Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2019, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2019, December - 2020, December - 2017, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
968
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 126.5 81.12 39.503 37.528 17.776 16.905 98.025 5.877 95% 77%
December - 2018
Length 8 Km - 5 km BT complted .
No Image
PK-47, Abbottabad
968
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 126.5 81.12 39.503 37.528 17.776 5.966 87.086 5.877 95% 69%
November - 2018
Length 5 Km - earth work 100%, structure work 100%, road work 100% completed.
No Image
PK-47, Abbottabad
968
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 126.5 81.12 39.503 37.528 17.776 5.966 87.086 5.877 95% 69%
November - 2018
Length 5 Km - earth work 100%, structure work 100%, road work 100% completed.
No Image
PK-47, Abbottabad
968
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 126.5 81.12 39.503 37.5279 37.5284 15.905 97.025 5.877 95% 77%
April - 2019
Length 8 Km - 5 Km BT completed.
No Image
PK-47, Abbottabad
968
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 126.5 81.12 39.503 37.5279 37.5284 15.905 97.025 5.877 95% 77%
March - 2019
Length 8 Km - 5 Km BT completed.
No Image
PK-47, Abbottabad
968
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 126.5 81.12 39.503 37.5279 37.5284 15.905 97.025 5.877 95% 77%
March - 2019
Length 8 Km - 5 Km BT completed.
No Image
PK-47, Abbottabad
968
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 126.5 81.12 39.503 37.5279 37.5284 15.905 97.025 5.877 95% 77%
February - 2019
Length 8 Km - 5 Km BT completed.
No Image
PK-47, Abbottabad
968
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 126.5 81.12 39.503 37.528 17.759 15.905 97.025 5.877 95% 77%
January - 2019
Length 8 Km - 5 km BT complted .
No Image
PK-47, Abbottabad
968
(New)
190235-Construction of RCC Bridge on River Panjkora at Timergara Bypass to Kandaro Munda Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 260 0 27.241 27.241 0 0 0 0 - -
December - 2019
DCSC meeting helf on 8/01/2020. Technical proposal opened.
No Image
968
(New)
190235-Construction of RCC Bridge on River Panjkora at Timergara Bypass to Kandaro Munda Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 260 0 27.241 27.241 0 0 0 0 - -
November - 2019
PC-II approved for Rs. 5.2 m. NIT flaoted.
No Image
968
(New)
190235-Construction of RCC Bridge on River Panjkora at Timergara Bypass to Kandaro Munda Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 260 0 27.241 27.241 0 0 0 0 - -
October - 2019
PC-II Approved for Rs. 13.0 M . AA awaited.
No Image
968
(New)
190235-Construction of RCC Bridge on River Panjkora at Timergara Bypass to Kandaro Munda Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 260 0 27.241 27.241 0 0 0 0 - -
September - 2019
PC-II re-submitted to P&D.
No Image
968
(New)
190235-Construction of RCC Bridge on River Panjkora at Timergara Bypass to Kandaro Munda Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 260 0 27.241 27.241 0 0 0 0 - -
August - 2019
PC-II submitted to P&D. Observations will be attended.
No Image
968
(New)
190235-Construction of RCC Bridge on River Panjkora at Timergara Bypass to Kandaro Munda Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 260 0 27.241 5.2 5.2 0 0 0 - -
May - 2020
Combined Evaluation of consultants issued.
No Image
968
(New)
190235-Construction of RCC Bridge on River Panjkora at Timergara Bypass to Kandaro Munda Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 260 0 27.241 5.2 5.2 0 0 0 - -
April - 2020
Combined Evaluation of consultants issued.
No Image
968
(New)
190235-Construction of RCC Bridge on River Panjkora at Timergara Bypass to Kandaro Munda Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 260 0 27.241 5.2 5.2 0 0 0 - -
March - 2020
Combined Evaluation of consultants issued.
No Image
968
(New)
190235-Construction of RCC Bridge on River Panjkora at Timergara Bypass to Kandaro Munda Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 260 0 27.241 5.2 5.2 0 0 0 - -
February - 2020
Combined Evaluation of consultants issued.
No Image
968
(New)
190235-Construction of RCC Bridge on River Panjkora at Timergara Bypass to Kandaro Munda Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 260 0 27.241 27.241 0 0 0 0 - -
January - 2020
DCSC meeting helf on 8/01/2020. Technical evaluatiobn submitted to CE
No Image
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
02-07-15 - - 28-01-15 - 293.915 129.61 40 34.2 34.2 34.2 163.81 124.305 58% 56%
December - 2017
Length 21.5 Km - earth work 13 Km completed. Sub-base 13 Km completed, base course (8-Km completed), remaining in progress, TST (8-Km completed) remaining in progress.
