Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2020, August - 2020, August - 2019, September - 2020, September - 2019, October - 2020, October - 2019, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
904
(OG)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 10.75 15 14.04375 14.04375 0 10.75 124.25 17% 7%
December - 2019
Spervisiory consultant selected (Spectra Consultants). Earth work in progress.
No Image
Abbottabad
904
(OG)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 10.75 15 15 3.75 0 10.75 124.25 17% 7%
November - 2019
Spervisiory consultant selected (Spectra Consultants). Earth work in progress.
No Image
Abbottabad
904
(OG)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 10.75 15 15 3.75 0 10.75 124.25 17% 7%
October - 2019
Spervisiory consultant selected (Spectra Consultants). Earth work in progress.
No Image
Abbottabad
904
(OG)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 10.75 15 15 3.75 0 10.75 124.25 17% 7%
September - 2019
Spervisiory consultant selected (Spectra Consultants). Earth work in progress.
No Image
Abbottabad
904
(OG)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 10.75 15 15 3.75 0 10.75 124.25 17% 7%
August - 2019
Spervisiory consultant selected (Spectra Consultants). Earth work in progress.
No Image
Abbottabad
904
(OG)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 10.75 15 14.04375 14.04375 11.86 22.61 124.25 17% 15%
May - 2020
Length 5 KM - Spervisiory consultant selected (Spectra Consultants). Earth work in progress.
No Image
Abbottabad
904
(OG)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 10.75 15 14.04375 14.04375 11.86 22.61 124.25 17% 15%
April - 2020
Length 5 KM - Spervisiory consultant selected (Spectra Consultants). Earth work in progress.
No Image
Abbottabad
904
(OG)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 10.75 15 14.04375 14.04375 11.86 22.61 124.25 17% 15%
March - 2020
Length 5 KM - Spervisiory consultant selected (Spectra Consultants). Earth work in progress.
No Image
Abbottabad
904
(OG)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 10.75 15 14.04375 14.04375 11.86 22.61 124.25 17% 15%
February - 2020
Length 5 KM - Spervisiory consultant selected (Spectra Consultants). Earth work in progress.
No Image
Abbottabad
904
(OG)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 10.75 15 14.04375 14.04375 11.86 22.61 124.25 17% 15%
January - 2020
Length 5 KM - Spervisiory consultant selected (Spectra Consultants). Earth work in progress.
No Image
Abbottabad
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 37.112 19 16.473 261.983 0 100% 100%
December - 2020
Main building - finishing, BW. Demond notice issue to XEN WAPDA.
No Image
PK-56 Charsadda
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 37.112 19 16.473 261.983 0 100% 100%
December - 2020
Main building - finishing, BW. Demond notice issue to XEN WAPDA.
No Image
PK-56 Charsadda
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 37.112 19 16.473 261.983 0 100% 100%
October - 2020
Main building - finishing, BW. Demond notice issue to XEN WAPDA.
No Image
PK-56 Charsadda
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 37.112 19 8.273 253.783 0 100% 100%
September - 2020
Main building - finishing, BW. Demond notice issue to XEN WAPDA.
No Image
PK-56 Charsadda
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 37.112 19 0 245.51 0 100% 100%
August - 2020
Main building - finishing, BW. Demond notice issue to XEN WAPDA.
No Image
PK-56 Charsadda
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 0 0 0 245.51 0 100% 100%
July - 2020
Main building - finishing, BW, developmental work
No Image
PK-56 Charsadda
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 28 28 24.293 269.803 0 100% 100%
May - 2021
01- Unit Finishing in progress Revised PC-I Submitted
No Image
PK-56 Charsadda
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 28 28 19.612 265.122 0 100% 100%
April - 2021
Main building - finishing, BW. Demond notice issue to XEN WAPDA. Revised PC-I Submitted
No Image
PK-56 Charsadda
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 28 28 19.612 265.122 0 100% 100%
March - 2021
Main building - finishing, BW. Demond notice issue to XEN WAPDA.
No Image
PK-56 Charsadda
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 28 28 19.612 265.122 0 100% 100%
February - 2021
Main building - finishing, BW. Demond notice issue to XEN WAPDA.
No Image
PK-56 Charsadda
904
(OG)
151058-Establishment of Government Degree College.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 232.812 245.51 37.112 28 28 19.612 265.122 0 100% 100%
January - 2021
Main building - finishing, BW. Demond notice issue to XEN WAPDA.
No Image
PK-56 Charsadda
904
(OG)
150815-(a) Improvement / Widening & BT of Baikand to Nakhtar Kandaw road and Mian Killay to Sarbanda, Nazarabad to Ashar Banr road (b) Improvement / Widening & BT of Sigram to Malooka road (c) Construction / Rehabilitation of Malakabad to Gat road in Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 280 211.27 63.705 63.705 52.779 34.421 245.691 5.025 98% 88%
December - 2018
Length 18.5 Km - 3 Km BT completed.
No Image
1) Biakand to Nakhtar Kandaw road (4 Km)
2) Mian Kallay to Sarbanda road (3.5 Km)
3) Ronyal to Sar Banda road (3 Km)
4) Nazar Abad to Ashar Banr road (1 Km)
5) Sigram to Malooka road (2 Km)
6) Malakabad to Gat road (5 Km)
904
(OG)
150815-(a) Improvement / Widening & BT of Baikand to Nakhtar Kandaw road and Mian Killay to Sarbanda, Nazarabad to Ashar Banr road (b) Improvement / Widening & BT of Sigram to Malooka road (c) Construction / Rehabilitation of Malakabad to Gat road in Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 280 211.27 63.705 63.705 41.853 25.103 236.373 5.025 98% 84%
November - 2018
Length 18.5 Km - 3 Km BT completed.
