Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2019, February - 2020, February - 2021, February - 2018, March - 2019, March - 2020, March - 2021, March - 2018, April - 2019, April - 2020, April - 2021, April - 2018, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
15-04-16 - - 05-05-17 - 199.822 78.357 20 17.1 12.1 12.1 90.457 101.465 49% 45%
December - 2017
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed.
No Image
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.822 78.357 20 17.1 12.1 12.1 90.457 101.465 49% 45%
November - 2017
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed.
No Image
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.822 78.357 20 20 7.1 7.1 85.457 101.465 49% 43%
October - 2017
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed.
No Image
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
15-04-16 - - 05-05-17 - 199.822 78.357 20 20 7.1 7.1 85.457 101.465 49% 43%
September - 2017
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed.
No Image
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
15-04-16 - - 05-05-17 - 199.822 78.357 20 20 7.1 7.1 85.457 101.465 49% 43%
August - 2017
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - not started. Bridge - boring soil investigation, confirmatory boring, test pile loading completed.
No Image
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
15-04-16 - - 05-05-17 - 199.822 78.357 20 20 7.1 0 78.357 101.465 49% 39%
July - 2017
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - not started. Bridge - boring soil investigation, confirmatory boring, test pile loading completed.
No Image
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.822 78.357 20 27.473 27.473 27.473 105.83 101.465 49% 53%
June - 2018
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - compelted (length 120 ft, 4 span).
No Image
1) Panyala Paharpur road 4 Km
2) Panyala Chunda road 3 Km
3) Paharpur Bypass road 2.3 Km
4) Construction of 1 No bridge on Panyala Bypass road
5) Paharpur Bypass road (balance portion) 3.30 Km
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.822 78.357 20 27.473 27.473 27.473 105.83 101.465 49% 53%
May - 2018
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - compelted (length 120 ft, 4 span).
No Image
1) Panyala Paharpur road 4 Km
2) Panyala Chunda road 3 Km
3) Paharpur Bypass road 2.3 Km
4) Construction of 1 No bridge on Panyala Bypass road
5) Paharpur Bypass road (balance portion) 3.30 Km
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.822 78.357 20 27.473 27.473 24.783 103.14 101.465 49% 52%
April - 2018
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - compelted (length 120 ft, 4 span).
No Image
1) Panyala Paharpur road 4 Km
2) Panyala Chunda road 3 Km
3) Paharpur Bypass road 2.3 Km
4) Construction of 1 No bridge on Panyala Bypass road
5) Paharpur Bypass road (balance portion) 3.30 Km
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.822 78.357 20 27.473 27.473 24.783 103.14 101.465 49% 52%
March - 2018
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - compelted (length 120 ft, 4 span).
No Image
1) Panyala Paharpur road 4 Km
2) Panyala Chunda road 3 Km
3) Paharpur Bypass road 2.3 Km
4) Construction of 1 No bridge on Panyala Bypass road
5) Paharpur Bypass road (balance portion) 3.30 Km
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.822 78.357 20 24.783 24.783 24.783 103.14 101.465 49% 52%
February - 2018
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - Complted ( Length 120 ft , 4 span )
No Image
1) Panyala Paharpur road 4 Km
2) Panyala Chunda road 3 Km
3) Paharpur Bypass road 2.3 Km
4) Construction of 1 No bridge on Panyala Bypass road
5) Paharpur Bypass road (balance portion) 3.30 Km
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.822 78.357 20 24.783 24.783 12.1 90.457 101.465 49% 45%
January - 2018
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed.
No Image
967
(OG)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 5 45 42.75 20.2505 11.442 16.442 0 100% 33%
December - 2018
Length 5 Km (width 18 ft) - earth work completed, structure work in progress.
No Image
Mansehra
967
(OG)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 5 45 42.75 20.251 5.53 10.53 0 100% 21%
November - 2018
Length 5 Km (width 18 ft) - earth work completed, structure work in progress.
No Image
Mansehra
967
(OG)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 5 45 42.75 20.251 5.53 10.53 0 100% 21%
November - 2018
Length 5 Km (width 18 ft) - earth work completed, structure work in progress.
No Image
Mansehra
967
(OG)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 5 45 42.75 42.7505 22.144 27.144 0 100% 54%
April - 2019
Length 5 Km (width 18 ft) - earth work completed, structure work in progress.
No Image
Mansehra
967
(OG)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 5 45 42.75 42.7505 19.625 24.625 0 100% 49%
March - 2019
Length 5 Km (width 18 ft) - earth work completed, structure work in progress.
No Image
Mansehra
967
(OG)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 5 45 42.75 42.7505 19.625 24.625 0 100% 49%
March - 2019
Length 5 Km (width 18 ft) - earth work completed, structure work in progress.
No Image
Mansehra
967
(OG)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 5 45 42.75 42.7505 14.653 19.653 0 100% 39%
February - 2019
Length 5 Km (width 18 ft) - earth work completed, structure work in progress.
No Image
Mansehra
967
(OG)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 5 45 42.75 20.2505 11.382 16.382 0 100% 33%
January - 2019
Length 5 Km (width 18 ft) - earth work completed, structure work in progress.
No Image
Mansehra
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 54.91 27.887 7.015 104.706 9.999 94% 64%
December - 2020
04- Packages Work in progress on all packages.
No Image
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 54.91 27.887 7.015 104.706 9.999 94% 64%
December - 2020
04- Packages Work in progress on all packages.
No Image
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 54.91 15 0 97.691 9.999 94% 60%
October - 2020
04- Packages Work in progress on all packages.
No Image
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 54.91 15 0 97.691 9.999 94% 60%
September - 2020
04- Packages Work in progress on all packages.
No Image
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 54.91 15 0 97.691 9.999 94% 60%
August - 2020
04- Packages Work in progress on all packages.
No Image
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 27.887 27.887 10.955 108.646 9.999 94% 67%
May - 2021
04- Packages Work in progress on all packages.
No Image
Package 1
Package 2
Package 3
Package 4
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 27.887 27.887 10.955 108.646 9.999 94% 67%
April - 2021
04- Packages Work in progress on all packages.
No Image
Package 1
Package 2
Package 3
Package 4
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 27.887 27.887 10.955 108.646 9.999 94% 67%
March - 2021
04- Packages Work in progress on all packages.
No Image
Package 1
Package 2
Package 3
Package 4
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 27.887 27.887 10.955 108.646 9.999 94% 67%
February - 2021
04- Packages Work in progress on all packages.
No Image
Package 1
Package 2
Package 3
Package 4
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 27.887 27.887 10.955 108.646 9.999 94% 67%
January - 2021
04- Packages Work in progress on all packages.
No Image
Package 1
Package 2
Package 3
Package 4
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Wazirstan
30-11--1 30-11--1 - 30-11--1 - 162.6 107.69 54.91 0 0 0 107.69 0
July - 2020
No Image
967
(New)
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 300 0 10 10 0 0 0 290 3% -
December - 2019
Financial Bids approval of contractors in processs.
No Image
967
(New)
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 300 0 10 10 0 0 0 290 3% -
November - 2019
Approval of Post Qualification of contractors in processs.
No Image
967
(New)
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 300 0 10 10 0 0 0 290 3% -
October - 2019
Technical bid opening obn 15/12/2019.
No Image
967
(New)
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 10 10 0 0 0 290 3% -
September - 2019
Approved. Procuremnet in progress.
No Image
967
(New)
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 10 10 0 0 0 0 - -
August - 2019
PC-II submitted to SE Swat on 29/08/2019. PC-I/DCE for Rs.300 m submitted to P&D on 18/09/2019.
No Image
967
(New)
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 300 0 10 10 10 10 10 290 3% 3%
May - 2020
4 - Units 2 - Work order issued 2 - Work in progress.
No Image
967
(New)
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 300 0 10 10 10 10 10 290 3% 3%
April - 2020
4 - Units 2 - Work order issued 2 - Work in progress.
No Image
967
(New)
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 300 0 10 10 10 10 10 290 3% 3%
March - 2020
4 - Units 2 - Work order issued 2 - Work in progress.
No Image
967
(New)
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 300 0 10 10 10 10 10 290 3% 3%
February - 2020
4 - Units 2 - Work order issued 2 - Work in progress.
No Image
967
(New)
190576-Construction of roads a) Kandak - Jehangir Malikdam Road Barikot, b) Rangilla Shamozai to Segawali, c) Talang-Churkhai, d) Najigram - Samsari, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 300 0 10 10 10 10 10 290 3% 3%
January - 2020
Financial Bids approval of contractors in processs.
No Image