 | 2.154 | 140.027 | 7% |
1% May - 2018 |
Delay due to stay order by court (vacated) Work in Progress on 21 Units |
No Image |
Bannu | |||||||||||||||||||
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 0.073 | 10 | 12.862 | 12.862 | 5.122 | 5.195 | 140.027 | 7% |
3% April - 2018 |
Delay due to stay order by court (vacated) Work in Progress on 21 Units |
No Image |
Bannu | |||||||||||||||||||
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 0.073 | 10 | 22.5 | 22.5 | 5.122 | 5.195 | 140.027 | 7% |
3% March - 2018 |
Delay due to stay order by court (vacated) Work in Progress on 21 Units |
No Image |
Bannu | |||||||||||||||||||
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 0.073 | 10 | 5.05 | 10.172 | 5.122 | 5.195 | 140.027 | 7% |
3% February - 2018 |
Delay due to stay order by court (vacated) Work started in Jan 2018. |
No Image |
Bannu | |||||||||||||||||||
981 (OG) |
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 0.073 | 10 | 5.05 | 10.172 | 5.122 | 5.195 | 140.027 | 7% |
3% January - 2018 |
Delay due to stay order by court. Work started. |
No Image |
981 (New) |
190373-Rehabilitation of internal roads in Kalabat Township to Kangra Colony District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- December - 2019 |
Procuremnet in Process |
No Image |
981 (New) |
190373-Rehabilitation of internal roads in Kalabat Township to Kangra Colony District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
PC-1/ DCE already sent. Pending for PDWP. |
No Image |
981 (New) |
190373-Rehabilitation of internal roads in Kalabat Township to Kangra Colony District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
DCE submitted to P&D. Discussed in PDWP. M&E report awaited. |
No Image |
981 (New) |
190373-Rehabilitation of internal roads in Kalabat Township to Kangra Colony District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
DCE submitted to P&D. |
No Image |
981 (New) |
190373-Rehabilitation of internal roads in Kalabat Township to Kangra Colony District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
DCE under preparation. Will be submitted within 2 days |
No Image |
981 (New) |
190373-Rehabilitation of internal roads in Kalabat Township to Kangra Colony District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- May - 2020 |
2 units - work order issued. |
No Image |
981 (New) |
190373-Rehabilitation of internal roads in Kalabat Township to Kangra Colony District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- April - 2020 |
2 units - work order issued. |
No Image |
981 (New) |
190373-Rehabilitation of internal roads in Kalabat Township to Kangra Colony District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- March - 2020 |
2 units - work order issued. |
No Image |
981 (New) |
190373-Rehabilitation of internal roads in Kalabat Township to Kangra Colony District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- February - 2020 |
2 units - work order issued. |
No Image |
981 (New) |
190373-Rehabilitation of internal roads in Kalabat Township to Kangra Colony District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- January - 2020 |
Tender approval under process. |
No Image |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
981 (New) |
195136-Performance based package for the teaching faculty (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1899 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |