Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
15-04-16 | - | - | 05-05-17 | - | 199.822 | 78.357 | 20 | 17.1 | 12.1 | 12.1 | 90.457 | 101.465 | 49% |
45% December - 2017 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed. |
No Image |
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.822 | 78.357 | 20 | 17.1 | 12.1 | 12.1 | 90.457 | 101.465 | 49% |
45% November - 2017 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed. |
No Image |
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.822 | 78.357 | 20 | 20 | 7.1 | 7.1 | 85.457 | 101.465 | 49% |
43% October - 2017 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed. |
No Image |
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
15-04-16 | - | - | 05-05-17 | - | 199.822 | 78.357 | 20 | 20 | 7.1 | 7.1 | 85.457 | 101.465 | 49% |
43% September - 2017 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed. |
No Image |
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
15-04-16 | - | - | 05-05-17 | - | 199.822 | 78.357 | 20 | 20 | 7.1 | 7.1 | 85.457 | 101.465 | 49% |
43% August - 2017 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - not started. Bridge - boring soil investigation, confirmatory boring, test pile loading completed. |
No Image |
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
15-04-16 | - | - | 05-05-17 | - | 199.822 | 78.357 | 20 | 20 | 7.1 | 0 | 78.357 | 101.465 | 49% |
39% July - 2017 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - not started. Bridge - boring soil investigation, confirmatory boring, test pile loading completed. |
No Image |
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.822 | 78.357 | 20 | 27.473 | 27.473 | 27.473 | 105.83 | 101.465 | 49% |
53% June - 2018 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - compelted (length 120 ft, 4 span). |
No Image |
1) Panyala Paharpur road 4 Km
2) Panyala Chunda road 3 Km
3) Paharpur Bypass road 2.3 Km
4) Construction of 1 No bridge on Panyala Bypass road
5) Paharpur Bypass road (balance portion) 3.30 Km | |||||||||||||||||||
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.822 | 78.357 | 20 | 27.473 | 27.473 | 27.473 | 105.83 | 101.465 | 49% |
53% May - 2018 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - compelted (length 120 ft, 4 span). |
No Image |
1) Panyala Paharpur road 4 Km
2) Panyala Chunda road 3 Km
3) Paharpur Bypass road 2.3 Km
4) Construction of 1 No bridge on Panyala Bypass road
5) Paharpur Bypass road (balance portion) 3.30 Km | |||||||||||||||||||
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.822 | 78.357 | 20 | 27.473 | 27.473 | 24.783 | 103.14 | 101.465 | 49% |
52% April - 2018 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - compelted (length 120 ft, 4 span). |
No Image |
1) Panyala Paharpur road 4 Km
2) Panyala Chunda road 3 Km
3) Paharpur Bypass road 2.3 Km
4) Construction of 1 No bridge on Panyala Bypass road
5) Paharpur Bypass road (balance portion) 3.30 Km | |||||||||||||||||||
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.822 | 78.357 | 20 | 27.473 | 27.473 | 24.783 | 103.14 | 101.465 | 49% |
52% March - 2018 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - compelted (length 120 ft, 4 span). |
No Image |
1) Panyala Paharpur road 4 Km
2) Panyala Chunda road 3 Km
3) Paharpur Bypass road 2.3 Km
4) Construction of 1 No bridge on Panyala Bypass road
5) Paharpur Bypass road (balance portion) 3.30 Km | |||||||||||||||||||
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.822 | 78.357 | 20 | 24.783 | 24.783 | 24.783 | 103.14 | 101.465 | 49% |
52% February - 2018 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - Complted ( Length 120 ft , 4 span ) |
No Image |
1) Panyala Paharpur road 4 Km
2) Panyala Chunda road 3 Km
3) Paharpur Bypass road 2.3 Km
4) Construction of 1 No bridge on Panyala Bypass road
5) Paharpur Bypass road (balance portion) 3.30 Km | |||||||||||||||||||
967 (OG) |
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.822 | 78.357 | 20 | 24.783 | 24.783 | 12.1 | 90.457 | 101.465 | 49% |
45% January - 2018 |
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed. |
No Image |
967 (OG) |
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 5 | 45 | 42.75 | 20.2505 | 11.442 | 16.442 | 0 | 100% |
33% December - 2018 |
Length 5 Km (width 18 ft) - earth work completed, structure work in progress. |
No Image |
Mansehra | |||||||||||||||||||
967 (OG) |
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 5 | 45 | 42.75 | 20.251 | 5.53 | 10.53 | 0 | 100% |
21% November - 2018 |
Length 5 Km (width 18 ft) - earth work completed, structure work in progress. |
No Image |
Mansehra | |||||||||||||||||||
967 (OG) |
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 5 | 45 | 42.75 | 20.251 | 5.53 | 10.53 | 0 | 100% |
21% November - 2018 |
Length 5 Km (width 18 ft) - earth work completed, structure work in progress. |
No Image |
Mansehra | |||||||||||||||||||
967 (OG) |
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 5 | 45 | 42.75 | 42.7505 | 22.144 | 27.144 | 0 | 100% |
54% April - 2019 |
Length 5 Km (width 18 ft) - earth work completed, structure work in progress. |
No Image |
Mansehra | |||||||||||||||||||
967 (OG) |
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 5 | 45 | 42.75 | 42.7505 | 19.625 | 24.625 | 0 | 100% |
