Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
885 (OG) |
150846-Construction of road (a) Dokda to Jawari to Korsar via Poland (b) Construction of Multi Span box culverts at village Sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 12.56 | 10 | 9.5 | 9.5 | 5 | 17.56 | 207.44 | 10% |
8% December - 2018 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
885 (OG) |
150846-Construction of road (a) Dokda to Jawari to Korsar via Poland (b) Construction of Multi Span box culverts at village Sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 12.56 | 10 | 9.5 | 4.501 | 5 | 17.56 | 207.44 | 10% |
8% November - 2018 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
885 (OG) |
150846-Construction of road (a) Dokda to Jawari to Korsar via Poland (b) Construction of Multi Span box culverts at village Sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 12.56 | 10 | 9.5 | 4.501 | 5 | 17.56 | 207.44 | 10% |
8% November - 2018 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
885 (OG) |
150846-Construction of road (a) Dokda to Jawari to Korsar via Poland (b) Construction of Multi Span box culverts at village Sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 12.56 | 10 | 49.5 | 49.5 | 12.54 | 25.1 | 207.44 | 10% |
11% April - 2019 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
885 (OG) |
150846-Construction of road (a) Dokda to Jawari to Korsar via Poland (b) Construction of Multi Span box culverts at village Sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 12.56 | 10 | 10 | 10 | 9.5 | 22.06 | 207.44 | 10% |
10% March - 2019 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. Liability 35 m |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
885 (OG) |
150846-Construction of road (a) Dokda to Jawari to Korsar via Poland (b) Construction of Multi Span box culverts at village Sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 12.56 | 10 | 10 | 10 | 9.5 | 22.06 | 207.44 | 10% |
10% March - 2019 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. Liability 35 m |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
885 (OG) |
150846-Construction of road (a) Dokda to Jawari to Korsar via Poland (b) Construction of Multi Span box culverts at village Sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 12.56 | 10 | 49.5 | 49.5005 | 4.5005 | 17.0605 | 207.44 | 10% |
7% February - 2019 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. Liability 35 m |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
885 (OG) |
150846-Construction of road (a) Dokda to Jawari to Korsar via Poland (b) Construction of Multi Span box culverts at village Sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 12.56 | 10 | 9.5 | 9.5 | 9.5 | 22.06 | 207.44 | 10% |
10% January - 2019 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
885 (OG) |
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.187 | 87.187 | 35 | 32.76875 | 32.76875 | 8.594886 | 95.781886 | 0 | 100% |
78% December - 2019 |
125.43 mtr -100 m bridge completed. Approach in progress. Right Approach road disputed by locals. REV DCE for RS. 186 M submitted to P&D (including cost of land) |
No Image |
PK-55, Mansehra | |||||||||||||||||||
885 (OG) |
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.187 | 87.187 | 35 | 35 | 8.75 | 5.2196 | 92.4066 | 0 | 100% |
76% November - 2019 |
125.43 mtr -100 m bridge completed. Approach in progress. Right Approach road disputed by locals. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
885 (OG) |
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.187 | 87.187 | 35 | 35 | 8.75 | 5.2196 | 92.4066 | 0 | 100% |
76% October - 2019 |
125.43 mtr -100 m bridge completed. Approach in progress. Right Approach road disputed by locals. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
885 (OG) |
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.187 | 87.187 | 35 | 35 | 8.75 | 5.2 | 92.387 | 0 | 100% |
76% September - 2019 |
125.43 mtr -100 m bridge completed. Approach in progress. Right Approach road disputed by locals. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
885 (OG) |
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.187 | 87.187 | 35 | 35 | 8.75 | 0 | 87.187 | 0 | 100% |
71% August - 2019 |
125.43 mtr -100 m bridge completed. Approach in progress. Right Approach road disputed by locals. |
No Image |
PK-55, Mansehra | |||||||||||||||||||
885 (OG) |
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.55 | 87.187 | 35 | 32.76875 | 32.76875 | 19.021 | 106.208 | 62.363 | 66% |
58% May - 2020 |
125.43 mtr -100 m bridge completed. Approach in progress. Right Approach road disputed by locals.
Cannot be completed (Court Stay) |
No Image |
PK-55, Mansehra | |||||||||||||||||||
885 (OG) |
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.55 | 87.187 | 35 | 32.76875 | 32.76875 | 16.347 | 103.534 | 62.363 | 66% |
56% April - 2020 |
125.43 mtr -100 m bridge completed. Approach in progress. Right Approach road disputed by locals.
Cannot be completed (Court Stay) |
No Image |
PK-55, Mansehra | |||||||||||||||||||
885 (OG) |
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.55 | 87.187 | 35 | 32.76875 | 32.76875 | 16.347 | 103.534 | 62.363 | 66% |
56% March - 2020 |
125.43 mtr -100 m bridge completed. Approach in progress. Right Approach road disputed by locals.
Cannot be completed (Court Stay) |
No Image |
PK-55, Mansehra | |||||||||||||||||||
885 (OG) |
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.55 | 87.187 | 35 | 32.76875 | 32.76875 | 16.347 | 103.534 | 62.363 | 66% |
56% February - 2020 |
125.43 mtr -100 m bridge completed. Approach in progress. Right Approach road disputed by locals.
Cannot be completed (Court Stay) |
No Image |
PK-55, Mansehra | |||||||||||||||||||
885 (OG) |
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.55 | 87.187 | 35 | 32.76875 | 32.76875 | 8.594886 | 95.781886 | 62.363 | 66% |
52% January - 2020 |
125.43 mtr -100 m bridge completed. Approach in progress. Right Approach road disputed by locals.
Cannot be completed (Court Stay) |
No Image |
PK-55, Mansehra | |||||||||||||||||||
885 (OG) |
195166-PPPs for 06 Type D Hospitals of Merged Areas through Health Foundation (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2264.454 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
885 (OG) |
195166-PPPs for 06 Type D Hospitals of Merged Areas through Health Foundation (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2264.454 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
885 (OG) |
195166-PPPs for 06 Type D Hospitals of Merged Areas through Health Foundation (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2264.454 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
885 (OG) |
195166-PPPs for 06 Type D Hospitals of Merged Areas through Health Foundation (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2264.454 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
885 (OG) |
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project". |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.318 | 18.525 | 5 | 5 | 2.5 | 0 | 18.525 | 35.793 | 40% |
31% September - 2018 |
PIU setup, staff deputed. Revised AA approved. |
No Image |
885 (OG) |
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project". |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.318 | 18.525 | 5 | 5 | 2.5 | 0 | 18.525 | 35.793 | 40% |
31% July - 2018 |
PIU setup, staff deputed. Revised AA approved. |
No Image |
Pages : 1 |