Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
962 (OG) |
140987-F/S, Design and Construction of Main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi, DI.Khan. |
D.I.Khan HW |
21-04-16 | - | - | 28-01-15 | - | 210.57 | 54.9 | 60 | 51.3 | 51.3 | 51.3 | 106.2 | 95.67 | 55% |
50% December - 2017 |
Length 16 Km - earth work completed. Sub-base 8 Km completed. Revised PC-I/DCE for Rs.210.223 m approved. AA awaited. Summary for change of nomenclature submitted to CA. |
No Image |
PK-67 | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.57 | 54.9 | 60 | 51.3 | 51.3 | 21.3 | 76.2 | 95.67 | 55% |
36% November - 2017 |
Length 16 Km - earth work completed. Sub-base 8 Km completed. Revised PC-I/DCE for Rs.210.223 m approved. AA awaited. Summary for Change of Nomenclature submitted to CA. |
No Image |
PK-67 | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.57 | 54.9 | 60 | 60 | 36.3 | 21.3 | 76.2 | 95.67 | 55% |
36% October - 2017 |
Length 16 Km - earth work completed. Sub-base 8 Km completed. Revised PC-I/DCE for Rs.210.223 m approved. AA awaited. |
No Image |
PK-67 | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi, DI.Khan. |
D.I.Khan HW |
21-04-16 | - | - | 28-01-15 | - | 210.57 | 54.9 | 60 | 60 | 21.3 | 21.3 | 76.2 | 95.67 | 55% |
36% September - 2017 |
Length 16 Km - earth work completed. S/Base 8-Km completed. Revised PC-I/DCE for Rs.210.223 m approved, AA awaited. |
No Image |
PK-67 | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi, DI.Khan. |
D.I.Khan HW |
21-04-16 | - | - | 28-01-15 | - | 210.57 | 54.9 | 60 | 60 | 21.3 | 21.3 | 76.2 | 95.67 | 55% |
36% August - 2017 |
Length 16 Km - earth work in progress. Revised PC-I/DCE for Rs.210.223 m submitted to P&D. Pre-PDWP held. |
No Image |
PK-67 | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi, DI.Khan. |
D.I.Khan HW |
21-04-16 | - | - | 28-01-15 | - | 210.57 | 54.9 | 60 | 60 | 21.3 | 0 | 54.9 | 95.67 | 55% |
26% July - 2017 |
Length 16 Km - earth work in progress. Revised PC-I/DCE for Rs.210.223 m submitted to P&D. Pre-PDWP held. |
No Image |
PK-67 | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraban Road from Saggu to Maddi via Gara Unra Attal Sharif Road (16 Km) Kulachi, District DI.Khan. (i) Improvement and Black Top Road from Kirri Shamozai to Jhoke Rind PK-67 (1 Km) (ii) Construction of Bridge on Lora Nullah Daraban City PK-67. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.223 | 54.9 | 60 | 61.673 | 61.673 | 61.673 | 116.573 | 95.323 | 55% |
55% June - 2018 |
Length 16 Km (width-12ft) - earth work completed. Sub-base 8 Km completed.
Lora Bridge (length 120 ft, 4 span) - tender aproval in progress.
Additional road (1 Km) - work order issued. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraban Road from Saggu to Maddi via Gara Unra Attal Sharif Road (16 Km) Kulachi, District DI.Khan. (i) Improvement and Black Top Road from Kirri Shamozai to Jhoke Rind PK-67 (1 Km) (ii) Construction of Bridge on Lora Nullah Daraban City PK-67. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.223 | 54.9 | 60 | 61.673 | 61.673 | 61.673 | 116.573 | 95.323 | 55% |
55% May - 2018 |
Length 16 Km (width-12ft) - earth work completed. Sub-base 8 Km completed.
Lora Bridge (length 120 ft, 4 span) - tender aproval in progress.
Additional road (1 Km) - work order issued. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraban Road from Saggu to Maddi via Gara Unra Attal Sharif Road (16 Km) Kulachi, District DI.Khan. (i) Improvement and Black Top Road from Kirri Shamozai to Jhoke Rind PK-67 (1 Km) (ii) Construction of Bridge on Lora Nullah Daraban City PK-67. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.223 | 54.9 | 60 | 61.673 | 61.673 | 58.983 | 113.883 | 95.323 | 55% |
54% April - 2018 |
Length 16 Km (width-12ft) - earth work completed. Sub-base 8 Km completed.
Lora Bridge (length 120 ft, 4 span) - tender aproval in progress.
Additional road (1 Km) - work order issued. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraban Road from Saggu to Maddi via Gara Unra Attal Sharif Road (16 Km) Kulachi, District DI.Khan. (i) Improvement and Black Top Road from Kirri Shamozai to Jhoke Rind PK-67 (1 Km) (ii) Construction of Bridge on Lora Nullah Daraban City PK-67. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.223 | 54.9 | 60 | 61.673 | 61.673 | 58.983 | 113.883 | 95.323 | 55% |
54% March - 2018 |
Length 16 Km (width-12ft) - earth work completed. Sub-base 8 Km completed.
Lora Bridge (length 120 ft, 4 span) - tender aproval in progress.
Additional road (1 Km) - tender approval in progress. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraban Road from Saggu to Maddi via Gara Unra Attal Sharif Road (16 Km) Kulachi, District DI.Khan. (i) Improvement and Black Top Road from Kirri Shamozai to Jhoke Rind PK-67 (1 Km) (ii) Construction of Bridge on Lora Nullah Daraban City PK-67. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.223 | 54.9 | 60 | 88.893 | 88.983 | 51.306 | 106.206 | 95.323 | 55% |
51% February - 2018 |
Length 16 Km (width-12ft) - earth work completed. Sub-base 8 Km completed.
Lora Bridge (Length-120 ft , 4 span) ) - Tender aproval in progress.
Additional road ( 1 km ) - tender approval in progress. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
962 (OG) |
140987-F/S, Design and Construction of Main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.57 | 54.9 | 60 | 58.983 | 58.983 | 51.3 | 106.2 | 95.67 | 55% |
50% January - 2018 |
Length 16 Km - earth work completed. Sub-base 8 Km completed. Revised PC-I/DCE for Rs.210.223 m approved. AA awaited. Summary for change of nomenclature submitted to CA. |
No Image |
PK-67 | |||||||||||||||||||
962 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 20.8 | 10 | 9.5 | 4.5005 | 4.5 | 25.3 | 69.2 | 31% |
25% December - 2018 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
962 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 20.8 | 10 | 9.5 | 4.501 | 4.5 | 25.3 | 69.2 | 31% |
25% November - 2018 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
962 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 20.8 | 10 | 9.5 | 4.501 | 4.5 | 25.3 | 69.2 | 31% |
25% November - 2018 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
962 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 20.8 | 10 | 9.5 | 9.5005 | 9.5 | 30.3 | 69.2 | 31% |
30% April - 2019 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
962 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 20.8 | 10 | 9.5 | 7.0005 | 7 | 27.8 | 69.2 | 31% |
28% March - 2019 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
962 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 20.8 | 10 | 9.5 | 7.0005 | 7 | 27.8 | 69.2 | 31% |
28% March - 2019 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
962 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 20.8 | 10 | 9.5 | 7.0005 | 4.5 | 25.3 | 69.2 | 31% |
25% February - 2019 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
962 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 20.8 | 10 | 9.5 | 4.5005 | 4.5 | 25.3 | 69.2 | 31% |
25% January - 2019 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 100 | 0 | 0 | 14.35 | 0 | - |
- December - 2020 |
No Image | |
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 100 | 0 | 0 | 14.35 | 0 | - |
- December - 2020 |
No Image | |
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 100 | 0 | 0 | 14.35 | 0 | - |
- October - 2020 |
Master planand preparing of Dce under process. |
No Image |
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 100 | 0 | 0 | 14.35 | 0 | - |
- September - 2020 |
No Image | |
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 100 | 0 | 0 | 14.35 | 0 | - |
- August - 2020 |
No Image | |
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 0 | 0 | 0 | 14.35 | 0 |
July - 2020 |
No Image | ||
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 100 | 0 | 0 | 14.35 | 0 | - |
- May - 2021 |
No Image | |
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 100 | 0 | 0 | 14.35 | 0 | - |
- April - 2021 |
No Image | |
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 100 | 0 | 0 | 14.35 | 0 | - |
- March - 2021 |
No Image | |
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 100 | 0 | 0 | 14.35 | 0 | - |
- February - 2021 |
No Image | |
962 (OG) |
190237- Establishment & Feasibility Study of UET Swat |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7000 | 14.35 | 100 | 100 | 0 | 0 | 14.35 | 0 | - |
- January - 2021 |
No Image | |
962 (New) |
190459-Construction/ Rehabilitation/ Widening/ PCC/ BT of internal roads in Ucs Sakhra, Darmai, Ashray, Durushkhela, Baidara, Khairari, Chuprial, Barthana & adjoining\ areas of District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1521.724 | 0 | 125 | 125 | 125 | 0 | 0 | 1396.724 | 8% |
- December - 2019 |
Financial Bid approval of contractors under porocess. |
No Image |
962 (New) |
190459-Construction/ Rehabilitation/ Widening/ PCC/ BT of internal roads in Ucs Sakhra, Darmai, Ashray, Durushkhela, Baidara, Khairari, Chuprial, Barthana & adjoining\ areas of District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1521.724 | 0 | 125 | 125 | 0 | 0 | 0 | 1396.724 | 8% |
- November - 2019 |
Financial Bid opened on 6/12/2019 |
No Image |
962 (New) |
190459-Construction/ Rehabilitation/ Widening/ PCC/ BT of internal roads in Ucs Sakhra, Darmai, Ashray, Durushkhela, Baidara, Khairari, Chuprial, Barthana & adjoining\ areas of District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1521.724 | 0 | 125 | 125 | 0 | 0 | 0 | 1396.724 | 8% |
- October - 2019 |
Technical bid opening obn 21/11/2019 |
No Image |
962 (New) |
190459-Construction/ Rehabilitation/ Widening/ PCC/ BT of internal roads in Ucs Sakhra, Darmai, Ashray, Durushkhela, Baidara, Khairari, Chuprial, Barthana & adjoining\ areas of District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1521 | 0 | 125 | 125 | 0 | 0 | 0 | 1396 | 8% |
- September - 2019 |
Approved. Procuremnet in progress. |
No Image |
962 (New) |
190459-Construction/ Rehabilitation/ Widening/ PCC/ BT of internal roads in Ucs Sakhra, Darmai, Ashray, Durushkhela, Baidara, Khairari, Chuprial, Barthana & adjoining\ areas of District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 700 | 0 | 125 | 125 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
PC-I under preparation. Identification awaited from CA |
No Image |
962 (New) |
190459-Construction/ Rehabilitation/ Widening/ PCC/ BT of internal roads in Ucs Sakhra, Darmai, Ashray, Durushkhela, Baidara, Khairari, Chuprial, Barthana & adjoining\ areas of District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1521.724 | 0 | 201.8 | 201.8 | 201.8 | 201.8 | 201.8 | 1319.924 | 13% |
13% May - 2020 |
42 Packages Work in progress on all units. |
No Image |
962 (New) |
190459-Construction/ Rehabilitation/ Widening/ PCC/ BT of internal roads in Ucs Sakhra, Darmai, Ashray, Durushkhela, Baidara, Khairari, Chuprial, Barthana & adjoining\ areas of District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1521.724 | 0 | 125 | 125 | 125 | 71.035 | 71.035 | 1396.724 | 8% |
5% April - 2020 |
42 Packages Work in progress on all units. |
No Image |
962 (New) |
190459-Construction/ Rehabilitation/ Widening/ PCC/ BT of internal roads in Ucs Sakhra, Darmai, Ashray, Durushkhela, Baidara, Khairari, Chuprial, Barthana & adjoining\ areas of District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1521.724 | 0 | 125 | 125 | 125 | 71.035 | 71.035 | 1396.724 | 8% |
5% March - 2020 |
42 Packages Work in progress on all units. |
No Image |
962 (New) |
190459-Construction/ Rehabilitation/ Widening/ PCC/ BT of internal roads in Ucs Sakhra, Darmai, Ashray, Durushkhela, Baidara, Khairari, Chuprial, Barthana & adjoining\ areas of District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1521.724 | 0 | 125 | 125 | 125 | 71.035 | 71.035 | 1396.724 | 8% |
5% February - 2020 |
42 Packages Work in progress on all units. |
No Image |
962 (New) |
190459-Construction/ Rehabilitation/ Widening/ PCC/ BT of internal roads in Ucs Sakhra, Darmai, Ashray, Durushkhela, Baidara, Khairari, Chuprial, Barthana & adjoining\ areas of District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1521.724 | 0 | 125 | 125 | 125 | 19.249 | 19.249 | 1396.724 | 8% |
1% January - 2020 |
Financial Bid approval of contractors under porocess. |
No Image |
Pages : 1 |