49% March - 2019 |
Length 5 Km (width 18 ft) - earth work completed, structure work in progress. |
No Image |
Mansehra | |||||||||||||||||||
967 (OG) |
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 5 | 45 | 42.75 | 42.7505 | 19.625 | 24.625 | 0 | 100% |
49% March - 2019 |
Length 5 Km (width 18 ft) - earth work completed, structure work in progress. |
No Image |
Mansehra | |||||||||||||||||||
967 (OG) |
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 5 | 45 | 42.75 | 42.7505 | 14.653 | 19.653 | 0 | 100% |
39% February - 2019 |
Length 5 Km (width 18 ft) - earth work completed, structure work in progress. |
No Image |
Mansehra | |||||||||||||||||||
967 (OG) |
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 5 | 45 | 42.75 | 20.2505 | 11.382 | 16.382 | 0 | 100% |
33% January - 2019 |
Length 5 Km (width 18 ft) - earth work completed, structure work in progress. |
No Image |
Mansehra | |||||||||||||||||||
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 97.691 | 54.91 | 54.91 | 27.887 | 7.015 | 104.706 | 9.999 | 94% |
64% December - 2020 |
04- Packages
Work in progress on all packages. |
No Image |
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 97.691 | 54.91 | 54.91 | 27.887 | 7.015 | 104.706 | 9.999 | 94% |
64% December - 2020 |
04- Packages
Work in progress on all packages. |
No Image |
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 97.691 | 54.91 | 54.91 | 15 | 0 | 97.691 | 9.999 | 94% |
60% October - 2020 |
04- Packages
Work in progress on all packages. |
No Image |
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 97.691 | 54.91 | 54.91 | 15 | 0 | 97.691 | 9.999 | 94% |
60% September - 2020 |
04- Packages
Work in progress on all packages. |
No Image |
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 97.691 | 54.91 | 54.91 | 15 | 0 | 97.691 | 9.999 | 94% |
60% August - 2020 |
04- Packages
Work in progress on all packages. |
No Image |
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 97.691 | 54.91 | 27.887 | 27.887 | 10.955 | 108.646 | 9.999 | 94% |
67% May - 2021 |
04- Packages
Work in progress on all packages. |
No Image |
Package 1
Package 2
Package 3
Package 4 | |||||||||||||||||||
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 97.691 | 54.91 | 27.887 | 27.887 | 10.955 | 108.646 | 9.999 | 94% |
67% April - 2021 |
04- Packages
Work in progress on all packages. |
No Image |
Package 1
Package 2
Package 3
Package 4 | |||||||||||||||||||
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 97.691 | 54.91 | 27.887 | 27.887 | 10.955 | 108.646 | 9.999 | 94% |
67% March - 2021 |
04- Packages
Work in progress on all packages. |
No Image |
Package 1
Package 2
Package 3
Package 4 | |||||||||||||||||||
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 97.691 | 54.91 | 27.887 | 27.887 | 10.955 | 108.646 | 9.999 | 94% |
67% February - 2021 |
04- Packages
Work in progress on all packages. |
No Image |
Package 1
Package 2
Package 3
Package 4 | |||||||||||||||||||
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 97.691 | 54.91 | 27.887 | 27.887 | 10.955 | 108.646 | 9.999 | 94% |
67% January - 2021 |
04- Packages
Work in progress on all packages. |
No Image |
Package 1
Package 2
Package 3
Package 4 | |||||||||||||||||||
967 (OG) |
191575-160036 - Re-construction of GDC Ladha, SWA. [MA] |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.6 | 107.69 | 54.91 | 0 | 0 | 0 | 107.69 | 0 |
July - 2020 |
No Image | ||
967 (New) |
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 0 | 0 | 0 | 290 | 3% |
- December - 2019 |
Financial Bids approval of contractors in processs. |
No Image |
967 (New) |
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 0 | 0 | 0 | 290 | 3% |
- November - 2019 |
Approval of Post Qualification of contractors in processs. |
No Image |
967 (New) |
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 0 | 0 | 0 | 290 | 3% |
- October - 2019 |
Technical bid opening obn 15/12/2019. |
No Image |
967 (New) |
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 10 | 10 | 0 | 0 | 0 | 290 | 3% |
- September - 2019 |
Approved. Procuremnet in progress. |
No Image |
967 (New) |
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
PC-II submitted to SE Swat on 29/08/2019. PC-I/DCE for Rs.300 m submitted to P&D on 18/09/2019. |
No Image |
967 (New) |
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 10 | 10 | 10 | 290 | 3% |
3% May - 2020 |
4 - Units
2 - Work order issued
2 - Work in progress. |
No Image |
967 (New) |
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 10 | 10 | 10 | 290 | 3% |
3% April - 2020 |
4 - Units
2 - Work order issued
2 - Work in progress. |
No Image |
967 (New) |
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 10 | 10 | 10 | 290 | 3% |
3% March - 2020 |
4 - Units
2 - Work order issued
2 - Work in progress. |
No Image |
967 (New) |
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 10 | 10 | 10 | 290 | 3% |
3% February - 2020 |
4 - Units
2 - Work order issued
2 - Work in progress. |
No Image |
967 (New) |
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 10 | 10 | 10 | 290 | 3% |
3% January - 2020 |
Financial Bids approval of contractors in processs. |
No Image |
Pages : 1 |