Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
- December - 2020 |
No Image | |
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
- December - 2020 |
No Image | |
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
- October - 2020 |
No Image | |
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
- September - 2020 |
No Image | |
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
- August - 2020 |
No Image | |
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
July - 2020 |
No Image | |
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
- May - 2021 |
No Image | |
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
- April - 2021 |
No Image | |
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
- March - 2021 |
No Image | |
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
- February - 2021 |
No Image | |
90 (OG) |
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.24 | 35.24 | 0 | 0 | 0 | 0 | 35.24 | 0 | - |
- January - 2021 |
No Image | |
90 (OG) |
150622-Construction of residences for P&D Staff at Hayatabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.3 | 24.061 | 51.025 | 51.025 | 40.512 | 30 | 54.061 | 75.214 | 50% |
36% December - 2018 |
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m. |
No Image |
8 Nos, Residences (1 Kanal ) | |||||||||||||||||||
90 (OG) |
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 387.641 | 317.283 | 30 | 30 | 30 | 20.087 | 337.37 | 40.358 | 90% |
87% December - 2019 |
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
Library- tile work in progress. |
No Image |
Peshawar | |||||||||||||||||||
90 (OG) |
150622-Construction of residences for P&D Staff at Hayatabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.3 | 24.061 | 51.025 | 51.025 | 30 | 30 | 54.061 | 75.214 | 50% |
36% November - 2018 |
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m. |
No Image |
8 Nos, Residences (1 Kanal ) | |||||||||||||||||||
90 (OG) |
150622-Construction of residences for P&D Staff at Hayatabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.3 | 24.061 | 51.025 | 51.025 | 30 | 30 | 54.061 | 75.214 | 50% |
36% November - 2018 |
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m. |
No Image |
8 Nos, Residences (1 Kanal ) | |||||||||||||||||||
90 (OG) |
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 387.641 | 317.283 | 30 | 30 | 30 | 20.087 | 337.37 | 40.358 | 90% |
87% November - 2019 |
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
Library- tile work in progress. |
No Image |
Peshawar | |||||||||||||||||||
90 (OG) |
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 387.641 | 317.283 | 30 | 30 | 7.5 | 7.5 | 324.783 | 40.358 | 90% |
84% October - 2019 |
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
Library- tile work in progress. |
No Image |
Peshawar | |||||||||||||||||||
90 (OG) |
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.5 | 0 | 0 | 10 | 5 | 0 | 0 | 51.5 | - |
- September - 2018 |
Work order issued. Site is not H/O. |
No Image |
Islamabad | |||||||||||||||||||
90 (OG) |
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 387.641 | 317.283 | 30 | 30 | 7.5 | 7.5 | 324.783 | 40.358 | 90% |
84% September - 2019 |
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
Library- tile work in progress. |
No Image |
Peshawar | |||||||||||||||||||
90 (OG) |
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 387.641 | 317.283 | 30 | 30 | 7.5 | 7.5 | 324.783 | 40.358 | 90% |
84% August - 2019 |
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. |
No Image |
Peshawar | |||||||||||||||||||
90 (OG) |
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.5 | 0 | 0 | 0 | 5 | 0 | 0 | 51.5 | - |
- July - 2018 |
Work order issued. Site is not H/O. |
No Image |
Islamabad | |||||||||||||||||||
90 (OG) |
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 387.641 | 317.283 | 30 | 30 | 30 | 30 | 347.283 | 40.358 | 90% |
90% May - 2020 |
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
Library- tile work in progress. |
No Image |
Peshawar | |||||||||||||||||||
90 (OG) |
150622-Construction of residences for P&D Staff at Hayatabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.3 | 24.061 | 51.025 | 51.923 | 51.923 | 40.512 | 64.573 | 75.214 | 50% |
43% April - 2019 |
Work started (Package-I & II). Basement roof laid of 8 Nos residences. |
No Image |
8 Nos, Residences (1 Kanal ) | |||||||||||||||||||
90 (OG) |
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 387.641 | 317.283 | 30 | 30 | 30 | 20.087 | 337.37 | 40.358 | 90% |
87% April - 2020 |
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
Library- tile work in progress. |
No Image |
Peshawar | |||||||||||||||||||
90 (OG) |
150622-Construction of residences for P&D Staff at Hayatabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.3 | 24.061 | 51.025 | 51.025 | 40.512 | 40.512 | 64.573 | 75.214 | 50% |
43% March - 2019 |
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m. |
No Image |
8 Nos, Residences (1 Kanal ) | |||||||||||||||||||
90 (OG) |
