Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
- | - | - | - | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
Site/scope of work not identified. |
No Image |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
- | - | - | - | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
No Image | |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
- | - | - | - | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
No Image | |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
- | - | - | - | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
No Image | |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
No Image | |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
No Image | |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 5 | 1.2 | 1.2 | 0 | 0 | 0 | - |
- June - 2018 |
Tender called on 04/05/2018. Technical evaluation under process. |
No Image |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
Tender called on 04/05/2018. Technical evaluation under process. |
No Image |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
Tender called on 04/05/2018. |
No Image |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
Site/scope of work not identified. |
No Image |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
Site/scope of work not identified. |
No Image |
947 (New) |
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
Site/scope of work not identified. |
No Image |
947 (OG) |
130420-Construction of Pre-stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 197.71 | 30 | 23.5 | 8.5 | 0 | 197.71 | 94.824 | 71% |
61% December - 2018 |
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
947 (OG) |
130420-Construction of Pre-stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 197.71 | 30 | 23.5 | 8.5 | 0 | 197.71 | 94.824 | 71% |
61% November - 2018 |
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
947 (OG) |
130420-Construction of Pre-stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 197.71 | 30 | 23.5 | 8.5 | 0 | 197.71 | 94.824 | 71% |
61% November - 2018 |
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
947 (OG) |
130420-Construction of Pre-stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 197.71 | 30 | 23.5 | 23.5 | 1.652 | 199.362 | 94.824 | 71% |
62% April - 2019 |
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
947 (OG) |
130420-Construction of Pre-stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 197.71 | 30 | 23.5 | 8.5 | 0 | 197.71 | 94.824 | 71% |
61% March - 2019 |
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
947 (OG) |
130420-Construction of Pre-stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 197.71 | 30 | 23.5 | 8.5 | 0 | 197.71 | 94.824 | 71% |
61% March - 2019 |
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
947 (OG) |
130420-Construction of Pre-stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 197.71 | 30 | 23.5 | 8.5 | 0 | 197.71 | 94.824 | 71% |
61% February - 2019 |
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
947 (OG) |
130420-Construction of Pre-stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 197.71 | 30 | 23.5 | 8.5 | 0 | 197.71 | 94.824 | 71% |
61% January - 2019 |
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
947 (New) |
190475-Construction /Rehabilitaiton of roads/Construction of Bridges/Dualization at Ucs Alo, Kharki, Dheri, Qasmi, Shamozia, Mian Essa, Kati Garhi, Babozai VC Shah Bathkhela VC Dewan Khel District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 17.14 | 17.14 | 0 | 0 | 0 | 182.86 | 9% |
- December - 2019 |
Tender approval under process. |
No Image |
947 (New) |
190475-Construction /Rehabilitaiton of roads/Construction of Bridges/Dualization at Ucs Alo, Kharki, Dheri, Qasmi, Shamozia, Mian Essa, Kati Garhi, Babozai VC Shah Bathkhela VC Dewan Khel District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 17.14 | 17.14 | 0 | 0 | 0 | 182.86 | 9% |
- November - 2019 |
Financial bid called in jan 2019 |
No Image |
947 (New) |
190475-Construction /Rehabilitaiton of roads/Construction of Bridges/Dualization at Ucs Alo, Kharki, Dheri, Qasmi, Shamozia, Mian Essa, Kati Garhi, Babozai VC Shah Bathkhela VC Dewan Khel District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 17.14 | 17.14 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
Tender Called on 20/11/19 |
No Image |
947 (New) |
190475-Construction /Rehabilitaiton of roads/Construction of Bridges/Dualization at Ucs Alo, Kharki, Dheri, Qasmi, Shamozia, Mian Essa, Kati Garhi, Babozai VC Shah Bathkhela VC Dewan Khel District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 17.14 | 17.14 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
PC-I/DCE for Rs.200 m approved on 8/10/2019. AA Awaited |
No Image |
947 (New) |
190475-Construction /Rehabilitaiton of roads/Construction of Bridges/Dualization at Ucs Alo, Kharki, Dheri, Qasmi, Shamozia, Mian Essa, Kati Garhi, Babozai VC Shah Bathkhela VC Dewan Khel District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 17.14 | 17.14 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
PC-I/DCE for Rs.200 m submitted to P&D on 18/09/2019. |
No Image |
947 (New) |
190475-Construction /Rehabilitaiton of roads/Construction of Bridges/Dualization at Ucs Alo, Kharki, Dheri, Qasmi, Shamozia, Mian Essa, Kati Garhi, Babozai VC Shah Bathkhela VC Dewan Khel District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 17.14 | 17.14 | 0 | 0 | 0 | 182.86 | 9% |
- May - 2020 |
Work started. |
No Image |
947 (New) |
190475-Construction /Rehabilitaiton of roads/Construction of Bridges/Dualization at Ucs Alo, Kharki, Dheri, Qasmi, Shamozia, Mian Essa, Kati Garhi, Babozai VC Shah Bathkhela VC Dewan Khel District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 17.14 | 17.14 | 0 | 0 | 0 | 182.86 | 9% |
- April - 2020 |
Work started. |
No Image |
947 (New) |
190475-Construction /Rehabilitaiton of roads/Construction of Bridges/Dualization at Ucs Alo, Kharki, Dheri, Qasmi, Shamozia, Mian Essa, Kati Garhi, Babozai VC Shah Bathkhela VC Dewan Khel District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 17.14 | 17.14 | 0 | 0 | 0 | 182.86 | 9% |
- March - 2020 |
Work started. |
No Image |
947 (New) |
190475-Construction /Rehabilitaiton of roads/Construction of Bridges/Dualization at Ucs Alo, Kharki, Dheri, Qasmi, Shamozia, Mian Essa, Kati Garhi, Babozai VC Shah Bathkhela VC Dewan Khel District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 17.14 | 17.14 | 0 | 0 | 0 | 182.86 | 9% |
- February - 2020 |
Work started. |
No Image |
947 (New) |
190475-Construction /Rehabilitaiton of roads/Construction of Bridges/Dualization at Ucs Alo, Kharki, Dheri, Qasmi, Shamozia, Mian Essa, Kati Garhi, Babozai VC Shah Bathkhela VC Dewan Khel District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 17.14 | 17.14 | 0 | 0 | 0 | 182.86 | 9% |
- January - 2020 |
Work order issued. |
No Image |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
- December - 2020 |
No Image | |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
- December - 2020 |
No Image | |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
- October - 2020 |
No Image | |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
- September - 2020 |
No Image | |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
- August - 2020 |
No Image | |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
July - 2020 |
No Image | |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
- May - 2021 |
No Image | |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
- April - 2021 |
No Image | |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
- March - 2021 |
No Image | |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
- February - 2021 |
No Image | |
947 (OG) |
130548-Establishment of Women University Campus in Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500.758 | 1215 | 0 | 0 | 0 | 0 | 1215 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |