Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
939 (OG) |
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.712 | 14.612 | 10.1 | 10.1 | 10.1 | 10.1 | 24.712 | 0 | 100% |
100% December - 2018 |
Piling and pile cap completed. Girder casted (single span bridge). Work stopped due to snow bound area. |
No Image |
PK-92, Dir Upper | |||||||||||||||||||
939 (OG) |
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.712 | 14.612 | 10.1 | 10.1 | 10.1 | 10 | 24.612 | 0 | 100% |
100% November - 2018 |
Piling and pile cap completed. Girder casted (single span bridge). |
No Image |
PK-92, Dir Upper | |||||||||||||||||||
939 (OG) |
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.712 | 14.612 | 10.1 | 10.1 | 10.1 | 10 | 24.612 | 0 | 100% |
100% November - 2018 |
Piling and pile cap completed. Girder casted (single span bridge). |
No Image |
PK-92, Dir Upper | |||||||||||||||||||
939 (OG) |
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.712 | 14.612 | 10.1 | 14.6 | 14.6 | 14.6 | 29.212 | 0 | 100% |
100% April - 2019 |
Completed |
No Image |
PK-92, Dir Upper | |||||||||||||||||||
939 (OG) |
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.712 | 14.612 | 10.1 | 14.6 | 14.6 | 14.6 | 29.212 | 0 | 100% |
100% March - 2019 |
Completed |
No Image |
PK-92, Dir Upper | |||||||||||||||||||
939 (OG) |
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.712 | 14.612 | 10.1 | 14.6 | 14.6 | 14.6 | 29.212 | 0 | 100% |
100% March - 2019 |
Completed |
No Image |
PK-92, Dir Upper | |||||||||||||||||||
939 (OG) |
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.712 | 14.612 | 10.1 | 14.6 | 14.6 | 10.1 | 24.712 | 0 | 100% |
100% February - 2019 |
Piling and pile cap completed. Girder casted (single span bridge). Work stopped due to snow bound area. |
No Image |
PK-92, Dir Upper | |||||||||||||||||||
939 (OG) |
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.712 | 14.612 | 10.1 | 14.6 | 14.6 | 10.1 | 24.712 | 0 | 100% |
100% January - 2019 |
Piling and pile cap completed. Girder casted (single span bridge). Work stopped due to snow bound area. |
No Image |
PK-92, Dir Upper | |||||||||||||||||||
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
- | - | - | 23-12-16 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
Site/scope of work not identified. |
No Image |
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
- | - | - | 23-12-16 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
Site/scope of work not identified. |
No Image |
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
- | - | - | 23-12-16 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
Site/scope of work not identified. |
No Image |
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
- | - | - | 23-12-16 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
Site/scope of work not identified. |
No Image |
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
Site/scope of work not identified. |
No Image |
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
Site/scope of work not identified. |
No Image |
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
Site/scope of work not identified. |
No Image |
Haripur | |||||||||||||||||||
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
Site/scope of work not identified. |
No Image |
Haripur | |||||||||||||||||||
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
Site/scope of work not identified. |
No Image |
Haripur | |||||||||||||||||||
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
Site/scope of work not identified. |
No Image |
Haripur | |||||||||||||||||||
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
Site/scope of work not identified. |
No Image |
939 (OG) |
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 242.629 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
Site/scope of work not identified. |
No Image |
939 (New) |
190589-Construction of roads in PK-65 District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 5 | 5 | 5 | 0 | 0 | 145 | 3% |
- December - 2019 |
Financial Bid opening on 13/1/2020 |
No Image |
939 (New) |
190589-Construction of roads in PK-65 District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 145 | 3% |
- November - 2019 |
Approved . Technical bids opening on 26/12/2019 |
No Image |
939 (New) |
190589-Construction of roads in PK-65 District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
DCE re-submitted to P&D. Pre PDWP held on 12/11/2019. |
No Image |
939 (New) |
190589-Construction of roads in PK-65 District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
DCE re-submitted to SE on 10/10/2019 to SE on MRS 2019 |
No Image |
939 (New) |
190589-Construction of roads in PK-65 District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
DCE submitted to SE on 11/09/2019 for Rs.150 m. |
No Image |
939 (New) |
190589-Construction of roads in PK-65 District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 5 | 0 | 0 | 0 | 0 | 145 | 3% |
- May - 2020 |
No Image | |
939 (New) |
190589-Construction of roads in PK-65 District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 5 | 0 | 0 | 0 | 0 | 145 | 3% |
- April - 2020 |
No Image | |
939 (New) |
190589-Construction of roads in PK-65 District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 5 | 0 | 0 | 0 | 0 | 145 | 3% |
- March - 2020 |
No Image | |
939 (New) |
190589-Construction of roads in PK-65 District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 5 | 0 | 0 | 0 | 0 | 145 | 3% |
- February - 2020 |
No Image | |
939 (New) |
190589-Construction of roads in PK-65 District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 0 | 5 | 0 | 0 | 0 | 0 | 145 | 3% |
- January - 2020 |
Work order issued |
No Image |
939 (OG) |
150751-Feasibility and improvement of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 2.727 | 0.001 | 0.001 | 0.0005 | 0 | 2.727 | 1375.15 | 0% |
0% September - 2018 |
Work order issued on 04/04/2018. |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
939 (OG) |
150751-Feasibility and improvement of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 2.727 | 0.001 | 0.001 | 0 | 0 | 2.727 | 1375.15 | 0% |
0% July - 2018 |
Work order issued on 04/04/2018. |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
- December - 2020 |
No Image | |
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
- December - 2020 |
No Image | |
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
- October - 2020 |
No Image | |
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
- September - 2020 |
No Image | |
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
- August - 2020 |
No Image | |
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
July - 2020 |
No Image | |
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
- May - 2021 |
No Image | |
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
- April - 2021 |
No Image | |
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
- March - 2021 |
No Image | |
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
- February - 2021 |
No Image | |
939 (OG) |
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2619.5 | 1154.68 | 0 | 0 | 0 | 0 | 1154.68 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |