Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
24-07-15 | 30-06-18 | - | 11-02-15 | - | 130 | 68.55 | 94.75 | 94.75 | 71.063 | 52.944 | 121.494 | 0 | 100% |
93% December - 2017 |
Length 13 Km - 13 Km road completed, 70% structure work completed. |
No Image |
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 68.55 | 94.75 | 94.75 | 71.063 | 52.944 | 121.494 | 0 | 100% |
93% November - 2017 |
Length 13 Km - 12 Km road completed. Remaining 1-Km WBM in progress. |
No Image |
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 68.55 | 94.75 | 94.75 | 47.375 | 42.495 | 111.045 | 0 | 100% |
85% October - 2017 |
Length 13 Km - 10 Km road completed. Remaining 3-Km WBM in progress. |
No Image |
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
24-07-15 | 30-06-18 | - | 11-02-15 | - | 130 | 68.55 | 94.75 | 94.75 | 47.375 | 22.136 | 90.686 | 0 | 100% |
70% September - 2017 |
Length 13 Km - 10 Km road completed. Remaining 3-Km WBM in progress. |
No Image |
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
24-07-15 | 30-06-18 | - | 11-02-15 | - | 130 | 68.55 | 94.75 | 94.75 | 47.375 | 22.136 | 90.686 | 0 | 100% |
70% August - 2017 |
Length 13 Km - 8 Km road completed. |
No Image |
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
24-07-15 | 30-06-18 | - | 11-02-15 | - | 130 | 68.55 | 94.75 | 94.75 | 33.636 | 0 | 68.55 | 0 | 100% |
53% July - 2017 |
Length 13 Km - 8 Km road completed. |
No Image |
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 68.55 | 94.75 | 53.83 | 53.83 | 53.283 | 121.833 | 0 | 100% |
94% June - 2018 |
Length 13 Km (width -12ft) - completed. |
No Image |
1) Multan road to Basti Gazar (Malana village) 0.8 Km
2) Balu Hazara link road (4 Km)
3) Rangpur Janubi to Adil Sapra Gharbi (5.4 Km)
4) Katcha Babar road to Katcha Hazara (1 Km)
5) Indus Highway to Distry-14 (Khana Sharif) 1.8 Km | |||||||||||||||||||
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 68.55 | 94.75 | 91.75 | 91.75 | 53.283 | 121.833 | 0 | 100% |
94% May - 2018 |
Length 13 Km (width -12ft) - completed. |
No Image |
1) Multan road to Basti Gazar (Malana village) 0.8 Km
2) Balu Hazara link road (4 Km)
3) Rangpur Janubi to Adil Sapra Gharbi (5.4 Km)
4) Katcha Babar road to Katcha Hazara (1 Km)
5) Indus Highway to Distry-14 (Khana Sharif) 1.8 Km | |||||||||||||||||||
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 68.55 | 94.75 | 91.75 | 91.75 | 53.283 | 121.833 | 0 | 100% |
94% April - 2018 |
Length 13 Km (width -12ft) - 13 Km road completed, 70% structure work completed. |
No Image |
1) Multan road to Basti Gazar (Malana village) 0.8 Km
2) Balu Hazara link road (4 Km)
3) Rangpur Janubi to Adil Sapra Gharbi (5.4 Km)
4) Katcha Babar road to Katcha Hazara (1 Km)
5) Indus Highway to Distry-14 (Khana Sharif) 1.8 Km | |||||||||||||||||||
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 68.55 | 94.75 | 94.75 | 68.063 | 53.283 | 121.833 | 0 | 100% |
94% March - 2018 |
Length 13 Km (width -12ft) - 13 Km road completed, 70% structure work completed. |
No Image |
1) Multan road to Basti Gazar (Malana village) 0.8 Km
2) Balu Hazara link road (4 Km)
3) Rangpur Janubi to Adil Sapra Gharbi (5.4 Km)
4) Katcha Babar road to Katcha Hazara (1 Km)
5) Indus Highway to Distry-14 (Khana Sharif) 1.8 Km | |||||||||||||||||||
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 68.55 | 94.75 | 94.75 | 68.063 | 53.283 | 121.833 | 0 | 100% |
94% February - 2018 |
Length 13 Km (width -12ft) - 13 Km road completed, 70% structure work completed. |
No Image |
1) Multan road to Basti Gazar (Malana village) 0.8 Km
2) Balu Hazara link road (4 Km)
3) Rangpur Janubi to Adil Sapra Gharbi (5.4 Km)
4) Katcha Babar road to Katcha Hazara (1 Km)
5) Indus Highway to Distry-14 (Khana Sharif) 1.8 Km | |||||||||||||||||||
961 (OG) |
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 68.55 | 94.75 | 94.75 | 71.063 | 53.283 | 121.833 | 0 | 100% |
94% January - 2018 |
Length 13 Km - 13 Km road completed, 70% structure work completed. |
No Image |
961 (OG) |
150842-Construction and Blacktopping of roads from (a) Darband to Kandgran (b) Sehkibala to Sokal UC Darra Shanaya District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35 | 23.95 | 7.25 | 7.069 | 5.257 | 1.771 | 25.721 | 3.8 | 89% |
73% December - 2018 |
Length - 3.6 Km (width 18 ft) 3 units - earth work 80% completed, structure work in progress. Court case. |
No Image |
1) Construction/BT of road Darband to Kandran UC Shanaya (2 Km) PK-57
2) Construction/BT of road Gali Badral to Labor UC Perhina (0.60 Km) PK-57
3) Construction/BT of road Lassan to Khamian UC Sawan Mera (1 Km) PK-57 | |||||||||||||||||||
961 (OG) |
150842-Construction and Blacktopping of roads from (a) Darband to Kandgran (b) Sehkibala to Sokal UC Darra Shanaya District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35 | 23.95 | 7.25 | 7.069 | 5.257 | 0.301 | 24.251 | 3.8 | 89% |
69% November - 2018 |
Length - 3.6 Km (width 18 ft) 3 units - earth work 80% completed, structure work in progress.
