Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2019, April - 2020, April - 2021, April - 2018, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, July - 2018, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, September - 2018, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 170 44.014 44.014 38 27.192 197.192 17.5 92% 85%
December - 2020
Academic block, admin block, suits (2 Nos) finihing in progress.
No Image
Abbottabad
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 170 44.014 44.014 38 27.192 197.192 17.5 92% 85%
December - 2020
Academic block, admin block, suits (2 Nos) finihing in progress.
No Image
Abbottabad
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 170 44.014 44.014 38 19.192 189.192 17.5 92% 82%
October - 2020
Academic block, admin block, suits (2 Nos) finihing in progress.
No Image
Abbottabad
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 170 44.014 44.014 8 8 178 17.5 92% 77%
September - 2020
Academic block, admin block, suits (2 Nos) finihing in progress.
No Image
Abbottabad
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 170 44.014 44.014 0 0 170 17.5 92% 73%
August - 2020
Academic block, admin block, suits (2 Nos) in progress.
No Image
Abbottabad
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 170 44.014 0 0 0 170 17.5 92% 73%
July - 2020
Academic block, admin block, suits (2 Nos), exam h
No Image
Abbottabad
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 189.21 56.011 56.011 56.011 44.011 233.221 0 100% 100%
May - 2021
01- Unit Finishing in progress
No Image
GCMS (Boys) Abbottabad.
 
Scope of work:
  • Academic Block
  • Admin Block
  • Suits 02 Nos
  • Exam Hall
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 170 44.014 44.011 44.011 44.011 214.011 17.5 92% 92%
April - 2021
finihing in progress.
No Image
GCMS (Boys) Abbottabad.
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 170 44.014 38 38 33.011 203.011 17.5 92% 88%
March - 2021
finihing in progress.
No Image
GCMS (Boys) Abbottabad.
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 170 44.014 33 33 33 203 17.5 92% 88%
February - 2021
finihing in progress.
No Image
GCMS (Boys) Abbottabad.
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 170 44.014 38 38 33.011 203.011 17.5 92% 88%
January - 2021
Academic block, admin block, suits (2 Nos) finihing in progress.
No Image
GCMS (Boys) Abbottabad.
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
- - - 21-01-16 - 411.88 0 10 10 0 0 0 0 - -
December - 2017
Site/scope of work not identified.
No Image
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
- - - 21-01-16 - 411.88 0 10 10 0 0 0 0 - -
September - 2017
No Image
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
- - - 21-01-16 - 411.88 0 10 10 0 0 0 0 - -
August - 2017
No Image
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
- - - 21-01-16 - 411.88 0 10 10 0 0 0 0 - -
July - 2017
No Image
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 411.88 0 10 10 0 0 0 0 - -
November - 2017
No Image
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 411.88 0 10 10 0 0 0 0 - -
October - 2017
No Image
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 411.88 0 10 10 0 0 0 0 - -
June - 2018
Site/scope of work not identified.
No Image
Chitral
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 411.88 0 10 10 0 0 0 0 - -
May - 2018
Site/scope of work not identified.
No Image
Chitral
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 411.88 0 10 10 0 0 0 0 - -
April - 2018
Site/scope of work not identified.
No Image
Chitral
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 411.88 0 10 10 0 0 0 0 - -
March - 2018
Site/scope of work not identified.
No Image
Chitral
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 411.88 0 10 10 0 0 0 0 - -
February - 2018
Site/scope of work not identified.
No Image
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 411.88 0 10 10 0 0 0 0 - -
January - 2018
Site/scope of work not identified.
No Image
936
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 35.862 10 9.5 5.0005 5 40.862 254.138 15% 14%
December - 2018
Out of 8 units, all in progress. Summary approved for revised cost for Rs.338.380 m. Work stopped due to snow bound area.
No Image
1) Sultan Khel Dara left Molvi road BT road (4 Km)
2) Sultan Khel Dara right Kass Banda to Patwo road (4 Km)
3) Roghano Dara right Nasir Abad toJilar road (3 Km BT)
4) Karo Dara left Bandagai to Mastai Dehrai (3 Km BT)
5) Karo Dara right Gulibagh raod (2 Km BT)
6) Luqman Banda Adhoky Payeen and Bala road (2 Km)
7) Luqman Banda Safary road (3 Km BT)
8) Luqman Banda Main and Kamar Tall road (4 Km BT)
936
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 35.862 10 9.5 4.501 0 35.862 254.138 15% 12%
November - 2018
Out of 8 units, all in progress. Summary approved for revised cost for Rs.338.380 m.
No Image
1) Sultan Khel Dara left Molvi road BT road (4 Km)
2) Sultan Khel Dara right Kass Banda to Patwo road (4 Km)
3) Roghano Dara right Nasir Abad toJilar road (3 Km BT)
4) Karo Dara left Bandagai to Mastai Dehrai (3 Km BT)
5) Karo Dara right Gulibagh raod (2 Km BT)
6) Luqman Banda Adhoky Payeen and Bala road (2 Km)
7) Luqman Banda Safary road (3 Km BT)
8) Luqman Banda Main and Kamar Tall road (4 Km BT)
936
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 35.862 10 9.5 4.501 0 35.862 254.138 15% 12%
November - 2018
Out of 8 units, all in progress. Summary approved for revised cost for Rs.338.380 m.
No Image
1) Sultan Khel Dara left Molvi road BT road (4 Km)
2) Sultan Khel Dara right Kass Banda to Patwo road (4 Km)
3) Roghano Dara right Nasir Abad toJilar road (3 Km BT)
4) Karo Dara left Bandagai to Mastai Dehrai (3 Km BT)
5) Karo Dara right Gulibagh raod (2 Km BT)
6) Luqman Banda Adhoky Payeen and Bala road (2 Km)
7) Luqman Banda Safary road (3 Km BT)
8) Luqman Banda Main and Kamar Tall road (4 Km BT)
936
(OG)
150833-Rehabilitation / Reconstruction of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 336.821 35.862 10 9.5 9.5 9.5 45.362 290.959 14% 13%
April - 2019
Out of 8 units, all in progress. Work stopped due to snow bound area. Liabilty Rs.31 m.
No Image
1) Sultan Khel Dara left Molvi road BT road (4 Km)
2) Sultan Khel Dara right Kass Banda to Patwo road (4 Km)
3) Roghano Dara right Nasir Abad toJilar road (3 Km BT)
4) Karo Dara left Bandagai to Mastai Dehrai (3 Km BT)
5) Karo Dara right Gulibagh raod (2 Km BT)
6) Luqman Banda Adhoky Payeen and Bala road (2 Km)
7) Luqman Banda Safary road (3 Km BT)
8) Luqman Banda Main and Kamar Tall road (4 Km BT)
936
(OG)
150833-Rehabilitation / Reconstruction of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 336.821 35.862 10 9.5 8.2505 8.25 44.112 290.959 14% 13%
March - 2019
Out of 8 units, all in progress. Work stopped due to snow bound area. Liabilty Rs.31 m.
No Image
1) Sultan Khel Dara left Molvi road BT road (4 Km)
2) Sultan Khel Dara right Kass Banda to Patwo road (4 Km)
3) Roghano Dara right Nasir Abad toJilar road (3 Km BT)
4) Karo Dara left Bandagai to Mastai Dehrai (3 Km BT)
5) Karo Dara right Gulibagh raod (2 Km BT)
6) Luqman Banda Adhoky Payeen and Bala road (2 Km)
7) Luqman Banda Safary road (3 Km BT)
8) Luqman Banda Main and Kamar Tall road (4 Km BT)
936
(OG)
150833-Rehabilitation / Reconstruction of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 336.821 35.862 10 9.5 8.2505 8.25 44.112 290.959 14% 13%
March - 2019
Out of 8 units, all in progress. Work stopped due to snow bound area. Liabilty Rs.31 m.
