Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, January - 2019, January - 2020, February - 2021, February - 2018, February - 2019, February - 2020, March - 2021, March - 2018, March - 2019, March - 2020, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2019, October - 2020, October - 2017, October - 2019, November - 2017, November - 2018, November - 2019, December - 2020, December - 2017, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
973
(OG)
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 180.78 70.485 10 13.5 8.501 8.5 78.985 100.295 45% 44%
December - 2018
Length 8 Km - out of 3 units, all in progress.
No Image
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48
973
(OG)
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 180.78 70.485 10 13.5 8.501 8.5 78.985 100.295 45% 44%
November - 2018
Length 8 Km - out of 3 units, all in progress.
No Image
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48
973
(OG)
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 180.78 70.485 10 13.5 8.501 8.5 78.985 100.295 45% 44%
November - 2018
Length 8 Km - out of 3 units, all in progress.
No Image
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48
973
(OG)
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 180.78 70.484 10 13.5 13.5005 8.5 78.984 100.296 45% 44%
April - 2019
Length 8 Km - out of 3 units, all in progress.
No Image
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48
973
(OG)
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 180.78 70.484 10 13.5 13.5005 8.5 78.984 100.296 45% 44%
March - 2019
Length 8 Km - out of 3 units, all in progress.
No Image
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48
973
(OG)
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 180.78 70.484 10 13.5 13.5005 8.5 78.984 100.296 45% 44%
March - 2019
Length 8 Km - out of 3 units, all in progress.
No Image
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48
973
(OG)
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 180.78 70.484 10 13.5 13.5005 8.5 78.984 100.296 45% 44%
February - 2019
Length 8 Km - out of 3 units, all in progress.
No Image
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48
973
(OG)
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 180.78 70.484 10 13.5 8.501 8.5 78.984 100.296 45% 44%
January - 2019
Length 8 Km - out of 3 units, all in progress.
No Image
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
27-05-16 - - 09-02-16 - 372.849 29.674 30 32.65 25.15 25.15 54.824 313.175 16% 15%
December - 2017
Length 10 Km - earth work, sub base completed, structure work (slab culvert) in progress.
No Image
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
- - - 09-02-16 - 372.849 29.674 30 37 17.75 17.75 47.424 313.175 16% 13%
September - 2017
Length 10 Km - earth work, sub base completed, structure work (slab culvert) in progress.
No Image
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
- - - 09-02-16 - 372.849 29.674 30 37 17.65 17.65 47.324 313.175 16% 13%
August - 2017
Length 10 Km - earth work, sub base completed, slab culvert in progress.
No Image
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
- - - 09-02-16 - 372.849 29.674 30 30 10.65 10.65 40.324 313.175 16% 11%
July - 2017
Length 10 Km - earth work, sub base completed, slab culvert in progress.
No Image
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 372.849 29.674 30 32.65 25.15 25.15 54.824 313.175 16% 15%
November - 2017
Length 10 Km - earth work, sub base completed, structure work (slab culvert) in progress.
No Image
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 372.849 29.674 30 37 17.75 17.75 47.424 313.175 16% 13%
October - 2017
Length 10 Km - earth work, sub base completed, structure work (slab culvert) in progress.
No Image
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 372.849 29.674 30 48.584 48.584 48.584 78.258 313.175 16% 21%
June - 2018
Length 15 Km (width 18ft) - earth work, sub base completed, structure work (slab culvert) in progress.
No Image
Bannu
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 372.849 29.674 30 48.584 48.584 48.584 78.258 313.175 16% 21%
May - 2018
Length 15 Km (width 18ft) - earth work, sub base completed, structure work (slab culvert) in progress.
No Image
Bannu
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 372.849 29.674 30 48.584 48.584 48.584 78.258 313.175 16% 21%
April - 2018
Length 15 Km (width 18ft) - earth work, sub base completed, structure work (slab culvert) in progress.
No Image
Bannu
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 372.849 29.674 30 48.584 48.584 46.381 76.055 313.175 16% 20%
March - 2018
Length 15 Km (width 18ft) - earth work, sub base completed, structure work (slab culvert) in progress.
No Image
Bannu
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 372.849 29.674 30 32.65 45.894 45.894 75.568 313.175 16% 20%
February - 2018
Length 15 Km (width 18ft) - earth work, sub base completed, structure work (slab culvert) in progress.
No Image
Bannu
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 372.849 29.674 30 32.65 45.894 25.15 54.824 313.175 16% 15%
January - 2018
Length 10 Km - earth work, sub base completed, structure work (slab culvert) in progress.
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 91.702 67.644 15 15 15 2.032 69.676 9.058 90% 76%
October - 2020
Academaic Block. W/S finishing & flooring in progress. Cafetaria - W/S finishing & flooring in progress. Residential portion. G/F finishing & flooring. Type-IV Qtr Excavation in progress.
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 91.702 67.644 15 15 15 2.032 69.676 9.058 90% 76%
September - 2020
Academaic Block. W/S finishing & flooring in progress. Cafetaria - W/S finishing & flooring in progress. Residential portion. G/F finishing & flooring. Type-IV Qtr Excavation in progress.
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 91.702 67.644 0 0 0 0 67.644 24.058 - 74%
August - 2020
Academaic Block. W/S finishing & flooring in progress. Cafetaria - W/S finishing & flooring in progress. Residential portion. G/F finishing & flooring. Type-IV Qtr Excavation in progress.
No Image
973
(New)
190584-Construction, Rehabilitation of internal roads of PK-30 District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 200 0 10 10 0 0 0 190 5% -
December - 2019
Approved . AA issued.
No Image
973
(New)
190584-Construction, Rehabilitation of internal roads of PK-30 District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 200 0 10 10 0 0 0 0 - -
November - 2019
Scheme deffered in PDWP meeting on 18/11/19. Re submitted to P&D
No Image
973
(New)
190584-Construction, Rehabilitation of internal roads of PK-30 District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 200 0 10 10 0 0 0 0 - -
October - 2019
DCE submitted to P&D. Pre PDWP held.
No Image
973
(New)
190584-Construction, Rehabilitation of internal roads of PK-30 District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 200 0 10 10 0 0 0 0 - -
September - 2019
DCE will be re submitted by 21-10-2019 on MRS 2019.
No Image
973
(New)
190584-Construction, Rehabilitation of internal roads of PK-30 District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 200 0 10 10 0 0 0 0 - -
August - 2019
Site identification awaited.
No Image
973
(New)
190584-Construction, Rehabilitation of internal roads of PK-30 District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 200 0 10 10 10 0 0 190 5% -
May - 2020
Work ordwer issued.
No Image
973
(New)
190584-Construction, Rehabilitation of internal roads of PK-30 District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 200 0 10 10 10 0 0 190 5% -
April - 2020
Work ordwer issued.
No Image
973
(New)
190584-Construction, Rehabilitation of internal roads of PK-30 District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 200 0 10 10 10 0 0 190 5% -
March - 2020
Work ordwer issued.
No Image
973
(New)
190584-Construction, Rehabilitation of internal roads of PK-30 District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 200 0 10 10 10 0 0 190 5% -
February - 2020
Work ordwer issued.
No Image
973
(New)
190584-Construction, Rehabilitation of internal roads of PK-30 District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 200 0 10 10 10 0 0 190 5% -
January - 2020
Tender floated.
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
December - 2020
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
December - 2020
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
October - 2020
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
September - 2020
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
August - 2020
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 91.702 67.644 35.058 0 0 0 67.644 0 100% 74%
July - 2020
Academaic Block. W/S finishing & flooring in progress. Cafetaria - W/S finishing & flooring in progress. Residential portion. G/F finishing & flooring. Type-IV Qtr Excavation in progress.
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 0 0 0 64.644 0
July - 2020
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
May - 2021
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
April - 2021
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
March - 2021
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
February - 2021
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
January - 2021
No Image