Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2019, January - 2020, January - 2021, February - 2018, February - 2019, February - 2020, February - 2021, March - 2018, March - 2019, March - 2020, March - 2021, April - 2018, April - 2019, April - 2020, April - 2021, May - 2018, May - 2020, May - 2021, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
969
(OG)
140782-F/S, Design, Construction, Improvement and Black Topping of Roads in Galyat Region, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 324.287 116.05 25 25 25 24.999 141.049 183.237 43% 43%
December - 2018
Length 26 Km (5 units) - earth work, structure work in progress.
No Image
1) Improvement/expansion and BT of Kahu to Julial road (2 Km) PK-45
2) Construction of road from Jandal to Lower Palak road (6 Km) PK-45
3) Improvement and BT of road from Mumbal to Kurli road (4 Km) PK-45
4) Improvement and BT of road from Butti to Lower Surjal Dana raod (10 Km) PK-45
5) Rehabilitation of flood damage road i/c bridge at Hoterol to BHU Mohra (4 Km) PK-45
969
(OG)
140782-F/S, Design, Construction, Improvement and Black Topping of Roads in Galyat Region, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 324.287 116.05 25 25 25 24.999 141.049 183.237 43% 43%
November - 2018
Length 26 Km (5 units) - earth work, structure work in progress.
No Image
1) Improvement/expansion and BT of Kahu to Julial road (2 Km) PK-45
2) Construction of road from Jandal to Lower Palak road (6 Km) PK-45
3) Improvement and BT of road from Mumbal to Kurli road (4 Km) PK-45
4) Improvement and BT of road from Butti to Lower Surjal Dana raod (10 Km) PK-45
5) Rehabilitation of flood damage road i/c bridge at Hoterol to BHU Mohra (4 Km) PK-45
969
(OG)
140782-F/S, Design, Construction, Improvement and Black Topping of Roads in Galyat Region, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 324.287 116.05 25 25 25 24.999 141.049 183.237 43% 43%
November - 2018
Length 26 Km (5 units) - earth work, structure work in progress.
No Image
1) Improvement/expansion and BT of Kahu to Julial road (2 Km) PK-45
2) Construction of road from Jandal to Lower Palak road (6 Km) PK-45
3) Improvement and BT of road from Mumbal to Kurli road (4 Km) PK-45
4) Improvement and BT of road from Butti to Lower Surjal Dana raod (10 Km) PK-45
5) Rehabilitation of flood damage road i/c bridge at Hoterol to BHU Mohra (4 Km) PK-45
969
(OG)
140782-F/S, Design, Construction, Improvement and Black Topping of Roads in Galyat Region, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 324.287 116.05 25 25 25 24.999 141.049 183.237 43% 43%
April - 2019
Length 26 Km (5 units) - earth work, structure work in progress.
No Image
1) Improvement/expansion and BT of Kahu to Julial road (2 Km) PK-45
2) Construction of road from Jandal to Lower Palak road (6 Km) PK-45
3) Improvement and BT of road from Mumbal to Kurli road (4 Km) PK-45
4) Improvement and BT of road from Butti to Lower Surjal Dana raod (10 Km) PK-45
5) Rehabilitation of flood damage road i/c bridge at Hoterol to BHU Mohra (4 Km) PK-45
969
(OG)
140782-F/S, Design, Construction, Improvement and Black Topping of Roads in Galyat Region, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 324.287 116.05 25 25 25 24.999 141.049 183.237 43% 43%
March - 2019
Length 26 Km (5 units) - earth work, structure work in progress.
No Image
1) Improvement/expansion and BT of Kahu to Julial road (2 Km) PK-45
2) Construction of road from Jandal to Lower Palak road (6 Km) PK-45
3) Improvement and BT of road from Mumbal to Kurli road (4 Km) PK-45
4) Improvement and BT of road from Butti to Lower Surjal Dana raod (10 Km) PK-45
5) Rehabilitation of flood damage road i/c bridge at Hoterol to BHU Mohra (4 Km) PK-45
969
(OG)
140782-F/S, Design, Construction, Improvement and Black Topping of Roads in Galyat Region, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 324.287 116.05 25 25 25 24.999 141.049 183.237 43% 43%
March - 2019
Length 26 Km (5 units) - earth work, structure work in progress.
No Image
1) Improvement/expansion and BT of Kahu to Julial road (2 Km) PK-45
2) Construction of road from Jandal to Lower Palak road (6 Km) PK-45
3) Improvement and BT of road from Mumbal to Kurli road (4 Km) PK-45
4) Improvement and BT of road from Butti to Lower Surjal Dana raod (10 Km) PK-45
5) Rehabilitation of flood damage road i/c bridge at Hoterol to BHU Mohra (4 Km) PK-45
969
(OG)
140782-F/S, Design, Construction, Improvement and Black Topping of Roads in Galyat Region, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 324.287 116.05 25 25 25 24.999 141.049 183.237 43% 43%
February - 2019
Length 26 Km (5 units) - earth work, structure work in progress.
No Image
1) Improvement/expansion and BT of Kahu to Julial road (2 Km) PK-45
2) Construction of road from Jandal to Lower Palak road (6 Km) PK-45
3) Improvement and BT of road from Mumbal to Kurli road (4 Km) PK-45
4) Improvement and BT of road from Butti to Lower Surjal Dana raod (10 Km) PK-45
5) Rehabilitation of flood damage road i/c bridge at Hoterol to BHU Mohra (4 Km) PK-45
969
(OG)
140782-F/S, Design, Construction, Improvement and Black Topping of Roads in Galyat Region, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 324.287 116.05 25 25 25 24.999 141.049 183.237 43% 43%
January - 2019
Length 26 Km (5 units) - earth work, structure work in progress.
