Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
959 (New) |
190577-Construction / Widening /Rehabilitation / lacktopping / PCC of C&W roads in PK-20 District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 140 | 7% |
- December - 2019 |
Technical bids evaluation of contractors in progress. |
No Image |
959 (New) |
190577-Construction / Widening /Rehabilitation / lacktopping / PCC of C&W roads in PK-20 District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 140 | 7% |
- November - 2019 |
Technical bids evaluation in progress. |
No Image |
959 (New) |
190577-Construction / Widening /Rehabilitation / lacktopping / PCC of C&W roads in PK-20 District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
PC-I/DCE for Rs.150 m approved on 8/10/2019. AA Awaited |
No Image |
959 (New) |
190577-Construction / Widening /Rehabilitation / lacktopping / PCC of C&W roads in PK-20 District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
PC-I/DCE for Rs.150 m approved on 8/10/2019. AA Awaited |
No Image |
959 (New) |
190577-Construction / Widening /Rehabilitation / lacktopping / PCC of C&W roads in PK-20 District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
PC-I/DCE submitted to P&D to 06/09/2019. Cost Rs.150 m. |
No Image |
959 (New) |
190577-Construction / Widening /Rehabilitation / lacktopping / PCC of C&W roads in PK-20 District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 140 | 7% |
- May - 2020 |
Tender 2nd time called on 17/02/2020. |
No Image |
959 (New) |
190577-Construction / Widening /Rehabilitation / lacktopping / PCC of C&W roads in PK-20 District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 140 | 7% |
- April - 2020 |
Tender 2nd time called on 17/02/2020. |
No Image |
959 (New) |
190577-Construction / Widening /Rehabilitation / lacktopping / PCC of C&W roads in PK-20 District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 140 | 7% |
- March - 2020 |
Tender 2nd time called on 17/02/2020. |
No Image |
959 (New) |
190577-Construction / Widening /Rehabilitation / lacktopping / PCC of C&W roads in PK-20 District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 140 | 7% |
- February - 2020 |
Tender 2nd time called on 17/02/2020. |
No Image |
959 (New) |
190577-Construction / Widening /Rehabilitation / lacktopping / PCC of C&W roads in PK-20 District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 140 | 7% |
- January - 2020 |
Tender 2nd time called on 17/02/2020. |
No Image |
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
28-05-15 | 30-06-18 | - | 02-03-17 | - | 197.162 | 127.003 | 50.495 | 50.495 | 37.872 | 32.1 | 159.103 | 19.664 | 90% |
81% December - 2017 |
Phase-1 (9 Km) Original Scope - 9 Km completed.
Additional Scope - PCC shoulders - work order issued. |
No Image |
1) Circular road 5.73 Kms
2) Bannu road 1.60 Kms
3) Diyal road 2.05 Kms
4) Zaffar Abad raod 2.50 Kms
5) Multan road 2.25 Kms
6) Sheikh Yousaf road 2.70 Kms
7) Dinpur road 2 Kms
8) Circular raod to old Parova Chungi in front of Bahu Petroleum 0.17 Kms | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 127.003 | 50.495 | 50.495 | 37.872 | 20.158 | 147.161 | 19.664 | 90% |
75% November - 2017 |
Phase-1 (9 Km) Original Scope - 9 Km completed.
Additional Scope-PCC Shoulders - Work Order issued |
No Image |
1) Circular road 5.73 Kms
2) Bannu road 1.60 Kms
3) Diyal road 2.05 Kms
4) Zaffar Abad raod 2.50 Kms
5) Multan road 2.25 Kms
6) Sheikh Yousaf road 2.70 Kms
7) Dinpur road 2 Kms
8) Circular raod to old Parova Chungi in front of Bahu Petroleum 0.17 Kms | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 127.003 | 50.495 | 50.495 | 37.87 | 20.111 | 147.114 | 19.664 | 90% |
75% October - 2017 |
Phase-1 (9 Km) - 9 Km completed. Road marking, center media in progress. |
No Image |
1) Circular road 5.73 Kms
2) Bannu road 1.60 Kms
3) Diyal road 2.05 Kms
4) Zaffar Abad raod 2.50 Kms
5) Multan road 2.25 Kms
6) Sheikh Yousaf road 2.70 Kms
7) Dinpur road 2 Kms
8) Circular raod to old Parova Chungi in front of Bahu Petroleum 0.17 Kms | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
28-05-15 | 30-06-18 | - | 02-03-17 | - | 197.162 | 127.003 | 50.495 | 50.495 | 25.248 | 17.812 | 144.815 | 19.664 | 90% |
73% September - 2017 |
Phase-1 (9 Km) - 9 Km completed. Road marking, center media in progress. |
No Image |
1) Circular road 5.73 Kms
2) Bannu road 1.60 Kms
3) Diyal road 2.05 Kms
4) Zaffar Abad raod 2.50 Kms
5) Multan road 2.25 Kms
6) Sheikh Yousaf road 2.70 Kms
7) Dinpur road 2 Kms
8) Circular raod to old Parova Chungi in front of Bahu Petroleum 0.17 Kms | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
28-05-15 | 30-06-18 | - | 02-03-17 | - | 197.162 | 127.003 | 50.495 | 50.495 | 25.248 | 0 | 127.003 | 19.664 | 90% |
64% August - 2017 |
Phase-1 (9 Km) - 9 Km completed. |
No Image |
1) Circular road 5.73 Kms
2) Bannu road 1.60 Kms
3) Diyal road 2.05 Kms
4) Zaffar Abad raod 2.50 Kms
5) Multan road 2.25 Kms
6) Sheikh Yousaf road 2.70 Kms
7) Dinpur road 2 Kms
8) Circular raod to old Parova Chungi in front of Bahu Petroleum 0.17 Kms | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
28-05-15 | 30-06-18 | - | 02-03-17 | - | 197.162 | 127.003 | 50.495 | 50.495 | 17.926 | 0 | 127.003 | 19.664 | 90% |
64% July - 2017 |
Phase-1 (9 Km) - 8 Km completed. |
No Image |
1) Circular road 5.73 Kms
2) Bannu road 1.60 Kms
3) Diyal road 2.05 Kms
4) Zaffar Abad raod 2.50 Kms
5) Multan road 2.25 Kms
6) Sheikh Yousaf road 2.70 Kms
7) Dinpur road 2 Kms
8) Circular raod to old Parova Chungi in front of Bahu Petroleum 0.17 Kms | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 127.003 | 50.495 | 43.203 | 43.203 | 41.334 | 168.337 | 19.664 | 90% |
85% June - 2018 |
Phase-1 (9 Km) Original Scope - 9 Km completed.
Additional Scope - PCC shoulders - work in progress. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 127.003 | 50.495 | 52.203 | 52.203 | 40.124 | 167.127 | 19.664 | 90% |
85% May - 2018 |
Phase-1 (9 Km) Original Scope - 9 Km completed.
Additional Scope - PCC shoulders - work in progress. Funds to the tune of Rs.20 m required for completion. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 127.003 | 50.495 | 52.203 | 52.203 | 34.759 | 161.762 | 19.664 | 90% |
82% April - 2018 |
Phase-1 (9 Km) Original Scope - 9 Km completed.
Additional Scope - PCC shoulders - work in progress. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 127.003 | 50.495 | 52.203 | 52.203 | 34.759 | 161.762 | 19.664 | 90% |
82% March - 2018 |
Phase-1 (9 Km) Original Scope - 9 Km completed.
Additional Scope - PCC shoulders - work started. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 127.003 | 50.495 | 52.203 | 52.203 | 33.732 | 160.735 | 19.664 | 90% |
82% February - 2018 |
Phase-1 (9 Km) Original Scope - 9 Km completed.
Additional Scope - PCC shoulders - work started. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
959 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 127.003 | 50.495 | 52.203 | 52.203 | 33.368 | 160.371 | 19.664 | 90% |
81% January - 2018 |
Phase-1 (9 Km) Original Scope - 9 Km completed.
Additional Scope - PCC shoulders - work started. |
No Image |
1) Circular road 5.73 Kms 2) Bannu road 1.60 Kms 3) Diyal road 2.05 Kms 4) Zaffar Abad raod 2.50 Kms 5) Multan road 2.25 Kms 6) Sheikh Yousaf road 2.70 Kms 7) Dinpur road 2 Kms 8) Circular raod to old Parova Chungi in front of Bahu Petroleum 0.17 Kms | |||||||||||||||||||
959 (OG) |
140676-F/S, Design and Construction of Sum Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89 | 67.355 | 14.85 | 14.85 | 14.85 | 14.346 | 81.701 | 6.795 | 92% |
92% December - 2018 |
Bridge 62.35 mtr - Physically complete. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
959 (OG) |
140676-F/S, Design and Construction of Sum Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89 | 67.355 | 14.85 | 14.85 | 14.85 | 14.346 | 81.701 | 6.795 | 92% |
92% November - 2018 |
Bridge 62.35 mtr - Physically complete. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
959 (OG) |
140676-F/S, Design and Construction of Sum Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89 | 67.355 | 14.85 | 14.85 | 14.85 | 14.346 | 81.701 | 6.795 | 92% |
92% November - 2018 |
Bridge 62.35 mtr - Physically complete. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
959 (OG) |
140676-F/S, Design and Construction of Sum Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89 | 67.355 | 14.85 | 14.85 | 14.85 | 14.85 | 82.205 | 6.795 | 92% |
92% April - 2019 |
Bridge 62.35 mtr - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
959 (OG) |
140676-F/S, Design and Construction of Sum Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89 | 67.355 | 14.85 | 14.85 | 14.85 | 14.85 | 82.205 | 6.795 | 92% |
92% March - 2019 |
Bridge 62.35 mtr - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
959 (OG) |
140676-F/S, Design and Construction of Sum Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89 | 67.355 | 14.85 | 14.85 | 14.85 | 14.85 | 82.205 | 6.795 | 92% |
92% March - 2019 |
Bridge 62.35 mtr - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
959 (OG) |
140676-F/S, Design and Construction of Sum Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89 | 67.355 | 14.85 | 14.85 | 14.85 | 14.346 | 81.701 | 6.795 | 92% |
92% February - 2019 |
Bridge 62.35 mtr - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
959 (OG) |
140676-F/S, Design and Construction of Sum Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89 | 67.355 | 14.85 | 14.85 | 14.85 | 14.346 | 81.701 | 6.795 | 92% |
92% January - 2019 |
Bridge 62.35 mtr - Physically complete. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
- December - 2020 |
No Image | |
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
- December - 2020 |
No Image | |
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
- October - 2020 |
No Image | |
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
- September - 2020 |
No Image | |
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
- August - 2020 |
No Image | |
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
July - 2020 |
No Image | |
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
- May - 2021 |
No Image | |
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
- April - 2021 |
No Image | |
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
- March - 2021 |
No Image | |
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
- February - 2021 |
No Image | |
959 (OG) |
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 18 | 0 | 0 | 0 | 0 | 18 | 0 | - |
- January - 2021 |
No Image | |