Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2019, February - 2020, February - 2021, February - 2018, March - 2019, March - 2020, March - 2021, March - 2018, April - 2019, April - 2020, April - 2021, April - 2018, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, July - 2018, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, September - 2018, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2018, December - 2019, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 - -
December - 2020
No Image
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 - -
December - 2020
No Image
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 - -
October - 2020
No Image
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 - -
September - 2020
No Image
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 - -
August - 2020
No Image
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 -
July - 2020
No Image
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 - -
May - 2021
No Image
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 - -
April - 2021
No Image
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 - -
March - 2021
No Image
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 - -
February - 2021
No Image
90
(OG)
191048-070007-Provision of Mobile Veterinary Clinic in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 38.24 35.24 0 0 0 0 35.24 0 - -
January - 2021
No Image
90
(OG)
150622-Construction of residences for P&D Staff at Hayatabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 150.3 24.061 51.025 51.025 40.512 30 54.061 75.214 50% 36%
December - 2018
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m.
No Image
8 Nos, Residences (1 Kanal )
90
(OG)
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 387.641 317.283 30 30 30 20.087 337.37 40.358 90% 87%
December - 2019
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. Library- tile work in progress.
No Image
Peshawar
90
(OG)
150622-Construction of residences for P&D Staff at Hayatabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 150.3 24.061 51.025 51.025 30 30 54.061 75.214 50% 36%
November - 2018
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m.
No Image
8 Nos, Residences (1 Kanal )
90
(OG)
150622-Construction of residences for P&D Staff at Hayatabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 150.3 24.061 51.025 51.025 30 30 54.061 75.214 50% 36%
November - 2018
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m.
No Image
8 Nos, Residences (1 Kanal )
90
(OG)
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 387.641 317.283 30 30 30 20.087 337.37 40.358 90% 87%
November - 2019
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. Library- tile work in progress.
No Image
Peshawar
90
(OG)
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 387.641 317.283 30 30 7.5 7.5 324.783 40.358 90% 84%
October - 2019
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. Library- tile work in progress.
No Image
Peshawar
90
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 0 10 5 0 0 51.5 - -
September - 2018
Work order issued. Site is not H/O.
No Image
Islamabad
90
(OG)
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 387.641 317.283 30 30 7.5 7.5 324.783 40.358 90% 84%
September - 2019
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. Library- tile work in progress.
No Image
Peshawar
90
(OG)
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 387.641 317.283 30 30 7.5 7.5 324.783 40.358 90% 84%
August - 2019
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
No Image
Peshawar
90
(OG)
160619-Uplift of existing Khyber Pakhtunkhwa House Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 51.5 0 0 0 5 0 0 51.5 - -
July - 2018
Work order issued. Site is not H/O.
No Image
Islamabad
90
(OG)
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 387.641 317.283 30 30 30 30 347.283 40.358 90% 90%
May - 2020
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. Library- tile work in progress.
No Image
Peshawar
90
(OG)
150622-Construction of residences for P&D Staff at Hayatabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 150.3 24.061 51.025 51.923 51.923 40.512 64.573 75.214 50% 43%
April - 2019
Work started (Package-I & II). Basement roof laid of 8 Nos residences.
No Image
8 Nos, Residences (1 Kanal )
90
(OG)
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 387.641 317.283 30 30 30 20.087 337.37 40.358 90% 87%
April - 2020
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. Library- tile work in progress.
No Image
Peshawar
90
(OG)
150622-Construction of residences for P&D Staff at Hayatabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 150.3 24.061 51.025 51.025 40.512 40.512 64.573 75.214 50% 43%
March - 2019
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m.
No Image
8 Nos, Residences (1 Kanal )
90
(OG)
150622-Construction of residences for P&D Staff at Hayatabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 150.3 24.061 51.025 51.025 40.512 40.512 64.573 75.214 50% 43%
March - 2019
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m.
No Image
8 Nos, Residences (1 Kanal )
90
(OG)
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 387.641 317.283 30 30 30 20.087 337.37 40.358 90% 87%
March - 2020
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. Library- tile work in progress.
No Image
Peshawar
90
(OG)
150622-Construction of residences for P&D Staff at Hayatabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 150.3 24.061 51.025 51.025 40.512 40.512 64.573 75.214 50% 43%
February - 2019
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m.
No Image
8 Nos, Residences (1 Kanal )
90
(OG)
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 387.641 317.283 30 30 30 20.087 337.37 40.358 90% 87%
February - 2020
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. Library- tile work in progress.
No Image
Peshawar
90
(OG)
150622-Construction of residences for P&D Staff at Hayatabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 150.3 24.061 51.025 51.025 40.512 30 54.061 75.214 50% 36%
January - 2019
Work started (Package-I & II). Basement roof laid of 8 Nos residences. Can be completed for Rs.111.14 m.
No Image
8 Nos, Residences (1 Kanal )
90
(OG)
150214-Construction of Cafeteria/car parking/masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 387.641 317.283 30 30 30 20.087 337.37 40.358 90% 87%
January - 2020
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. Library- tile work in progress.
No Image
Peshawar
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-04-10 30-06-18 - 14-05-14 - 389.729 316.768 48.681 48.681 21.906 16.267 333.035 24.28 94% 85%
December - 2017
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.
No Image
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 389.729 316.768 48.681 48.681 21.906 9.968 326.736 24.28 94% 84%
November - 2017
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.
No Image
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 389.729 316.768 48.681 48.681 21.906 4.965 321.733 24.28 94% 83%
October - 2017
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.
No Image
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-04-10 30-06-18 - 14-05-14 - 389.729 316.768 48.681 48.681 21.906 0 316.768 24.28 94% 81%
September - 2017
Block-1 half portion - in progress. Day Care Center - GF slab in progress. Ramp - slab in progress.
No Image
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-04-10 30-06-18 - 14-05-14 - 389.729 316.768 48.681 48.681 21.906 0 316.768 24.28 94% 81%
August - 2017
Block-1 half portion - in progress. Day Care Center - GF slab in progress. Ramp - slab in progress.
No Image
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-04-10 30-06-18 - 14-05-14 - 389.729 316.768 48.681 48.681 21.906 0 316.768 24.28 94% 81%
July - 2017
Block-1 half portion - in progress. Day Care Center - GF slab in progress. Ramp - slab in progress.
No Image
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 389.729 316.768 48.681 48.681 36.511 28.223 344.991 24.28 94% 89%
June - 2018
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.
No Image
Civil Secretariat, Peshawar
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 389.729 316.768 48.681 48.681 36.511 28.223 344.991 24.28 94% 89%
May - 2018
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.
No Image
Civil Secretariat, Peshawar
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 389.729 316.768 48.681 48.681 36.511 17.36 334.128 24.28 94% 86%
April - 2018
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.
No Image
Civil Secretariat, Peshawar
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 389.729 316.768 48.681 48.681 21.906 17.36 334.128 24.28 94% 86%
March - 2018
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.
No Image
Civil Secretariat, Peshawar
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 389.729 316.768 48.681 48.681 21.906 16.267 333.035 24.28 94% 85%
February - 2018
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.
No Image
Civil Secretariat, Peshawar
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 389.729 316.768 48.681 48.681 21.906 16.267 333.035 24.28 94% 85%
January - 2018
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.