No Image
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
02-07-15 - - 28-01-15 - 293.915 129.61 40 40 14.8 14.8 144.41 124.305 58% 49%
September - 2017
Length 21.5 Km - earth work 13 Km completed. Sub-base 13 Km completed, base course (8-Km completed), remaining in progress, TST (8-Km completed) remaining in progress.
No Image
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
02-07-15 - - 28-01-15 - 293.915 129.61 40 40 14.8 14.8 144.41 124.305 58% 49%
August - 2017
Length 21.5 Km - earth work 13 Km completed. Sub-base 13 Km completed, base course in progress.
No Image
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
02-07-15 - - 28-01-15 - 293.915 129.61 40 40 14.2 0 129.61 124.305 58% 44%
July - 2017
Length 21.5 Km - earth work 13 Km completed. Sub-base 13 Km completed, base course in progress.
No Image
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 293.915 129.61 40 34.2 34.2 34.2 163.81 124.305 58% 56%
November - 2017
Length 21.5 Km - earth work 13 Km completed. Sub-base 13 Km completed, base course (8-Km completed), remaining in progress, TST (8-Km completed) remaining in progress.
No Image
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 293.915 129.61 40 40 34.2 34.2 163.81 124.305 58% 56%
October - 2017
Length 21.5 Km - earth work 13 Km completed. Sub-base 13 Km completed, base course (8-Km completed), remaining in progress, TST (8-Km completed) remaining in progress.
No Image
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 293.915 129.61 40 54.2 54.2 54.2 183.81 124.305 58% 63%
June - 2018
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed.
No Image
Lakki Marwat (21.50 Km)
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 293.915 129.61 40 54.2 54.2 54.2 183.81 124.305 58% 63%
May - 2018
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed.
No Image
Lakki Marwat (21.50 Km)
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 293.915 129.61 40 54.2 54.2 54.079 183.689 124.305 58% 62%
April - 2018
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed.
No Image
Lakki Marwat (21.50 Km)
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 293.915 129.61 40 54.2 54.2 54.079 183.689 124.305 58% 62%
March - 2018
Length 21.5 Km - Earth work , Sub base completed, Base course 7 km complted, TST 4 km Complted.
No Image
Lakki Marwat (21.50 Km)
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 293.915 129.61 40 54.2 54.2 53.108 182.718 124.305 58% 62%
February - 2018
Length 21.5 Km - Earth work , Sub base completed, Base course 7 km complted, TST 4 km Complted.
ADP's Images
Lakki Marwat (21.50 Km)
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 293.915 129.61 40 34.2 34.2 34.2 163.81 124.305 58% 56%
January - 2018
Length 21.5 Km - earth work 13 Km completed. Sub-base 13 Km completed, base course (8-Km completed), remaining in progress, TST (8-Km completed) remaining in progress.
No Image
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 57.273 28.442 3.49 45.763 0 100% 46%
December - 2020
03- Packages Work in progress.
No Image
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 57.273 28.442 3.49 45.763 0 100% 46%
December - 2020
03- Packages Work in progress.
No Image
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 57.273 15 2.037 44.31 0 100% 45%
October - 2020
03- Packages Work in progress.
No Image
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 57.273 15 2.037 44.31 0 100% 45%
September - 2020
03- Packages Work in progress.
No Image
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 57.273 15 0 42.273 0 100% 42%
August - 2020
03- Packages Work in progress.
No Image
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 28.442 28.442 4.442 46.715 0 100% 47%
May - 2021
03- Packages Work in progress.
No Image
Package 1
Package 2
Package 3
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 28.442 28.442 3.49 45.763 0 100% 46%
April - 2021
03- Packages Work in progress.
No Image
Package 1
Package 2
Package 3
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 28.442 28.442 3.49 45.763 0 100% 46%
March - 2021
03- Packages Work in progress.
No Image
Package 1
Package 2
Package 3
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 28.442 28.442 3.49 45.763 0 100% 46%
February - 2021
03- Packages Work in progress.
No Image
Package 1
Package 2
Package 3
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 28.442 28.442 3.49 45.763 0 100% 46%
January - 2021
03- Packages Work in progress.
No Image
Package 1
Package 2
Package 3
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Wazirstan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 0 0 0 42.273 0
July - 2020
No Image