No Image
1) Improvement/expansion and BT of Kahu to Julial road (2 Km) PK-45
2) Construction of road from Jandal to Lower Palak road (6 Km) PK-45
3) Improvement and BT of road from Mumbal to Kurli road (4 Km) PK-45
4) Improvement and BT of road from Butti to Lower Surjal Dana raod (10 Km) PK-45
5) Rehabilitation of flood damage road i/c bridge at Hoterol to BHU Mohra (4 Km) PK-45
969
(New)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 0 30 30 0 0 0 418.952 7% -
December - 2019
Procuremnet in Progress.
No Image
969
(New)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 0 30 30 0 0 0 418.952 7% -
November - 2019
Procuremnet in Progress.
No Image
969
(New)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 0 30 30 0 0 0 418.952 7% -
October - 2019
Land acquisation in progress. Procuremnet in progress.
No Image
969
(New)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 360 0 30 30 0 0 0 0 - -
September - 2019
PC-I/DCE for Rs.463.420 m submitted to P&D. PDWP Held. Deffered.
No Image
969
(New)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 360 0 30 30 0 0 0 0 - -
August - 2019
PC-I/DCE for Rs.463.420 m submitted to P&D on 18/09/2019.
No Image
969
(New)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 0 30 30 0 0 0 418.952 7% -
May - 2020
Work started.
No Image
969
(New)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 0 30 30 0 0 0 418.952 7% -
April - 2020
Work started.
No Image
969
(New)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 0 30 30 0 0 0 418.952 7% -
March - 2020
Work started.
No Image
969
(New)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 0 30 30 0 0 0 418.952 7% -
February - 2020
Work started.
No Image
969
(New)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 0 30 30 0 0 0 418.952 7% -
January - 2020
Work order issued.
No Image
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
- - - 03-11-16 - 96.787 0 20 17.1 12.1 7.472 7.472 76.787 21% 8%
December - 2017
Length 5.15 Km - earth work 50% completed.
No Image
To be change of nomenclature
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
- - - 03-11-16 - 96.787 0 20 20 7.1 1.283 1.283 76.787 21% 1%
September - 2017
Length 5.15 Km - earth work 50% completed.
No Image
To be change of nomenclature
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
- - - 03-11-16 - 96.787 0 20 20 7.1 0 0 76.787 21% -
August - 2017
Earth work 50% completed.
No Image
To be change of nomenclature
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
- - - 03-11-16 - 96.787 0 20 20 7.1 0 0 76.787 21% -
July - 2017
Earth work 50% completed.
No Image
To be change of nomenclature
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 96.787 0 20 17.1 12.1 3.93 3.93 76.787 21% 4%
November - 2017
Length 5.15 Km - earth work 50% completed.
No Image
To be change of nomenclature
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 96.787 0 20 20 7.1 2.721 2.721 76.787 21% 3%
October - 2017
Length 5.15 Km - earth work 50% completed.
No Image
To be change of nomenclature
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 96.787 0 20 15.68 15.68 15.68 15.68 76.787 21% 16%
June - 2018
Length 5.15 Km (width 18 ft) - earth work, sub base, base course 80% completed.
No Image
PK-75, Lakki Marwat
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 96.787 0 20 17.1 17.1 14.347 14.347 76.787 21% 15%
May - 2018
Length 5.15 Km (width 18 ft) - earth work, sub base, base course 80% completed.
No Image
PK-75, Lakki Marwat
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 96.787 0 20 17.1 17.1 12.999 12.999 76.787 21% 13%
April - 2018
Length 5.15 Km (width 18 ft) - earth work, sub base, base course 80% completed.
No Image
PK-75, Lakki Marwat
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 96.787 0 20 17.1 12.1 12 12 76.787 21% 12%
March - 2018
Length 5.15 Km (width 18 ft) - earth work, sub base, base course 80% completed.
No Image
PK-75, Lakki Marwat
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 96.787 0 20 17.1 12.1 9.55 9.55 76.787 21% 10%
February - 2018
Length 5.15 Km (Width 18 ft) - earth work , sub Base , Base corse 80 % completed.
ADP's Images
PK-75, Lakki Marwat
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 96.787 0 20 17.1 12.1 7.472 7.472 76.787 21% 8%
January - 2018
Length 5.15 Km - earth work 50% completed.
No Image
To be change of nomenclature
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 18.818 11 0 126.041 33.64 81% 71%
December - 2020
MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 18.818 11 0 126.041 33.64 81% 71%
December - 2020
MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 18.818 7 0 126.041 33.64 81% 71%
October - 2020
MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 18.818 7 0 126.041 33.64 81% 71%
September - 2020
MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 18.818 7 0 126.041 33.64 81% 71%
August - 2020
MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 159.681 18.818 0 0 0 159.681 0
July - 2020
No Image
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 11.417 11.417 8.416 134.457 33.64 81% 75%
May - 2021
01- Unit MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
Construction of Boys Degree College, Orakzai
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 11 11 0 126.041 33.64 81% 71%
April - 2021
MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
Construction of Boys Degree College, Orakzai
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 11 11 0 126.041 33.64 81% 71%
March - 2021
MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
Construction of Boys Degree College, Orakzai
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 11 11 0 126.041 33.64 81% 71%
February - 2021
MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
Construction of Boys Degree College, Orakzai
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 11 11 0 126.041 33.64 81% 71%
January - 2021
MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
Construction of Boys Degree College, Orakzai
Pages : 1