Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, January - 2018, February - 2019, February - 2020, February - 2021, February - 2018, March - 2019, March - 2020, March - 2021, March - 2018, April - 2019, April - 2020, April - 2021, April - 2018, May - 2018, May - 2020, May - 2021, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
975
(OG)
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200.064 106.462 10 9.5 7.001 4.5 110.962 83.602 58% 55%
December - 2018
Out of 9 units, all in progress.
No Image
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch
975
(OG)
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200.064 106.462 10 9.5 4.501 4.5 110.962 83.602 58% 55%
November - 2018
Out of 9 units, all in progress.
No Image
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch
975
(OG)
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200.064 106.462 10 9.5 4.501 4.5 110.962 83.602 58% 55%
November - 2018
Out of 9 units, all in progress.
No Image
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch
975
(OG)
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200.064 106.462 10 9.5 8.2505 6.9 113.362 83.602 58% 57%
April - 2019
Out of 9 units, all in progress.
No Image
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch
975
(OG)
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200.064 106.462 10 9.5 8.2505 6.9 113.362 83.602 58% 57%
March - 2019
Out of 9 units, all in progress.
No Image
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch
975
(OG)
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200.064 106.462 10 9.5 8.2505 6.9 113.362 83.602 58% 57%
March - 2019
Out of 9 units, all in progress.
No Image
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch
975
(OG)
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200.064 106.462 10 9.5 8.2505 6.9 113.362 83.602 58% 57%
February - 2019
Out of 9 units, all in progress.
No Image
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch
975
(OG)
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200.064 106.462 10 9.5 7.001 6.9 113.362 83.602 58% 57%
January - 2019
Out of 9 units, all in progress.
No Image
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
- 30-06-18 - 28-01-15 - 76.516 28.193 49.073 49.073 24.537 9.451 37.644 0 100% 49%
December - 2017
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed.
No Image
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
- 30-06-18 - 28-01-15 - 76.516 28.193 49.073 49.073 17.421 0 28.193 0 100% 37%
September - 2017
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5-Km) earth work completed.
No Image
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
- 30-06-18 - 28-01-15 - 76.516 28.193 49.073 49.073 17.421 0 28.193 0 100% 37%
August - 2017
Length 8 Km - road work 3 Km, earth work 80%, structure work 40% completed, WBM in progress.
No Image
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
- 30-06-18 - 28-01-15 - 76.516 28.193 49.073 49.073 17.421 0 28.193 0 100% 37%
July - 2017
Length 8 Km - road work 3 Km, earth work 80%, structure work 40% completed, WBM in progress.
No Image
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 28.193 49.073 49.073 24.537 9.613 37.806 0 100% 49%
November - 2017
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed.
No Image
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 28.193 49.073 49.073 24.537 0 28.193 0 100% 37%
October - 2017
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed.
No Image
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 28.7917 49.073 39.074 39.074 31.272 60.0637 0 100% 78%
June - 2018
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. Cannot be completed to court case.
No Image
Bannu
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 28.7917 49.073 49.074 49.074 27.868 56.6597 0 100% 74%
May - 2018
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. Cannot be completed to court case.
No Image
Bannu
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 28.7917 49.073 49.074 49.074 24.533 53.3247 0 100% 70%
April - 2018
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed.
No Image
Bannu
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 28.7917 49.073 49.073 24.537 24.537 53.3287 0 100% 70%
March - 2018
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed.
No Image
Bannu
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 28.7917 49.073 49.073 24.537 17.66 46.4517 0 100% 61%
February - 2018
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed.
No Image
Bannu
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 28.193 49.073 49.073 24.537 9.451 37.644 0 100% 49%
January - 2018
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed.
No Image
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 190.505 190.505 20 2.447 16.584 0 100% 8%
December - 2020
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress. Revised DCE submitted
No Image
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 190.505 190.505 20 2.447 16.584 0 100% 8%
December - 2020
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress. Revised DCE submitted
No Image
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 0 0 20 2.447 16.584 184.414 - 8%
October - 2020
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress.
No Image
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 0 0 20 2.447 16.584 184.414 - 8%
September - 2020
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress.
No Image
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 0 0 0 0 14.137 184.414 - 7%
August - 2020
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress.
No Image
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 190.505 0 0 0 14.137 0 100% 7%
July - 2020
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress.
No Image
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 190.505 64.712 64.712 2.447 16.584 0 100% 8%
May - 2021
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress. Cannot be completed due to revision Revised DCE submitted
No Image
Construction of Building for Govt Degree College Ara Khel, FR Kohat.
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 190.505 64.712 64.712 2.447 16.584 0 100% 8%
April - 2021
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress. Cannot be completed due to revision Revised DCE submitted
No Image
Construction of Building for Govt Degree College Ara Khel, FR Kohat.
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 190.505 64.712 64.712 2.447 16.584 0 100% 8%
March - 2021
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress. Cannot be completed due to revision Revised DCE submitted
No Image
Construction of Building for Govt Degree College Ara Khel, FR Kohat.
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 190.505 64.712 64.712 2.447 16.584 0 100% 8%
February - 2021
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress. Cannot be completed due to revision Revised DCE submitted
No Image
Construction of Building for Govt Degree College Ara Khel, FR Kohat.
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 190.505 64.712 64.712 2.447 16.584 0 100% 8%
January - 2021
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress. Revised DCE submitted
No Image
Construction of Building for Govt Degree College Ara Khel, FR Kohat.
975
(New)
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 0 0 0 240 4% -
December - 2019
Tender floated on 13/01/2020.
No Image
975
(New)
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 0 0 0 240 4% -
November - 2019
Approved.
No Image
975
(New)
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 250 0 10 10 0 0 0 0 - -
October - 2019
Approved on 08/11/2019. AA awaited.
No Image
975
(New)
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 250 0 10 10 0 0 0 0 - -
September - 2019
DCE will be re submitted by 21-10-2019 on MRS 2019.
No Image
975
(New)
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 250 0 10 10 0 0 0 0 - -
August - 2019
Dce under preparation
No Image
975
(New)
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 0 0 0 240 4% -
May - 2020
Work order issued.
No Image
975
(New)
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 0 0 0 240 4% -
April - 2020
Work order issued.
No Image
975
(New)
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 0 0 0 240 4% -
March - 2020
Work order issued.
No Image
975
(New)
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 0 0 0 240 4% -
February - 2020
Work order issued.
No Image
975
(New)
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 0 0 0 240 4% -
January - 2020
Tender approval under process.
No Image
Pages : 1