Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, January - 2018, February - 2019, February - 2020, February - 2021, February - 2018, March - 2018, March - 2019, March - 2020, March - 2021, April - 2018, April - 2019, April - 2020, April - 2021, May - 2018, May - 2020, May - 2021, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
966
(OG)
150785-Construction of Road from Chodhwaan to Gataar to Jandi Babar to Maro Main Road (UC Chodhwaan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan.
D.I.Khan
HW
12-04-16 - - 10-09-15 - 199.624 8.9 25 21.375 15.125 15.125 24.025 165.724 17% 12%
December - 2017
Length 26 Km - Jandi Babar to Maroo - earth work, sub base, structure work completed. Revised PC-I/DCE for Rs.199.526 m approved. AA awaited. Summary for change of nomenclature submitted to CA.
No Image
966
(OG)
150785-Construction of Road from Chodhwaan to Gataar to Jandi Babar to Maro Main Road (UC Chodhwaan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.624 8.9 25 21.375 15.125 15.125 24.025 165.724 17% 12%
November - 2017
Length 26 Km - Jandi Babar to Maroo - earth work, sub base, structure work completed. Revised PC-I/DCE for Rs.199.526 m approved. AA awaited. Summary for Change of Nomenclature submitted to CA
No Image
966
(OG)
150785-Construction of Road from Chodhwaan to Gataar to Jandi Babar to Maro Main Road (UC Chodhwaan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.624 8.9 25 25 8.875 8.875 17.775 165.724 17% 9%
October - 2017
Length 26 Km - Jandi Babar to Maroo - earth work, sub base, structure work completed. Revised PC-I/DCE for Rs.199.526 m approved. AA awaited.
No Image
966
(OG)
150785-Construction of Road from Chodhwaan to Gataar to Jandi Babar to Maro Main Road (UC Chodhwaan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan.
D.I.Khan
HW
12-04-16 - - 10-09-15 - 199.624 8.9 25 25 8.875 8.875 17.775 165.724 17% 9%
September - 2017
Length 26 Km - Jandi Babar to Maroo - earth work, sub base, structure work completed. Revised PC-I/DCE for Rs.199.526 m approved, AA awaited.
No Image
966
(OG)
150785-Construction of Road from Chodhwaan to Gataar to Jandi Babar to Maro Main Road (UC Chodhwaan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan.
D.I.Khan
HW
12-04-16 - - 10-09-15 - 199.624 8.9 25 25 8.875 0 8.9 165.724 17% 4%
August - 2017
Length 26 Km - Jandi Babar to Maroo - earth work 65%, sub base 35%, structure work 20% completed. Revised PC-I/DCE for Rs.199.526 m To P&D
No Image
966
(OG)
150785-Construction of Road from Chodhwaan to Gataar to Jandi Babar to Maro Main Road (UC Chodhwaan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan.
D.I.Khan
HW
12-04-16 - - 10-09-15 - 199.624 8.9 25 25 8.875 0 8.9 165.724 17% 4%
July - 2017
Length 26 Km - Jandi Babar to Maroo - earth work 65%, sub base 35%, structure work 20% completed. Revised PC-I/DCE for Rs.199.526 m submitted to SOR on 25/05/2017.
No Image
966
(OG)
150785-Construction of Road from Choudwan to Gataar to Jandi Baber to Maro Main Road (UC Choudwan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan (i) Construction of Bridge on Valeri Nullah Choudwan Kot Tagga Road (265 rft).
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.526 8.9 25 25 25 21.968 30.868 165.626 17% 15%
June - 2018
Length 26 Km (width 12 ft) - Jandi Babar to Maroo - earth work, sub base, structure work completed. Revised scope - work order issued.
No Image
1) Choudwanto Gataar to Jhandi Babar to Maro Main road UC Choudwan 13 Km
2) Musa Zai Sharif to Kot Shah Nawaz to Garah Mir Alam to Gara Issa Khan UC Musa Zai Sharif 13 Km
3) Construction of Bridge on Waleri Nullah Choudwan Kot Tagga raod 265 rft) - additional work
966
(OG)
150785-Construction of Road from Choudwan to Gataar to Jandi Baber to Maro Main Road (UC Choudwan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan (i) Construction of Bridge on Valeri Nullah Choudwan Kot Tagga Road (265 rft).
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.526 8.9 25 30.467 30.467 21.968 30.868 165.626 17% 15%
May - 2018
Length 26 Km (width 12 ft) - Jandi Babar to Maroo - earth work, sub base, structure work completed. Revised scope - work order issued.
No Image
1) Choudwanto Gataar to Jhandi Babar to Maro Main road UC Choudwan 13 Km
2) Musa Zai Sharif to Kot Shah Nawaz to Garah Mir Alam to Gara Issa Khan UC Musa Zai Sharif 13 Km
3) Construction of Bridge on Waleri Nullah Choudwan Kot Tagga raod 265 rft) - additional work
966
(OG)
150785-Construction of Road from Choudwan to Gataar to Jandi Baber to Maro Main Road (UC Choudwan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan (i) Construction of Bridge on Valeri Nullah Choudwan Kot Tagga Road (265 rft).
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.526 8.9 25 30.467 30.467 21.968 30.868 165.626 17% 15%
April - 2018
Length 26 Km (width 12 ft) - Jandi Babar to Maroo - earth work, sub base, structure work completed. Revised scope - work order issued.
No Image
1) Choudwanto Gataar to Jhandi Babar to Maro Main road UC Choudwan 13 Km
2) Musa Zai Sharif to Kot Shah Nawaz to Garah Mir Alam to Gara Issa Khan UC Musa Zai Sharif 13 Km
3) Construction of Bridge on Waleri Nullah Choudwan Kot Tagga raod 265 rft) - additional work
966
(OG)
150785-Construction of Road from Choudwan to Gataar to Jandi Baber to Maro Main Road (UC Choudwan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan (i) Construction of Bridge on Valeri Nullah Choudwan Kot Tagga Road (265 rft).
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.526 8.9 25 30.467 30.467 21.968 30.868 165.626 17% 15%
March - 2018
Length 26 Km (width 12 ft) - Jandi Babar to Maroo - earth work, sub base, structure work completed. Revised scope - tender approval in progress.
No Image
1) Choudwanto Gataar to Jhandi Babar to Maro Main road UC Choudwan 13 Km
2) Musa Zai Sharif to Kot Shah Nawaz to Garah Mir Alam to Gara Issa Khan UC Musa Zai Sharif 13 Km
3) Construction of Bridge on Waleri Nullah Choudwan Kot Tagga raod 265 rft) - additional work
966
(OG)
150785-Construction of Road from Choudwan to Gataar to Jandi Baber to Maro Main Road (UC Choudwan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan (i) Construction of Bridge on Valeri Nullah Choudwan Kot Tagga Road (265 rft).
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.526 8.9 25 27.777 27.777 15.125 24.025 165.626 17% 12%
February - 2018
Length 26 Km (width 12 Ft ) - Jandi Babar to Maroo - earth work, sub base, structure work completed. Revised Scope - Tender approval in progress.
No Image
1) Choudwanto Gataar to Jhandi Babar to Maro Main road UC Choudwan 13 Km
2) Musa Zai Sharif to Kot Shah Nawaz to Garah Mir Alam to Gara Issa Khan UC Musa Zai Sharif 13 Km
3) Construction of Bridge on Waleri Nullah Choudwan Kot Tagga raod 265 rft) - additional work
966
(OG)
150785-Construction of Road from Chodhwaan to Gataar to Jandi Babar to Maro Main Road (UC Chodhwaan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 199.526 8.9 25 27.777 27.777 15.125 24.025 165.626 17% 12%
January - 2018
Length 26 Km - Jandi Babar to Maroo - earth work, sub base, structure work completed.
No Image
966
(OG)
170565-Construction of roads from (a) Dehgri to Moharr (1 Km), (b) Ghazi Kot - Chameri (1 Km), ? Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal (1 Km) (e) Saira to Daraband (1 Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 0 10 9.5 4.5005 3.008 3.008 61.292 14% 4%
December - 2018
Work started.
No Image
Mansehra
966
(OG)
170565-Construction of roads from (a) Dehgri to Moharr (1 Km), (b) Ghazi Kot - Chameri (1 Km), ? Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal (1 Km) (e) Saira to Daraband (1 Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 0 10 9.5 4.501 1.091 1.091 61.292 14% 2%
November - 2018
Work started.
No Image
Mansehra
966
(OG)
170565-Construction of roads from (a) Dehgri to Moharr (1 Km), (b) Ghazi Kot - Chameri (1 Km), ? Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal (1 Km) (e) Saira to Daraband (1 Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 0 10 9.5 4.501 1.091 1.091 61.292 14% 2%
November - 2018
Work started.
No Image
Mansehra
966
(OG)
170565-Construction of roads from (a) Dehgri to Moharr (1 Km), (b) Ghazi Kot - Chameri (1 Km), ? Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal (1 Km) (e) Saira to Daraband (1 Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 0 10 9.5 9.5005 9.5 9.5 61.292 14% 13%
April - 2019
Earth work completed. Structure work in progress.
No Image
Mansehra
966
(OG)
170565-Construction of roads from (a) Dehgri to Moharr (1 Km), (b) Ghazi Kot - Chameri (1 Km), ? Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal (1 Km) (e) Saira to Daraband (1 Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 0 10 9.5 7.0005 7.0005 7.0005 61.292 14% 10%
March - 2019
Earth work completed. Structure work in progress.
No Image
Mansehra
966
(OG)
170565-Construction of roads from (a) Dehgri to Moharr (1 Km), (b) Ghazi Kot - Chameri (1 Km), ? Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal (1 Km) (e) Saira to Daraband (1 Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 0 10 9.5 7.0005 7.0005 7.0005 61.292 14% 10%
March - 2019
Earth work completed. Structure work in progress.
No Image
Mansehra
966
(OG)
170565-Construction of roads from (a) Dehgri to Moharr (1 Km), (b) Ghazi Kot - Chameri (1 Km), ? Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal (1 Km) (e) Saira to Daraband (1 Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 0 10 9.5 7.0005 4.5005 4.5005 61.292 14% 6%
February - 2019
Earth work completed.
No Image
Mansehra
966
(OG)
170565-Construction of roads from (a) Dehgri to Moharr (1 Km), (b) Ghazi Kot - Chameri (1 Km), ? Phulra to Madserian UC Phulra (1 Km), (d) Ratta Depo to Chanyal (1 Km) (e) Saira to Daraband (1 Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 0 10 9.5 4.5005 3.008 3.008 61.292 14% 4%
January - 2019
Work started.
No Image
Mansehra
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 18.876 11.43 0 38.95 7 89% 60%
December - 2020
04- Units Work in progress.
No Image
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 18.876 11.43 0 38.95 7 89% 60%
December - 2020
04- Units Work in progress.
No Image
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 18.876 7 0 38.95 7 89% 60%
October - 2020
04- Units Work in progress.
No Image
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 18.876 7 0 38.95 7 89% 60%
September - 2020
04- Units Work in progress.
No Image
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 18.876 7 0 38.95 7 89% 60%
August - 2020
04- Units Work in progress.
No Image
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 11.43 11.43 0 38.95 7 89% 60%
May - 2021
04- Units 1. Finishing 2. Roofing 3. Finishing 4. Finishing
No Image
1 Student Hostel
2 Cat: III Residentail 01 No
3 Type IV Quarter 01
4 Type V Quarter 01
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 11.43 11.43 0 38.95 7 89% 60%
April - 2021
04- Units Work in progress.
No Image
1 Student Hostel
2 Cat: III Residentail 01 No
3 Type IV Quarter 01
4 Type V Quarter 01
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 11.43 11.43 0 38.95 7 89% 60%
March - 2021
04- Units Work in progress.
No Image
1 Student Hostel
2 Cat: III Residentail 01 No
3 Type IV Quarter 01
4 Type V Quarter 01
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 11.43 11.43 0 38.95 7 89% 60%
February - 2021
04- Units Work in progress.
No Image
1 Student Hostel
2 Cat: III Residentail 01 No
3 Type IV Quarter 01
4 Type V Quarter 01
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 11.43 11.43 0 38.95 7 89% 60%
January - 2021
04- Units Work in progress.
No Image
1 Student Hostel
2 Cat: III Residentail 01 No
3 Type IV Quarter 01
4 Type V Quarter 01
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Wazirstan
30-11--1 30-11--1 - 30-11--1 - 67.826 48.95 18.876 0 0 0 48.95 0
July - 2020
No Image
966
(New)
190574-FS and Design of road from Odigram to Guligram, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
December - 2019
PC-II approved for Rs.8 m. RFP submitted to DS Technical evauation of consultant in progress.
No Image
966
(New)
190574-FS and Design of road from Odigram to Guligram, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
November - 2019
PC-II approved for Rs.8 m. RFP submitted to DS Technical for approval.
No Image
966
(New)
190574-FS and Design of road from Odigram to Guligram, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
October - 2019
PC-II approved for Rs.8 m. RFP called on 28/11/2019.
No Image
966
(New)
190574-FS and Design of road from Odigram to Guligram, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
September - 2019
PC-II approved for Rs. 8 m.
No Image
966
(New)
190574-FS and Design of road from Odigram to Guligram, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
August - 2019
PC-II submitted to P&D. Pre PDWP held.
No Image
966
(New)
190574-FS and Design of road from Odigram to Guligram, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
May - 2020
PC-II approved for Rs.8 m. Survery for Studying Feasibility has been started.
No Image
966
(New)
190574-FS and Design of road from Odigram to Guligram, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
April - 2020
PC-II approved for Rs.8 m. Survery for Studying Feasibility has been started.
No Image
966
(New)
190574-FS and Design of road from Odigram to Guligram, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
March - 2020
PC-II approved for Rs.8 m. Survery for Studying Feasibility has been started.
No Image
966
(New)
190574-FS and Design of road from Odigram to Guligram, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
February - 2020
PC-II approved for Rs.8 m. Survery for Studying Feasibility has been started.
No Image
966
(New)
190574-FS and Design of road from Odigram to Guligram, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
January - 2020
PC-II approved for Rs.8 m. RFP submitted to DS Technical evauation of consultant in progress.
No Image
Pages : 1