Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
895 (OG) |
140884-F/S, design and Construction of a) Arro Kas Summa to Lora via Banwari b) Improvement/Wiidening & BT of Tajwal to Bagan Road c) Garhi ? Chanali road via Seri, Abbottabad |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 148.985 | 31.795 | 31.795 | 31.795 | 16.847247 | 165.832247 | 0 | 100% |
92% December - 2019 |
Length 8 Km - out of 3 units, all in progress. |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
895 (OG) |
140884-F/S, design and Construction of a) Arro Kas Summa to Lora via Banwari b) Improvement/Wiidening & BT of Tajwal to Bagan Road c) Garhi ? Chanali road via Seri, Abbottabad |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 148.985 | 31.795 | 31.795 | 7.949 | 7.949 | 156.934 | 0 | 100% |
87% November - 2019 |
Length 8 Km - out of 3 units, all in progress. |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
895 (OG) |
140884-F/S, design and Construction of a) Arro Kas Summa to Lora via Banwari b) Improvement/Wiidening & BT of Tajwal to Bagan Road c) Garhi ? Chanali road via Seri, Abbottabad |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 148.985 | 31.795 | 31.795 | 7.949 | 7.949 | 156.934 | 0 | 100% |
87% October - 2019 |
Length 8 Km - out of 3 units, all in progress. |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
895 (OG) |
140884-F/S, design and Construction of a) Arro Kas Summa to Lora via Banwari b) Improvement/Wiidening & BT of Tajwal to Bagan Road c) Garhi ? Chanali road via Seri, Abbottabad |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 148.985 | 31.795 | 31.795 | 7.949 | 7.949 | 156.934 | 0 | 100% |
87% September - 2019 |
Length 8 Km - out of 3 units, all in progress. |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
895 (OG) |
140884-F/S, design and Construction of a) Arro Kas Summa to Lora via Banwari b) Improvement/Wiidening & BT of Tajwal to Bagan Road c) Garhi ? Chanali road via Seri, Abbottabad |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 148.985 | 31.795 | 31.795 | 7.949 | 0 | 148.985 | 0 | 100% |
82% August - 2019 |
Length 8 Km - out of 3 units, all in progress. |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
895 (OG) |
140884-F/S, design and Construction of a) Arro Kas Summa to Lora via Banwari b) Improvement/Wiidening & BT of Tajwal to Bagan Road c) Garhi ? Chanali road via Seri, Abbottabad |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 148.985 | 31.795 | 31.795 | 31.795 | 16.847247 | 165.832247 | 0 | 100% |
92% May - 2020 |
Length 8 Km - out of 3 units, all in progress.
Demand Rs. 36.02 as per TS + (2 M in PFY ) |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
895 (OG) |
140884-F/S, design and Construction of a) Arro Kas Summa to Lora via Banwari b) Improvement/Wiidening & BT of Tajwal to Bagan Road c) Garhi ? Chanali road via Seri, Abbottabad |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 148.985 | 31.795 | 31.795 | 31.795 | 16.847247 | 165.832247 | 0 | 100% |
92% April - 2020 |
Length 8 Km - out of 3 units, all in progress.
Demand Rs. 36.02 as per TS + (2 M in PFY ) |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
895 (OG) |
140884-F/S, design and Construction of a) Arro Kas Summa to Lora via Banwari b) Improvement/Wiidening & BT of Tajwal to Bagan Road c) Garhi ? Chanali road via Seri, Abbottabad |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 148.985 | 31.795 | 31.795 | 31.795 | 16.847247 | 165.832247 | 0 | 100% |
92% March - 2020 |
Length 8 Km - out of 3 units, all in progress.
Demand Rs. 36.02 as per TS + (2 M in PFY ) |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
895 (OG) |
140884-F/S, design and Construction of a) Arro Kas Summa to Lora via Banwari b) Improvement/Wiidening & BT of Tajwal to Bagan Road c) Garhi ? Chanali road via Seri, Abbottabad |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 148.985 | 31.795 | 31.795 | 31.795 | 16.847247 | 165.832247 | 0 | 100% |
92% February - 2020 |
Length 8 Km - out of 3 units, all in progress.