No Image
1) Sultan Khel Dara left Molvi road BT road (4 Km)
2) Sultan Khel Dara right Kass Banda to Patwo road (4 Km)
3) Roghano Dara right Nasir Abad toJilar road (3 Km BT)
4) Karo Dara left Bandagai to Mastai Dehrai (3 Km BT)
5) Karo Dara right Gulibagh raod (2 Km BT)
6) Luqman Banda Adhoky Payeen and Bala road (2 Km)
7) Luqman Banda Safary road (3 Km BT)
8) Luqman Banda Main and Kamar Tall road (4 Km BT)
936
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 35.862 10 9.5 8.2505 7.5 43.362 254.138 15% 14%
February - 2019
Out of 8 units, all in progress. Summary approved for revised cost for Rs.338.380 m. Work stopped due to snow bound area. Liabilty Rs. 31 M
No Image
1) Sultan Khel Dara left Molvi road BT road (4 Km)
2) Sultan Khel Dara right Kass Banda to Patwo road (4 Km)
3) Roghano Dara right Nasir Abad toJilar road (3 Km BT)
4) Karo Dara left Bandagai to Mastai Dehrai (3 Km BT)
5) Karo Dara right Gulibagh raod (2 Km BT)
6) Luqman Banda Adhoky Payeen and Bala road (2 Km)
7) Luqman Banda Safary road (3 Km BT)
8) Luqman Banda Main and Kamar Tall road (4 Km BT)
936
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 35.862 10 9.5 7.5005 7.5 43.362 254.138 15% 14%
January - 2019
Out of 8 units, all in progress. Summary approved for revised cost for Rs.338.380 m. Work stopped due to snow bound area.
No Image
1) Sultan Khel Dara left Molvi road BT road (4 Km)
2) Sultan Khel Dara right Kass Banda to Patwo road (4 Km)
3) Roghano Dara right Nasir Abad toJilar road (3 Km BT)
4) Karo Dara left Bandagai to Mastai Dehrai (3 Km BT)
5) Karo Dara right Gulibagh raod (2 Km BT)
6) Luqman Banda Adhoky Payeen and Bala road (2 Km)
7) Luqman Banda Safary road (3 Km BT)
8) Luqman Banda Main and Kamar Tall road (4 Km BT)
936
(OG)
150468-Establishment of Sports Complex at Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 161.987 82.553 10 10 5 5 87.553 69.434 57% 54%
September - 2018
SHAZ consultant - design and supervision. Hostel - flooring in progress. Gymnasium - SS in progress. Swimming pool - foundation in progress. Revised PC-I/DCE for RS.258.850 m submitted to Sports Officer on 11/04/2018.
No Image
Kohat
936
(OG)
150468-Establishment of Sports Complex at Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 161.987 82.553 10 10 0 0 82.553 69.434 57% 51%
July - 2018
SHAZ consultant - design and supervision. Hostel - flooring in progress. Gymnasium - SS in progress. Swimming pool - foundation in progress. Revised PC-I/DCE for RS.258.850 m submitted to Sports Officer on 11/04/2018.
No Image
Kohat
936
(New)
190586-Construction of roads in PK-62 District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 0 5 5 0 0 0 0 - -
December - 2019
Approved for Rs. 338 M. Summary for cost enhancement submitted to CA
No Image
936
(New)
190586-Construction of roads in PK-62 District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 5 5 0 0 0 0 - -
November - 2019
Approved. Summary for cost enhancement submitted to CA
No Image
936
(New)
190586-Construction of roads in PK-62 District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 5 5 0 0 0 0 - -
October - 2019
DCE re-submitted to P&D. Pre PDWP held on 12/11/2019.
No Image
936
(New)
190586-Construction of roads in PK-62 District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 5 5 0 0 0 0 - -
September - 2019
DCE re-submitted to SE on 10/10/2019 to SE on MRS 2019
No Image
936
(New)
190586-Construction of roads in PK-62 District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 5 5 0 0 0 0 - -
August - 2019
DCE submitted to SE on 11/09/2019 for Rs.150 m.
No Image
936
(New)
190586-Construction of roads in PK-62 District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 338 0 5 5 0 0 0 333 1% -
May - 2020
Technical bids opened
No Image
936
(New)
190586-Construction of roads in PK-62 District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 338 0 5 5 0 0 0 333 1% -
April - 2020
Technical bids opened
No Image
936
(New)
190586-Construction of roads in PK-62 District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 338 0 5 5 0 0 0 333 1% -
March - 2020
Technical bids opened
No Image
936
(New)
190586-Construction of roads in PK-62 District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 338 0 5 5 0 0 0 333 1% -
February - 2020
Technical bids opened
No Image
936
(New)
190586-Construction of roads in PK-62 District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 338 0 5 5 0 0 0 333 1% -
January - 2020
Technical bids opened
No Image
Pages : 1