Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, February - 2019, February - 2020, February - 2021, March - 2019, March - 2020, March - 2021, April - 2019, April - 2020, April - 2021, May - 2020, May - 2021, July - 2018, July - 2020, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2018, November - 2019, December - 2018, December - 2019, December - 2020,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 36.386 24 0 0 0 0 24 12.386 - 66%
September - 2018
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - Work started
No Image
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level)
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 36.386 24 0 0 0 0 24 12.386 - 66%
July - 2018
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - revised on new site work started.
No Image
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level)
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 82.286 30 0 0 0 0 30 52.286 - 36%
September - 2018
Completed & H/O (Domel & lalozai ) site dispute (Baka Khel ).
No Image
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 82.286 30 0 0 0 0 30 52.286 - 36%
July - 2018
Completed & H/O (Domel). Pavilian - roof laid, BW in progress, site dispute (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
30-11--1 30-11--1 - 30-11--1 - 30 15 0 0 0 0 15 15 - 50%
September - 2018
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
30-11--1 30-11--1 - 30-11--1 - 30 15 0 0 0 0 15 15 - 50%
July - 2018
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
30-11--1 30-11--1 - 30-11--1 - 59.264 14.312 0 0 0 0 14.312 44.952 - 24%
September - 2018
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
30-11--1 30-11--1 - 30-11--1 - 59.264 14.312 0 0 0 0 14.312 44.952 - 24%
July - 2018
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
December - 2020
No Image
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
December - 2020
No Image
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
October - 2020
No Image
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 45 43.05 0 0 0 0 43.05 1.95 - 96%
September - 2018
Completed & H/O (4 units).
No Image
1) PG at Tangi
2) PG at Attakay Shabqadar
3) PG at GCMHS Turangzai
4) PG at GHS Muslim Abad Shakoor
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
September - 2020
No Image
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
August - 2020
No Image
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 45 43.05 0 0 0 0 43.05 1.95 - 96%
July - 2018
Completed & H/O (4 units).
No Image
1) PG at Tangi
2) PG at Attakay Shabqadar
3) PG at GCMHS Turangzai
4) PG at GHS Muslim Abad Shakoor
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 -
July - 2020
No Image
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
May - 2021
No Image
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
April - 2021
No Image
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
March - 2021
No Image
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
February - 2021
No Image
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
January - 2021
No Image
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Chitral
30-11--1 30-11--1 - 30-11--1 - 31.211 30 0 0 0 0 30 1.211 - 96%
September - 2018
PG Gahli Booni - completed. PG Chitral - finishing in progress.
No Image
1) PG Gahli Booni
2) PG Syed Abad Chitral
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Chitral
30-11--1 30-11--1 - 30-11--1 - 31.211 30 0 0 0 0 30 1.211 - 96%
July - 2018
PG Gahli Booni - completed. PG Chitral - finishing in progress.
No Image
1) PG Gahli Booni
2) PG Syed Abad Chitral
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 93.69 65.739 5 5 5 5 70.739 22.951 76% 76%
September - 2018
Out of 7 units, Kulachi, Daraban and Paroa - completed & H/O. GMS Mali Khel and GGHS Islamia completed. Paharpur and GMS Darban - stay order by PHC, work stopped.
No Image
1) Kulachi PK-67
2) Daraban PK-67
3) Paroa PK-66
4) Paharpur PK-68
5) GHSS No.2 Islamia DI.Khan PK-64
6) GGHS Kacha Mali Khel Paharpur PK-64
7) GMS No.1 Daraban Kalan PK-67 shifted to GHS Takwara
8) Tehsil level PG at Panyala Tehsil Paharpur
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 93.69 65.739 0 0 0 0 65.739 27.951 - 70%
July - 2018
Out of 7 units, Kulachi, Daraban and Paroa - completed & H/O. GMS Mali Khel and GGHS Islamia completed. Paharpur and GMS Darban - stay order by PHC, work stopped.
No Image
1) Kulachi PK-67
2) Daraban PK-67
3) Paroa PK-66
4) Paharpur PK-68
5) GHSS No.2 Islamia DI.Khan PK-64
6) GGHS Kacha Mali Khel Paharpur PK-64
7) GMS No.1 Daraban Kalan PK-67 shifted to GHS Takwara
8) Tehsil level PG at Panyala Tehsil Paharpur
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 87.9048 55.983 0 0 0 0 55.983 31.922 - 64%
September - 2018
Completed & H/O (2 PG Lal Qilla and Samer Bagh). PG Balambat - physically completed. Land for approach not yet acquired. PG at Warsak and Sado - completed. PG at Munda - roof laid, finishing in progress.