Court case. |
No Image |
1) Construction/BT of road Darband to Kandran UC Shanaya (2 Km) PK-57
2) Construction/BT of road Gali Badral to Labor UC Perhina (0.60 Km) PK-57
3) Construction/BT of road Lassan to Khamian UC Sawan Mera (1 Km) PK-57 | |||||||||||||||||||
961 (OG) |
150842-Construction and Blacktopping of roads from (a) Darband to Kandgran (b) Sehkibala to Sokal UC Darra Shanaya District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35 | 23.95 | 7.25 | 7.069 | 5.257 | 0.301 | 24.251 | 3.8 | 89% |
69% November - 2018 |
Length - 3.6 Km (width 18 ft) 3 units - earth work 80% completed, structure work in progress.
Court case. |
No Image |
1) Construction/BT of road Darband to Kandran UC Shanaya (2 Km) PK-57
2) Construction/BT of road Gali Badral to Labor UC Perhina (0.60 Km) PK-57
3) Construction/BT of road Lassan to Khamian UC Sawan Mera (1 Km) PK-57 | |||||||||||||||||||
961 (OG) |
150842-Construction and Blacktopping of roads from (a) Darband to Kandgran (b) Sehkibala to Sokal UC Darra Shanaya District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35 | 23.95 | 7.25 | 7.0687 | 7.0687 | 2.277 | 26.227 | 3.8 | 89% |
75% April - 2019 |
Length - 3.6 Km (width 18 ft) 3 units - earth work 80% completed, structure work in progress. Court case. |
No Image |
1) Construction/BT of road Darband to Kandran UC Shanaya (2 Km) PK-57
2) Construction/BT of road Gali Badral to Labor UC Perhina (0.60 Km) PK-57
3) Construction/BT of road Lassan to Khamian UC Sawan Mera (1 Km) PK-57 | |||||||||||||||||||
961 (OG) |
150842-Construction and Blacktopping of roads from (a) Darband to Kandgran (b) Sehkibala to Sokal UC Darra Shanaya District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35 | 23.95 | 7.25 | 7.0687 | 7.0687 | 2.277 | 26.227 | 3.8 | 89% |
75% March - 2019 |
Length - 3.6 Km (width 18 ft) 3 units - earth work 80% completed, structure work in progress. Court case. |
No Image |
1) Construction/BT of road Darband to Kandran UC Shanaya (2 Km) PK-57
2) Construction/BT of road Gali Badral to Labor UC Perhina (0.60 Km) PK-57
3) Construction/BT of road Lassan to Khamian UC Sawan Mera (1 Km) PK-57 | |||||||||||||||||||
961 (OG) |
150842-Construction and Blacktopping of roads from (a) Darband to Kandgran (b) Sehkibala to Sokal UC Darra Shanaya District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35 | 23.95 | 7.25 | 7.0687 | 7.0687 | 2.277 | 26.227 | 3.8 | 89% |
75% March - 2019 |
Length - 3.6 Km (width 18 ft) 3 units - earth work 80% completed, structure work in progress. Court case. |
No Image |
1) Construction/BT of road Darband to Kandran UC Shanaya (2 Km) PK-57
2) Construction/BT of road Gali Badral to Labor UC Perhina (0.60 Km) PK-57
3) Construction/BT of road Lassan to Khamian UC Sawan Mera (1 Km) PK-57 | |||||||||||||||||||
961 (OG) |
150842-Construction and Blacktopping of roads from (a) Darband to Kandgran (b) Sehkibala to Sokal UC Darra Shanaya District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35 | 23.95 | 7.25 | 7.0687 | 7.0687 | 2.277 | 26.227 | 3.8 | 89% |
75% February - 2019 |
Length - 3.6 Km (width 18 ft) 3 units - earth work 80% completed, structure work in progress. Court case. |
No Image |
1) Construction/BT of road Darband to Kandran UC Shanaya (2 Km) PK-57
2) Construction/BT of road Gali Badral to Labor UC Perhina (0.60 Km) PK-57
3) Construction/BT of road Lassan to Khamian UC Sawan Mera (1 Km) PK-57 | |||||||||||||||||||
961 (OG) |
150842-Construction and Blacktopping of roads from (a) Darband to Kandgran (b) Sehkibala to Sokal UC Darra Shanaya District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35 | 23.95 | 7.25 | 7.069 | 5.257 | 1.771 | 25.721 | 3.8 | 89% |
73% January - 2019 |
Length - 3.6 Km (width 18 ft) 3 units - earth work 80% completed, structure work in progress. Court case. |
No Image |
1) Construction/BT of road Darband to Kandran UC Shanaya (2 Km) PK-57
2) Construction/BT of road Gali Badral to Labor UC Perhina (0.60 Km) PK-57
3) Construction/BT of road Lassan to Khamian UC Sawan Mera (1 Km) PK-57 | |||||||||||||||||||
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
- December - 2020 |
No Image | |
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
- December - 2020 |
No Image | |
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
- October - 2020 |
No Image | |
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
- September - 2020 |
No Image | |
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
- August - 2020 |
No Image | |
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
July - 2020 |
No Image | |
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
- May - 2021 |
No Image | |
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
- April - 2021 |
No Image | |
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
- March - 2021 |
No Image | |
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
- February - 2021 |
No Image | |
961 (OG) |
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 119.28 | 56.75 | 0 | 0 | 0 | 0 | 56.75 | 0 | - |
- January - 2021 |
No Image | |
961 (New) |
170179-Construction of road from Kuza Bandai to New Cantt Swat (2.40 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 311.201 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
PC-1 for Rs.921.173 M submitted to P&D department Pre PDWP held. |
No Image |
PK-83, Swat | |||||||||||||||||||
961 (New) |
170179-Construction of road from Kuza Bandai to New Cantt Swat (2.40 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 311.201 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
PC-II approved for Rs8 m. LOA issued to Creative Consultants.
Survey in progress on new identifed alighnment. PC-I/Dce on the alignemnet finalized by Pak Army will be submitted in a week time |
No Image |
PK-83, Swat | |||||||||||||||||||
961 (New) |
170179-Construction of road from Kuza Bandai to New Cantt Swat (2.40 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 311.201 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
PC-II approved for Rs.3.997 m in DDWP on 18/07/2017. LOA issued to Creative Consultants.
Survey in progress on new identifed alighnment. PC-I/Dce on the alignemnet finalized by Pak Army will be submitted in a week time |
No Image |
PK-83, Swat | |||||||||||||||||||
961 (New) |
170179-Construction of road from Kuza Bandai to New Cantt Swat (2.40 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 311.201 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
PC-II approved for Rs.3.997 m in DDWP on 18/07/2017. LOA issued to Creative Consultants.
Survey in progress on new identifed alighnment. PC-I prepared for Rs.311 m. Meeting with District administration and Pak Army awaited. |
No Image |
PK-83, Swat | |||||||||||||||||||
961 (New) |
170179-Construction of road from Kuza Bandai to New Cantt Swat (2.40 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 311.201 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
PC-II approved for Rs.3.997 m in DDWP on 18/07/2017. LOA issued to Creative Consultants. PC-I/DCE under preparation. Survey in progress on new identifed alighnment. PC-I prepared for Rs.311 m. Meeting with District administration and Pak Army awaited. |
No Image |
PK-83, Swat | |||||||||||||||||||
961 (New) |
170179-Construction of road from Kuza Bandai to New Cantt Swat (2.40 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 311.201 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
PC-1 for Rs.921.173 M submitted to P&D department Pre PDWP held. |
No Image |
PK-83, Swat | |||||||||||||||||||
961 (New) |
170179-Construction of road from Kuza Bandai to New Cantt Swat (2.40 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 311.201 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
PC-1 for Rs.921.173 M submitted to P&D department Pre PDWP held. |
No Image |
PK-83, Swat | |||||||||||||||||||
961 (New) |
170179-Construction of road from Kuza Bandai to New Cantt Swat (2.40 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 311.201 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
PC-1 for Rs.921.173 M submitted to P&D department Pre PDWP held. |
No Image |
PK-83, Swat | |||||||||||||||||||
961 (New) |
170179-Construction of road from Kuza Bandai to New Cantt Swat (2.40 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 311.201 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
PC-1 for Rs.921.173 M submitted to P&D department Pre PDWP held. |
No Image |
PK-83, Swat | |||||||||||||||||||
961 (New) |
170179-Construction of road from Kuza Bandai to New Cantt Swat (2.40 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 311.201 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
PC-1 for Rs.921.173 M submitted to P&D department Pre PDWP held. |
No Image |
PK-83, Swat | |||||||||||||||||||
Pages : 1 |