Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
976 (OG) |
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Darwaza via Cham U/C Plack Distt. Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 16.3 | 53.7 | 51.015 | 24.166 | 0 | 16.3 | 0 | 100% |
23% December - 2018 |
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress. |
No Image |
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45 | |||||||||||||||||||
976 (New) |
190371-Construction of roads a) Bara Gali, Goragali, Baknotar, Khun Palkot Kutli road, b) Khatwal, Mir Rehmat Khan, Peer Lal Mori Sambal Dhara road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 75 | 6% |
- December - 2019 |
Approved. |
No Image |
976 (OG) |
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Darwaza via Cham U/C Plack Distt. Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 16.3 | 53.7 | 51.015 | 24.166 | 0 | 16.3 | 0 | 100% |
23% November - 2018 |
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress. |
No Image |
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45 | |||||||||||||||||||
976 (OG) |
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Darwaza via Cham U/C Plack Distt. Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 16.3 | 53.7 | 51.015 | 24.166 | 0 | 16.3 | 0 | 100% |
23% November - 2018 |
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress. |
No Image |
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45 | |||||||||||||||||||
976 (New) |
190371-Construction of roads a) Bara Gali, Goragali, Baknotar, Khun Palkot Kutli road, b) Khatwal, Mir Rehmat Khan, Peer Lal Mori Sambal Dhara road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
Condiltionally approved in DDWP. (Clerance from Finanace deptt awaited) |
No Image |
976 (New) |
190371-Construction of roads a) Bara Gali, Goragali, Baknotar, Khun Palkot Kutli road, b) Khatwal, Mir Rehmat Khan, Peer Lal Mori Sambal Dhara road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
DCE submitted to SOR. Deffered in DDWP.
DCE under preparation on the new scope of work. |
No Image |
976 (New) |
190371-Construction of roads a) Bara Gali, Goragali, Baknotar, Khun Palkot Kutli road, b) Khatwal, Mir Rehmat Khan, Peer Lal Mori Sambal Dhara road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
DCE submitted to SOR for Rs. 80 m |
No Image |
976 (New) |
190371-Construction of roads a) Bara Gali, Goragali, Baknotar, Khun Palkot Kutli road, b) Khatwal, Mir Rehmat Khan, Peer Lal Mori Sambal Dhara road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
DCE under preparation. Will be submitted within 2 weeks time |
No Image |
976 (New) |
190371-Construction of roads a) Bara Gali, Goragali, Baknotar, Khun Palkot Kutli road, b) Khatwal, Mir Rehmat Khan, Peer Lal Mori Sambal Dhara road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 75 | 6% |
- May - 2020 |
work order issued. |
No Image |
976 (OG) |
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Darwaza via Cham U/C Plack Distt. Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 16.3 | 53.7 | 51.015 | 51.0155 | 3.388 | 19.688 | 0 | 100% |
28% April - 2019 |
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress. |
No Image |
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45 | |||||||||||||||||||
976 (New) |
190371-Construction of roads a) Bara Gali, Goragali, Baknotar, Khun Palkot Kutli road, b) Khatwal, Mir Rehmat Khan, Peer Lal Mori Sambal Dhara road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 75 | 6% |
- April - 2020 |
work order issued. |
No Image |
976 (OG) |
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Darwaza via Cham U/C Plack Distt. Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 16.3 | 53.7 | 51.015 | 51.0155 | 3.388 | 19.688 | 0 | 100% |
28% March - 2019 |
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress. |
No Image |
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45 | |||||||||||||||||||
976 (OG) |
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Darwaza via Cham U/C Plack Distt. Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 16.3 | 53.7 | 51.015 | 51.0155 | 3.388 | 19.688 | 0 | 100% |
28% March - 2019 |
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress. |
No Image |
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45 | |||||||||||||||||||
976 (New) |
190371-Construction of roads a) Bara Gali, Goragali, Baknotar, Khun Palkot Kutli road, b) Khatwal, Mir Rehmat Khan, Peer Lal Mori Sambal Dhara road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 75 | 6% |
- March - 2020 |
work order issued. |
No Image |
976 (OG) |
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Darwaza via Cham U/C Plack Distt. Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 16.3 | 53.7 | 51.015 | 51.0155 | 3.388 | 19.688 | 0 | 100% |
28% February - 2019 |
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress. |
No Image |
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45 | |||||||||||||||||||
976 (New) |
190371-Construction of roads a) Bara Gali, Goragali, Baknotar, Khun Palkot Kutli road, b) Khatwal, Mir Rehmat Khan, Peer Lal Mori Sambal Dhara road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 75 | 6% |
- February - 2020 |
work order issued. |