No Image
1) Samar Bagh
2) Lal Qilla PK-96
3) Balambat
4) PG at Warsak Tehsil Adenzai
5) PG at Munda PK-95
6) PG at GHSS Sado Timergara
7) PG Khall
8) Construction of BW at GHS at Rehanpur PK-96 (school level PG) 9) Construction of BW at GHSS at Bagh Maidan PK-96 (school level PG) 10) Construction of BW at GHS at Lal Qilla Maidan PK-96 (school level PG)
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 87.9048 55.983 0 0 0 0 55.983 31.922 - 64%
July - 2018
Completed & H/O (2 PG Lal Qilla and Samer Bagh). PG Balambat - physically completed. Land for approach not yet acquired. PG at Warsak and Sado - completed. PG at Munda - roof laid, finishing in progress.
No Image
1) Samar Bagh
2) Lal Qilla PK-96
3) Balambat
4) PG at Warsak Tehsil Adenzai
5) PG at Munda PK-95
6) PG at GHSS Sado Timergara
7) PG Khall
8) Construction of BW at GHS at Rehanpur PK-96 (school level PG) 9) Construction of BW at GHSS at Bagh Maidan PK-96 (school level PG) 10) Construction of BW at GHS at Lal Qilla Maidan PK-96 (school level PG)
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 36.152 0 0 0 0 0 0 36.152 - -
September - 2018
S# 1: Site disputed. S# 2 & 3: work order issued.
No Image
1) PG Wari PK-93
2) PG at Barawal Bandai PK-91
3) PG at Dir
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 36.152 0 0 0 0 0 0 36.152 - -
July - 2018
S# 1: Site disputed. S# 2 & 3: work order issued.
No Image
1) PG Wari PK-93
2) PG at Barawal Bandai PK-91
3) PG at Dir
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Hangu
30-11--1 30-11--1 - 30-11--1 - 45 15.064 0 0 0 0 15.064 29.936 - 33%
September - 2018
Thall - pavilion, BW in progress. GMS Togh Serai PG completed. GMS Anar Cheena site disputed, court stay. Hangu PG - Completed.
No Image
1) Thall
2) Hangu
3) GHS Togh Sarai PK-42
4) GMS Anar China PK-42
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Hangu
30-11--1 30-11--1 - 30-11--1 - 45 15.064 0 0 0 0 15.064 29.936 - 33%
July - 2018
4 PG Hangu - completed & H/O. Thall - pavilion, BW in progress. GMS Togh Serai PG completed. GMS Anar Cheena site disputed, court stay.
No Image
1) Thall
2) Hangu
3) GHS Togh Sarai PK-42
4) GMS Anar China PK-42
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Haripur
30-11--1 30-11--1 - 30-11--1 - 30 32.77 0 0 0 0 32.77 0 - 100%
September - 2018
Completed & H/O (Ghazi & Haripur).
No Image
1) PG Ghazi
2) PG Sarai Saleh Haripur
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Haripur
30-11--1 30-11--1 - 30-11--1 - 30 32.77 0 0 0 0 32.77 0 - 100%
July - 2018
Completed & H/O (Ghazi & Haripur).
No Image
1) PG Ghazi
2) PG Sarai Saleh Haripur
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Karak
30-11--1 30-11--1 - 30-11--1 - 61.583 51.312 0 0 0 0 51.312 10.271 - 83%
September - 2018
4 PG - BD Shah, Takhat Nusrati, Karak completed, GHSS GHS Gurguri - tender opening on 19/9/2018.
No Image
1) Banda Daud Shah
2) Takhti Nasrati
3) Karak
4) GHSS Jahangari PK-41 shifted to GHS Gurguri
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Karak
30-11--1 30-11--1 - 30-11--1 - 61.583 51.312 0 0 0 0 51.312 10.271 - 83%
July - 2018
4 PG - BD Shah, Takhat Nusrati, Karak completed, GHSS GHS Gurguri - work order issued but site not available.
No Image
1) Banda Daud Shah
2) Takhti Nasrati
3) Karak
4) GHSS Jahangari PK-41 shifted to GHS Gurguri
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Kohat
30-11--1 30-11--1 - 30-11--1 - 38.158 36.569 0 0 0 0 36.569 1.589 - 96%
September - 2018
Completed & H/O (6 units).
