Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
July - 2020 |
No Image | |
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
- December - 2020 |
No Image | |
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
- December - 2020 |
No Image | |
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
- October - 2020 |
No Image | |
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
- September - 2020 |
No Image | |
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
- August - 2020 |
No Image | |
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
- May - 2021 |
No Image | |
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
- April - 2021 |
No Image | |
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
- March - 2021 |
No Image | |
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
- February - 2021 |
No Image | |
957 (OG) |
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 402.02 | 302.091 | 0 | 0 | 0 | 0 | 302.091 | 0 | - |
- January - 2021 |
No Image | |
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
12-05-15 | 30-06-18 | - | 24-01-14 | - | 59 | 42.25 | 2.88 | 2.88 | 2.16 | 2.16 | 44.41 | 13.87 | 76% |
75% December - 2017 |
2 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur), Liability of Contractor Rs.14.491 m. Summary submitted to CA. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59 | 42.25 | 2.88 | 2.88 | 2.16 | 2.16 | 44.41 | 13.87 | 76% |
75% November - 2017 |
2 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur), Liability of Contractor Rs.14.491 m. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59 | 42.25 | 2.88 | 2.88 | 2.16 | 2.16 | 44.41 | 13.87 | 76% |
75% October - 2017 |
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur), 1 90% completed (U/S Right Guide Bund). |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
12-05-15 | 30-06-18 | - | 24-01-14 | - | 59 | 42.25 | 2.88 | 2.88 | 1.44 | 1.44 | 43.69 | 13.87 | 76% |
74% September - 2017 |
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur), 1 90% completed (U/S Right Guide Bund). |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
12-05-15 | 30-06-18 | - | 24-01-14 | - | 59 | 42.25 | 2.88 | 2.88 | 1.44 | 0 | 42.25 | 13.87 | 76% |
72% August - 2017 |
3 units - 2 completed, 1 90% completed. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
12-05-15 | 30-06-18 | - | 24-01-14 | - | 59 | 42.25 | 2.88 | 2.88 | 1.022 | 0 | 42.25 | 13.87 | 76% |
72% July - 2017 |
3 units - 2 completed, 1 90% completed. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 42.25 | 2.88 | 2.88 | 2.88 | 2.16 | 44.41 | 77.051 | 37% |
36% June - 2018 |
2 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Revised scope - tender approval under process (left guide spur removed form scope). |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 42.25 | 2.88 | 2.88 | 2.88 | 2.16 | 44.41 | 77.051 | 37% |
36% May - 2018 |
2 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Revised scope - tender approval under process (left guide spur removed form scope). Rs.77.151 m demanded for completion. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 42.25 | 2.88 | 2.88 | 2.88 | 2.16 | 44.41 | 77.051 | 37% |
36% April - 2018 |
2 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Revised scope - tender approval under process (left guide spur removed form scope). Rs.77.151 m demanded for completion. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 42.25 | 2.88 | 2.88 | 2.88 | 2.16 | 44.41 | 77.051 | 37% |
36% March - 2018 |
2 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Revised scope - tender approval under process (left guide spur removed form scope). |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 42.25 | 2.88 | 2.88 | 2.16 | 2.16 | 44.41 | 77.051 | 37% |
36% February - 2018 |
2 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Revised scope - tender approval under process. ( left Guide Spur Removed form Scope ) |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
957 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.281 | 42.25 | 2.88 | 2.88 | 2.16 | 2.16 | 44.41 | 77.151 | 37% |
36% January - 2018 |
2 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Revised Scope- tendering in progress. |
No Image |
1) Main Righ Spur 2) Additional Spur 3) Right Guide Bund Upstream 4) Left Guide Bund Upstream | |||||||||||||||||||
957 (New) |
190571-Construction of internal road in different Ucs PK-18, Agra, Pirkhel,Totakan, Dheri Jolagram,Malakand Khass,Khar,Batkhela Upper, Batkela Lower,Batkhela Middle,Aladand,Dheri,Thana Bandjai,Thana Khass,Thana Jadeed & Palai District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- December - 2019 |
Approved. A.A issued. |
No Image |
957 (New) |
190571-Construction of internal road in different Ucs PK-18, Agra, Pirkhel,Totakan, Dheri Jolagram,Malakand Khass,Khar,Batkhela Upper, Batkela Lower,Batkhela Middle,Aladand,Dheri,Thana Bandjai,Thana Khass,Thana Jadeed & Palai District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
PC-I/DCE submitted P&D. Pre PDWP held. |
No Image |
957 (New) |
190571-Construction of internal road in different Ucs PK-18, Agra, Pirkhel,Totakan, Dheri Jolagram,Malakand Khass,Khar,Batkhela Upper, Batkela Lower,Batkhela Middle,Aladand,Dheri,Thana Bandjai,Thana Khass,Thana Jadeed & Palai District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
PC-I/DCE submitted to CE on 13/11/2019 on MRS 2019 |
No Image |
957 (New) |
190571-Construction of internal road in different Ucs PK-18, Agra, Pirkhel,Totakan, Dheri Jolagram,Malakand Khass,Khar,Batkhela Upper, Batkela Lower,Batkhela Middle,Aladand,Dheri,Thana Bandjai,Thana Khass,Thana Jadeed & Palai District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
DCE under preparation will be submitted within a week time. |
No Image |
957 (New) |
190571-Construction of internal road in different Ucs PK-18, Agra, Pirkhel,Totakan, Dheri Jolagram,Malakand Khass,Khar,Batkhela Upper, Batkela Lower,Batkhela Middle,Aladand,Dheri,Thana Bandjai,Thana Khass,Thana Jadeed & Palai District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
DCE under preparation will be submitted within a week time |
No Image |
957 (New) |
190571-Construction of internal road in different Ucs PK-18, Agra, Pirkhel,Totakan, Dheri Jolagram,Malakand Khass,Khar,Batkhela Upper, Batkela Lower,Batkhela Middle,Aladand,Dheri,Thana Bandjai,Thana Khass,Thana Jadeed & Palai District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- May - 2020 |
Procuremnet in Progress. |
No Image |
957 (New) |
190571-Construction of internal road in different Ucs PK-18, Agra, Pirkhel,Totakan, Dheri Jolagram,Malakand Khass,Khar,Batkhela Upper, Batkela Lower,Batkhela Middle,Aladand,Dheri,Thana Bandjai,Thana Khass,Thana Jadeed & Palai District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- April - 2020 |
Procuremnet in Progress. |
No Image |
957 (New) |
190571-Construction of internal road in different Ucs PK-18, Agra, Pirkhel,Totakan, Dheri Jolagram,Malakand Khass,Khar,Batkhela Upper, Batkela Lower,Batkhela Middle,Aladand,Dheri,Thana Bandjai,Thana Khass,Thana Jadeed & Palai District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- March - 2020 |
Procuremnet in Progress. |
No Image |
957 (New) |
190571-Construction of internal road in different Ucs PK-18, Agra, Pirkhel,Totakan, Dheri Jolagram,Malakand Khass,Khar,Batkhela Upper, Batkela Lower,Batkhela Middle,Aladand,Dheri,Thana Bandjai,Thana Khass,Thana Jadeed & Palai District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- February - 2020 |
Procuremnet in Progress. |
No Image |
957 (New) |
190571-Construction of internal road in different Ucs PK-18, Agra, Pirkhel,Totakan, Dheri Jolagram,Malakand Khass,Khar,Batkhela Upper, Batkela Lower,Batkhela Middle,Aladand,Dheri,Thana Bandjai,Thana Khass,Thana Jadeed & Palai District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 190 | 5% |
- January - 2020 |
Procuremnet in Progress. |
No Image |
957 (OG) |
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 39.6 | 17 | 17 | 17 | 12.065 | 51.665 | 0 | 100% |
100% December - 2018 |
Length 4.8 Km - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
957 (OG) |
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 39.6 | 17 | 17 | 17 | 12.065 | 51.665 | 0 | 100% |
100% November - 2018 |
Length 4.8 Km - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
957 (OG) |
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 39.6 | 17 | 17 | 17 | 12.065 | 51.665 | 0 | 100% |
100% November - 2018 |
Length 4.8 Km - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
957 (OG) |
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 39.6 | 17 | 17 | 17 | 17 | 56.6 | 0 | 100% |
100% April - 2019 |
Length 4.8 Km - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
957 (OG) |
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 39.6 | 17 | 17 | 17 | 12.065 | 51.665 | 0 | 100% |
100% March - 2019 |
Length 4.8 Km - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
957 (OG) |
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 39.6 | 17 | 17 | 17 | 12.065 | 51.665 | 0 | 100% |
100% March - 2019 |
Length 4.8 Km - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
957 (OG) |
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 39.6 | 17 | 17 | 17 | 12.065 | 51.665 | 0 | 100% |
100% February - 2019 |
Length 4.8 Km - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
957 (OG) |
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 39.6 | 17 | 17 | 17 | 12.065 | 51.665 | 0 | 100% |
100% January - 2019 |
Length 4.8 Km - Physically completed. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
Pages : 1 |