No Image |
976 (OG) |
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Darwaza via Cham U/C Plack Distt. Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 16.3 | 53.7 | 51.015 | 24.165 | 3.388 | 19.688 | 0 | 100% |
28% January - 2019 |
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress. |
No Image |
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45 | |||||||||||||||||||
976 (New) |
190371-Construction of roads a) Bara Gali, Goragali, Baknotar, Khun Palkot Kutli road, b) Khatwal, Mir Rehmat Khan, Peer Lal Mori Sambal Dhara road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 0 | 5 | 5 | 0 | 0 | 0 | 75 | 6% |
- January - 2020 |
Tender approval under process. |
No Image |
976 (OG) |
140983-Construction / Extension and Black Topping of Road (a) From Ghora Road to Malik Shay Koroona (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) and (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
08-09-15 | 30-06-18 | - | 13-02-15 | - | 59.965 | 14.048 | 43.417 | 43.417 | 21.708 | 15.126 | 29.174 | 2.5 | 96% |
49% December - 2017 |
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit (Narmi Khel to Gul Andor Koroona), summary approved for shifting of site. Revised PC-I/DCE for Rs.65.111 m submitted to SOR on 18/12/2017. |
No Image |
976 (OG) |
140983-Constn / Ext: and BT of road (a) Narmi Khel to Gul Andar Korma (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) & (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
08-09-15 | 30-06-18 | - | 13-02-15 | - | 59.965 | 14.048 | 43.417 | 43.417 | 15.413 | 6.325 | 20.373 | 2.5 | 96% |
34% September - 2017 |
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit at serial no. (a) shifting involved, summary under process. |
No Image |
976 (OG) |
140983-Constn / Ext: and BT of road (a) Narmi Khel to Gul Andar Korma (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) & (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
08-09-15 | 30-06-18 | - | 13-02-15 | - | 59.965 | 14.048 | 43.417 | 43.417 | 15.413 | 3.418 | 17.466 | 2.5 | 96% |
29% August - 2017 |
Length 6 Km (3 units) -earth work, structure work in progress on all 3 units. Revised PC-I/DCE for Rs.59.966 m submitted to SOR on 20/06/2017. |
No Image |
976 (OG) |
140983-Constn / Ext: and BT of road (a) Narmi Khel to Gul Andar Korma (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) & (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
08-09-15 | 30-06-18 | - | 13-02-15 | - | 59.965 | 14.048 | 43.417 | 43.417 | 15.413 | 0 | 14.048 | 2.5 | 96% |
23% July - 2017 |
Length 6 Km (3 units) -earth work, structure work in progress on all 3 units. Revised PC-I/DCE for Rs.59.966 m submitted to SOR on 20/06/2017. |
No Image |
976 (OG) |
140983-Construction / Extension and Black Topping of Road (a) From Ghora Road to Malik Shay Koroona (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) and (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.965 | 14.048 | 43.417 | 43.417 | 21.708 | 10.95 | 24.998 | 2.5 | 96% |
42% November - 2017 |
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit ( Narmi khel to Gul andor korna).shifting involved, summary approved. |
No Image |
976 (OG) |
140983-Constn / Ext: and BT of road (a) Narmi Khel to Gul Andar Korma (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) & (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.965 | 14.048 | 43.417 | 43.417 | 15.413 | 8.414 | 22.462 | 2.5 | 96% |
37% October - 2017 |
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit at serial no. (a) shifting involved, summary under process. |
No Image |
976 (OG) |
140983-Construction / Extension and Black Topping of Road (a) From Ghora Road to Malik Shay Koroona (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) and (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.965 | 14.048 | 43.417 | 40.917 | 40.917 | 39.996 | 54.044 | 2.5 | 96% |
90% June - 2018 |
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit (Narmi Khel to Gul Andor Koroona). |
No Image |
1) Constn/BT road from Narmi Khel to Gul Andor Koroona (2 Km) shifted to BTR from Ghora road to Malik Shay Koroona (2 Km)
2) Construction/extension of BT road from Spin Filling Station to Gul Badin Sardi Khel (2 Km)
3) Construction/BT road from Marwatl Canal to Laka Shuviey (2 Km) | |||||||||||||||||||
976 (OG) |
140983-Construction / Extension and Black Topping of Road (a) From Ghora Road to Malik Shay Koroona (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) and (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.965 | 14.048 | 43.417 | 43.419 | 43.419 | 34.758 | 48.806 | 2.5 | 96% |
81% May - 2018 |
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit (Narmi Khel to Gul Andor Koroona), |
No Image |
1) Constn/BT road from Narmi Khel to Gul Andor Koroona (2 Km) shifted to BTR from Ghora road to Malik Shay Koroona (2 Km)
2) Construction/extension of BT road from Spin Filling Station to Gul Badin Sardi Khel (2 Km)
3) Construction/BT road from Marwatl Canal to Laka Shuviey (2 Km) | |||||||||||||||||||
976 (OG) |
140983-Construction / Extension and Black Topping of Road (a) From Ghora Road to Malik Shay Koroona (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) and (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.965 | 14.048 | 43.417 | 49.073 | 49.073 | 32.202 | 46.25 | 2.5 | 96% |