Demand Rs. 36.02 as per TS + (2 M in PFY ) |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
895 (OG) |
140884-F/S, design and Construction of a) Arro Kas Summa to Lora via Banwari b) Improvement/Wiidening & BT of Tajwal to Bagan Road c) Garhi ? Chanali road via Seri, Abbottabad |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 148.985 | 31.795 | 31.795 | 31.795 | 16.847247 | 165.832247 | 0 | 100% |
92% January - 2020 |
Length 8 Km - out of 3 units, all in progress.
Demand Rs. 36.02 as per TS + (2 M in PFY ) |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 148.467 | 0 | 50 | 0 | 0 | 0 | 0 | 98.467 | 34% |
- May - 2021 |
Tender Floated |
No Image |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 148.467 | 0 | 50 | 0 | 0 | 0 | 0 | 98.467 | 34% |
- April - 2021 |
Tender Floated |
No Image |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 148.467 | 0 | 50 | 0 | 0 | 0 | 0 | 98.467 | 34% |
- March - 2021 |
Tender Floated |
No Image |
895 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 4809 | 4809 | 0 | 0 | 0 | 9758.928 | 33% |
- September - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
895 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 14.722 | 30 | 30 | 15 | 0 | 14.722 | 2490.35 | 2% |
1% September - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
895 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 4809 | 4809 | 0 | 0 | 0 | 9758.928 | 33% |
- July - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
895 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 14.722 | 30 | 30 | 15 | 0 | 14.722 | 2490.35 | 2% |
1% July - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
895 (New) |
200096-Expansion/Upgradation of Khyber Girls Medical College, Peshawar for additional students of Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
895 (OG) |
31122-Improvement and widening of Matta-Fazil Banda Road, Bagh Dheri - Rahat Kot Road, Gari Lalkoo Road, Beryum Gat Shawar and Gat Peochar Road, Swat (59 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 838.228 | 784.955 | 34.644 | 34.644 | 17.3225 | 8.4795 | 793.4345 | 18.629 | 98% |
95% December - 2018 |
Out of 59 Km (width 18 ft) 58.3 Km completed. Matta Fazil Banda Section - (21/23.5 Km BT), WBM in 8 Km completed, structure work in all packages in progress. |
No Image |
1) Matta Fazal Banda (Km-1 and 23.5)
2) Rehabilitation of Beryum Shawar Gat road (22 Km)
3) Gat Peochar road (7 Km) | |||||||||||||||||||
895 (OG) |
31122-Improvement and widening of Matta-Fazil Banda Road, Bagh Dheri - Rahat Kot Road, Gari Lalkoo Road, Beryum Gat Shawar and Gat Peochar Road, Swat (59 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 838.228 | 784.955 | 34.644 | 34.644 | 17.3225 | 0.0005 | 784.9555 | 18.629 | 98% |
94% November - 2018 |
Out of 59 Km (width 18 ft) 58.3 Km completed. Matta Fazil Banda Section - (21/23.5 Km BT), WBM in 8 Km completed, structure work in all packages in progress. |
No Image |
1) Matta Fazal Banda (Km-1 and 23.5)
2) Rehabilitation of Beryum Shawar Gat road (22 Km)
3) Gat Peochar road (7 Km) | |||||||||||||||||||
895 (OG) |
31122-Improvement and widening of Matta-Fazil Banda Road, Bagh Dheri - Rahat Kot Road, Gari Lalkoo Road, Beryum Gat Shawar and Gat Peochar Road, Swat (59 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 838.228 | 784.955 | 34.644 | 34.644 | 17.3225 | 0.0005 | 784.9555 | 18.629 | 98% |
94% November - 2018 |
Out of 59 Km (width 18 ft) 58.3 Km completed. Matta Fazil Banda Section - (21/23.5 Km BT), WBM in 8 Km completed, structure work in all packages in progress. |
No Image |
1) Matta Fazal Banda (Km-1 and 23.5)
2) Rehabilitation of Beryum Shawar Gat road (22 Km)
3) Gat Peochar road (7 Km) | |||||||||||||||||||
895 (OG) |
31122-Improvement and widening of Matta-Fazil Banda Road, Bagh Dheri - Rahat Kot Road, Gari Lalkoo Road, Beryum Gat Shawar and Gat Peochar Road, Swat (59 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 838.228 | 784.955 | 34.644 | 34.644 | 34.6445 | 13.9165 | 798.8715 | 18.629 | 98% |
95% April - 2019 |
Out of 59 Km (width 18 ft) 58.3 Km completed. Matta Fazil Banda Section - (21/23.5 Km BT), WBM in 8 Km completed, structure work in all packages in progress. |
No Image |
1) Matta Fazal Banda (Km-1 and 23.5)
2) Rehabilitation of Beryum Shawar Gat road (22 Km)
3) Gat Peochar road (7 Km) | |||||||||||||||||||
895 (OG) |
31122-Improvement and widening of Matta-Fazil Banda Road, Bagh Dheri - Rahat Kot Road, Gari Lalkoo Road, Beryum Gat Shawar and Gat Peochar Road, Swat (59 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 838.228 | 784.955 | 34.644 | 34.644 | 34.6445 | 13.9165 | 798.8715 | 18.629 | 98% |
95% March - 2019 |
Out of 59 Km (width 18 ft) 58.3 Km completed. Matta Fazil Banda Section - (21/23.5 Km BT), WBM in 8 Km completed, structure work in all packages in progress. |
No Image |
1) Matta Fazal Banda (Km-1 and 23.5)
2) Rehabilitation of Beryum Shawar Gat road (22 Km)
3) Gat Peochar road (7 Km) | |||||||||||||||||||
895 (OG) |
31122-Improvement and widening of Matta-Fazil Banda Road, Bagh Dheri - Rahat Kot Road, Gari Lalkoo Road, Beryum Gat Shawar and Gat Peochar Road, Swat (59 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 838.228 | 784.955 | 34.644 | 34.644 | 34.6445 | 13.9165 | 798.8715 | 18.629 | 98% |
95% March - 2019 |
Out of 59 Km (width 18 ft) 58.3 Km completed. Matta Fazil Banda Section - (21/23.5 Km BT), WBM in 8 Km completed, structure work in all packages in progress. |
No Image |
1) Matta Fazal Banda (Km-1 and 23.5)
2) Rehabilitation of Beryum Shawar Gat road (22 Km)
3) Gat Peochar road (7 Km) | |||||||||||||||||||
895 (OG) |
31122-Improvement and widening of Matta-Fazil Banda Road, Bagh Dheri - Rahat Kot Road, Gari Lalkoo Road, Beryum Gat Shawar and Gat Peochar Road, Swat (59 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 838.228 | 784.955 | 34.644 | 34.644 | 34.6445 | 8.4795 | 793.4345 | 18.629 | 98% |
95% February - 2019 |
Out of 59 Km (width 18 ft) 58.3 Km completed. Matta Fazil Banda Section - (21/23.5 Km BT), WBM in 8 Km completed, structure work in all packages in progress. |
No Image |
1) Matta Fazal Banda (Km-1 and 23.5)
2) Rehabilitation of Beryum Shawar Gat road (22 Km)
3) Gat Peochar road (7 Km) | |||||||||||||||||||
895 (OG) |
31122-Improvement and widening of Matta-Fazil Banda Road, Bagh Dheri - Rahat Kot Road, Gari Lalkoo Road, Beryum Gat Shawar and Gat Peochar Road, Swat (59 Km). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 838.228 | 784.955 | 34.644 | 34.644 | 17.3225 | 8.4795 | 793.4345 | 18.629 | 98% |
95% January - 2019 |
Out of 59 Km (width 18 ft) 58.3 Km completed. Matta Fazil Banda Section - (21/23.5 Km BT), WBM in 8 Km completed, structure work in all packages in progress. |
No Image |
1) Matta Fazal Banda (Km-1 and 23.5)
2) Rehabilitation of Beryum Shawar Gat road (22 Km)
3) Gat Peochar road (7 Km) | |||||||||||||||||||