No Image
1) Babri Banda Kohat
2) Lachi
3) PG at GHSS Gumbat PK-37
4) PG at GGHS Togh Bala PK-37
5) PG at GHS Khadizai PK-38
6) PG at GHHS Nandaraka PK-39
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Kohat
30-11--1 30-11--1 - 30-11--1 - 38.158 36.569 0 0 0 0 36.569 1.589 - 96%
July - 2018
Completed & H/O (6 units).
No Image
1) Babri Banda Kohat
2) Lachi
3) PG at GHSS Gumbat PK-37
4) PG at GGHS Togh Bala PK-37
5) PG at GHS Khadizai PK-38
6) PG at GHHS Nandaraka PK-39
946
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 406.458 81.423 10 10 10 9.837 91.26 315.035 22% 22%
December - 2018
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
No Image
1) Bataira to Mirbat Road PK-62 (BW 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (BW 7 Km)
946
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 406.458 81.423 10 10 10 9.837 91.26 315.035 22% 22%
November - 2018
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
No Image
1) Bataira to Mirbat Road PK-62 (BW 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (BW 7 Km)
946
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 406.458 81.423 10 10 10 9.837 91.26 315.035 22% 22%
November - 2018
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
No Image
1) Bataira to Mirbat Road PK-62 (BW 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (BW 7 Km)
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 30 14.918 0 0 0 0 14.918 15.082 - 50%
September - 2018
Pattan - completed & H/O. Dassu - site not H/O. Bataira - site not H/O.
No Image
1) Dassu
2) Pattan
3) Bataira Palas
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 30 14.918 0 0 0 0 14.918 15.082 - 50%
July - 2018
Pattan - completed & H/O. Dassu - site not H/O. Bataira - site not H/O.
No Image
1) Dassu
2) Pattan
3) Bataira Palas
946
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 406.458 81.423 10 16.925 16.925 16.925 98.348 315.035 22% 24%
April - 2019
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
No Image
1) Bataira to Mirbat Road PK-62 (BW 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (BW 7 Km)
946
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 406.458 81.423 10 16.925 16.925 16.925 98.348 315.035 22% 24%
March - 2019
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
No Image
1) Bataira to Mirbat Road PK-62 (BW 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (BW 7 Km)
946
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 406.458 81.423 10 16.925 16.925 16.925 98.348 315.035 22% 24%
March - 2019
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
No Image
1) Bataira to Mirbat Road PK-62 (BW 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (BW 7 Km)
946
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 406.458 81.423 10 16.925 16.925 9.837 91.26 315.035 22% 22%
February - 2019
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
No Image
1) Bataira to Mirbat Road PK-62 (BW 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (BW 7 Km)
946
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 406.458 81.423 10 10 10 9.837 91.26 315.035 22% 22%
January - 2019
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
No Image
1) Bataira to Mirbat Road PK-62 (BW 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (BW 7 Km)
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 44.551 29.4 0.001 0.001 0.001 0 29.4 15.15 66% 66%
September - 2018
Completed (9 units).
No Image
1) GHSS Shahbaz Khel PK-75
2) GHS Ghazni Khel PK-75
3) GHS Taja Zai PK-75
4) GHS Kot Kashmir PK-74
5) GHS Dara Pezu PK-75
6) GHS Kheru Kanal PK-75
7) PG at GHS Dallo Khel PK-76
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 44.551 29.4 0 0 0 0 29.4 15.151 - 66%
July - 2018
Completed (9 units).
No Image
1) GHSS Shahbaz Khel PK-75
2) GHS Ghazni Khel PK-75
3) GHS Taja Zai PK-75
4) GHS Kot Kashmir PK-74
5) GHS Dara Pezu PK-75
6) GHS Kheru Kanal PK-75
7) PG at GHS Dallo Khel PK-76
946
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Malakand
30-11--1 30-11--1 - 30-11--1 - 31.357 18.522 3.552 3.552 3.552 0 18.522 9.283 70% 59%
September - 2018
Out of 2 units, PG Totakan - completed & H/O. PG Dargai - BW, pavilion in progress, main gate completed.
No Image
1) Totakan at Tehsil Batkhela (construction of playground)
2) Dargai (construction of playground)