77% April - 2018 |
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit (Narmi Khel to Gul Andor Koroona), |
No Image |
1) Constn/BT road from Narmi Khel to Gul Andor Koroona (2 Km) shifted to BTR from Ghora road to Malik Shay Koroona (2 Km)
2) Construction/extension of BT road from Spin Filling Station to Gul Badin Sardi Khel (2 Km)
3) Construction/BT road from Marwatl Canal to Laka Shuviey (2 Km) | |||||||||||||||||||
976 (OG) |
140983-Construction / Extension and Black Topping of Road (a) From Ghora Road to Malik Shay Koroona (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) and (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.965 | 14.048 | 43.417 | 43.417 | 43.416 | 21.708 | 35.756 | 2.5 | 96% |
60% March - 2018 |
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit (Narmi Khel to Gul Andor Koroona), |
No Image |
1) Constn/BT road from Narmi Khel to Gul Andor Koroona (2 Km) shifted to BTR from Ghora road to Malik Shay Koroona (2 Km)
2) Construction/extension of BT road from Spin Filling Station to Gul Badin Sardi Khel (2 Km)
3) Construction/BT road from Marwatl Canal to Laka Shuviey (2 Km) | |||||||||||||||||||
976 (OG) |
140983-Construction / Extension and Black Topping of Road (a) From Ghora Road to Malik Shay Koroona (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) and (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.965 | 14.048 | 43.417 | 43.417 | 21.708 | 21.708 | 35.756 | 2.5 | 96% |
60% February - 2018 |
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit (Narmi Khel to Gul Andor Koroona), |
No Image |
1) Constn/BT road from Narmi Khel to Gul Andor Koroona (2 Km) shifted to BTR from Ghora road to Malik Shay Koroona (2 Km)
2) Construction/extension of BT road from Spin Filling Station to Gul Badin Sardi Khel (2 Km)
3) Construction/BT road from Marwatl Canal to Laka Shuviey (2 Km) | |||||||||||||||||||
976 (OG) |
140983-Construction / Extension and Black Topping of Road (a) From Ghora Road to Malik Shay Koroona (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) and (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.965 | 14.048 | 43.417 | 43.417 | 21.708 | 15.126 | 29.174 | 2.5 | 96% |
49% January - 2018 |
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit (Narmi Khel to Gul Andor Koroona), |
No Image |
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.544 | 26.959 | 17.944 | 17.944 | 14.56 | 6.194 | 33.153 | 9.641 | 82% |
61% December - 2020 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress. |
No Image |
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.544 | 26.959 | 17.944 | 17.944 | 14.56 | 6.194 | 33.153 | 9.641 | 82% |
61% December - 2020 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress. |
No Image |
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.544 | 26.959 | 17.944 | 17.944 | 6.3 | 6.3 | 33.259 | 9.641 | 82% |
61% October - 2020 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress. |
No Image |
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.544 | 26.959 | 17.944 | 17.944 | 6.3 | 4.935 | 31.894 | 9.641 | 82% |
58% September - 2020 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress. |
No Image |
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.544 | 26.959 | 17.944 | 17.944 | 0 | 0 | 26.959 | 9.641 | 82% |
49% August - 2020 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress. |
No Image |
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.344 | 26.959 | 17.944 | 0 | 0 | 0 | 26.959 | 14.441 | 76% |
45% July - 2020 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress. |
No Image |
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.544 | 26.959 | 17.944 | 14.56 | 14.56 | 11.594 | 38.553 | 9.641 | 82% |
71% May - 2021 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress.
Demand Rs: 10 M |
No Image |
1 GHSS Sama Badaber to Degree College FR Peshawar | |||||||||||||||||||
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.544 | 26.959 | 17.944 | 14.56 | 14.56 | 11.594 | 38.553 | 9.641 | 82% |
71% April - 2021 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress.
Demand Rs: 10 M |
No Image |
1 GHSS Sama Badaber to Degree College FR Peshawar | |||||||||||||||||||
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.544 | 26.959 | 17.944 | 14.56 | 14.56 | 11.594 | 38.553 | 9.641 | 82% |
71% March - 2021 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress.
Demand Rs: 10 M |
No Image |
1 GHSS Sama Badaber to Degree College FR Peshawar | |||||||||||||||||||
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.544 | 26.959 | 17.944 | 14.56 | 14.56 | 11.594 | 38.553 | 9.641 | 82% |
71% February - 2021 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress.
Demand Rs: 10 M |
No Image |
1 GHSS Sama Badaber to Degree College FR Peshawar | |||||||||||||||||||
976 (OG) |
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.544 | 26.959 | 17.944 | 14.56 | 14.56 | 6.194 | 33.153 | 9.641 | 82% |
61% January - 2021 |
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress. |
No Image |
1 GHSS Sama Badaber to Degree College FR Peshawar | |||||||||||||||||||