150622-Construction of residences for P&D Staff at Hayatabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.3 | 24.061 | 51.025 | 51.025 | 40.512 | 40.512 | 64.573 | 75.214 | 50% |
43% March - 2019 |
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m. |
No Image |
8 Nos, Residences (1 Kanal ) | |||||||||||||||||||
90 (OG) |
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 387.641 | 317.283 | 30 | 30 | 30 | 20.087 | 337.37 | 40.358 | 90% |
87% March - 2020 |
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
Library- tile work in progress. |
No Image |
Peshawar | |||||||||||||||||||
90 (OG) |
150622-Construction of residences for P&D Staff at Hayatabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.3 | 24.061 | 51.025 | 51.025 | 40.512 | 40.512 | 64.573 | 75.214 | 50% |
43% February - 2019 |
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m. |
No Image |
8 Nos, Residences (1 Kanal ) | |||||||||||||||||||
90 (OG) |
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 387.641 | 317.283 | 30 | 30 | 30 | 20.087 | 337.37 | 40.358 | 90% |
87% February - 2020 |
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
Library- tile work in progress. |
No Image |
Peshawar | |||||||||||||||||||
90 (OG) |
150622-Construction of residences for P&D Staff at Hayatabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.3 | 24.061 | 51.025 | 51.025 | 40.512 | 30 | 54.061 | 75.214 | 50% |
36% January - 2019 |
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m. |
No Image |
8 Nos, Residences (1 Kanal ) | |||||||||||||||||||
90 (OG) |
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 387.641 | 317.283 | 30 | 30 | 30 | 20.087 | 337.37 | 40.358 | 90% |
87% January - 2020 |
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
Library- tile work in progress. |
No Image |
Peshawar | |||||||||||||||||||
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-04-10 | 30-06-18 | - | 14-05-14 | - | 389.729 | 316.768 | 48.681 | 48.681 | 21.906 | 16.267 | 333.035 | 24.28 | 94% |
85% December - 2017 |
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress. |
No Image |
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 389.729 | 316.768 | 48.681 | 48.681 | 21.906 | 9.968 | 326.736 | 24.28 | 94% |
84% November - 2017 |
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress. |
No Image |
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 389.729 | 316.768 | 48.681 | 48.681 | 21.906 | 4.965 | 321.733 | 24.28 | 94% |
83% October - 2017 |
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress. |
No Image |
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-04-10 | 30-06-18 | - | 14-05-14 | - | 389.729 | 316.768 | 48.681 | 48.681 | 21.906 | 0 | 316.768 | 24.28 | 94% |
81% September - 2017 |
Block-1 half portion - in progress. Day Care Center - GF slab in progress. Ramp - slab in progress. |
No Image |
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-04-10 | 30-06-18 | - | 14-05-14 | - | 389.729 | 316.768 | 48.681 | 48.681 | 21.906 | 0 | 316.768 | 24.28 | 94% |
81% August - 2017 |
Block-1 half portion - in progress. Day Care Center - GF slab in progress. Ramp - slab in progress. |
No Image |
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-04-10 | 30-06-18 | - | 14-05-14 | - | 389.729 | 316.768 | 48.681 | 48.681 | 21.906 | 0 | 316.768 | 24.28 | 94% |
81% July - 2017 |
Block-1 half portion - in progress. Day Care Center - GF slab in progress. Ramp - slab in progress. |
No Image |
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 389.729 | 316.768 | 48.681 | 48.681 | 36.511 | 28.223 | 344.991 | 24.28 | 94% |
89% June - 2018 |
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress. |
No Image |
Civil Secretariat, Peshawar | |||||||||||||||||||
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 389.729 | 316.768 | 48.681 | 48.681 | 36.511 | 28.223 | 344.991 | 24.28 | 94% |
89% May - 2018 |
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress. |
No Image |
Civil Secretariat, Peshawar | |||||||||||||||||||
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 389.729 | 316.768 | 48.681 | 48.681 | 36.511 | 17.36 | 334.128 | 24.28 | 94% |
86% April - 2018 |
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress. |
No Image |
Civil Secretariat, Peshawar | |||||||||||||||||||
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 389.729 | 316.768 | 48.681 | 48.681 | 21.906 | 17.36 | 334.128 | 24.28 | 94% |
86% March - 2018 |
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress. |
No Image |
Civil Secretariat, Peshawar | |||||||||||||||||||
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 389.729 | 316.768 | 48.681 | 48.681 | 21.906 | 16.267 | 333.035 | 24.28 | 94% |
85% February - 2018 |
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress. |
No Image |
Civil Secretariat, Peshawar | |||||||||||||||||||
90 (OG) |
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 389.729 | 316.768 | 48.681 | 48.681 | 21.906 | 16.267 | 333.035 | 24.28 | 94% |
85% January - 2018 |
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress. |
No Image |
Pages : 1 |