No Image
1) Biakand to Nakhtar Kandaw road (4 Km)
2) Mian Kallay to Sarbanda road (3.5 Km)
3) Ronyal to Sar Banda road (3 Km)
4) Nazar Abad to Ashar Banr road (1 Km)
5) Sigram to Malooka road (2 Km)
6) Malakabad to Gat road (5 Km)
904
(OG)
150815-(a) Improvement / Widening & BT of Baikand to Nakhtar Kandaw road and Mian Killay to Sarbanda, Nazarabad to Ashar Banr road (b) Improvement / Widening & BT of Sigram to Malooka road (c) Construction / Rehabilitation of Malakabad to Gat road in Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 280 211.27 63.705 63.705 41.853 25.103 236.373 5.025 98% 84%
November - 2018
Length 18.5 Km - 3 Km BT completed.
No Image
1) Biakand to Nakhtar Kandaw road (4 Km)
2) Mian Kallay to Sarbanda road (3.5 Km)
3) Ronyal to Sar Banda road (3 Km)
4) Nazar Abad to Ashar Banr road (1 Km)
5) Sigram to Malooka road (2 Km)
6) Malakabad to Gat road (5 Km)
904
(OG)
150815-(a) Improvement / Widening & BT of Baikand to Nakhtar Kandaw road and Mian Killay to Sarbanda, Nazarabad to Ashar Banr road (b) Improvement / Widening & BT of Sigram to Malooka road (c) Construction / Rehabilitation of Malakabad to Gat road in Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 280 211.27 63.705 63.705 63.705 34.421 245.691 5.025 98% 88%
April - 2019
Length 18.5 Km - 3 Km BT completed. Rs.11.07 m required additionally.
No Image
1) Biakand to Nakhtar Kandaw road (4 Km)
2) Mian Kallay to Sarbanda road (3.5 Km)
3) Ronyal to Sar Banda road (3 Km)
4) Nazar Abad to Ashar Banr road (1 Km)
5) Sigram to Malooka road (2 Km)
6) Malakabad to Gat road (5 Km)
904
(OG)
150815-(a) Improvement / Widening & BT of Baikand to Nakhtar Kandaw road and Mian Killay to Sarbanda, Nazarabad to Ashar Banr road (b) Improvement / Widening & BT of Sigram to Malooka road (c) Construction / Rehabilitation of Malakabad to Gat road in Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 280 211.27 63.705 63.705 63.705 34.421 245.691 5.025 98% 88%
March - 2019
Length 18.5 Km - 3 Km BT completed. Rs.11.07 m required additionally.
No Image
1) Biakand to Nakhtar Kandaw road (4 Km)
2) Mian Kallay to Sarbanda road (3.5 Km)
3) Ronyal to Sar Banda road (3 Km)
4) Nazar Abad to Ashar Banr road (1 Km)
5) Sigram to Malooka road (2 Km)
6) Malakabad to Gat road (5 Km)
904
(OG)
150815-(a) Improvement / Widening & BT of Baikand to Nakhtar Kandaw road and Mian Killay to Sarbanda, Nazarabad to Ashar Banr road (b) Improvement / Widening & BT of Sigram to Malooka road (c) Construction / Rehabilitation of Malakabad to Gat road in Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 280 211.27 63.705 63.705 63.705 34.421 245.691 5.025 98% 88%
March - 2019
Length 18.5 Km - 3 Km BT completed. Rs.11.07 m required additionally.
No Image
1) Biakand to Nakhtar Kandaw road (4 Km)
2) Mian Kallay to Sarbanda road (3.5 Km)
3) Ronyal to Sar Banda road (3 Km)
4) Nazar Abad to Ashar Banr road (1 Km)
5) Sigram to Malooka road (2 Km)
6) Malakabad to Gat road (5 Km)
904
(OG)
150815-(a) Improvement / Widening & BT of Baikand to Nakhtar Kandaw road and Mian Killay to Sarbanda, Nazarabad to Ashar Banr road (b) Improvement / Widening & BT of Sigram to Malooka road (c) Construction / Rehabilitation of Malakabad to Gat road in Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 280 211.27 63.705 63.705 63.705 34.421 245.691 5.025 98% 88%
February - 2019
Length 18.5 Km - 3 Km BT completed. Rs. 11.07 m required additionally
No Image
1) Biakand to Nakhtar Kandaw road (4 Km)
2) Mian Kallay to Sarbanda road (3.5 Km)
3) Ronyal to Sar Banda road (3 Km)
4) Nazar Abad to Ashar Banr road (1 Km)
5) Sigram to Malooka road (2 Km)
6) Malakabad to Gat road (5 Km)
904
(OG)
150815-(a) Improvement / Widening & BT of Baikand to Nakhtar Kandaw road and Mian Killay to Sarbanda, Nazarabad to Ashar Banr road (b) Improvement / Widening & BT of Sigram to Malooka road (c) Construction / Rehabilitation of Malakabad to Gat road in Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 280 211.27 63.705 63.705 52.779 34.421 245.691 5.025 98% 88%
January - 2019
Length 18.5 Km - 3 Km BT completed.
No Image
1) Biakand to Nakhtar Kandaw road (4 Km)
2) Mian Kallay to Sarbanda road (3.5 Km)
3) Ronyal to Sar Banda road (3 Km)
4) Nazar Abad to Ashar Banr road (1 Km)
5) Sigram to Malooka road (2 Km)
6) Malakabad to Gat road (5 Km)
Pages : 1