Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2018, November - 2019, December - 2018, December - 2019, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
883
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 20.25 30 28.0875 28.0875 27.499505 47.749505 285.053 15% 14%
December - 2019
8.725Km road - Earth work 6Km completed. Bridge - Work started.
No Image
Battagram
883
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 20.25 30 30 7.5 7.5 27.75 285.053 15% 8%
November - 2019
8.725Km road - Earth work 6Km completed. Bridge - Work started.
No Image
Battagram
883
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 20.25 30 30 7.5 7.5 27.75 285.053 15% 8%
October - 2019
8.725Km road - Earth work 6Km completed. Bridge - Work started.
No Image
Battagram
883
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 20.25 30 30 7.5 7.5 27.75 285.053 15% 8%
September - 2019
8.725Km road - Earth work 6Km completed. Bridge - Work started.
No Image
Battagram
883
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 20.25 30 30 7.5 7.5 27.75 285.053 15% 8%
August - 2019
8.725Km road - Earth work 6Km completed. Bridge - Work started.
No Image
Battagram
883
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 20.25 30 28.0875 28.0875 28.087 48.337 285.053 15% 14%
May - 2020
8.725Km road - Earth work 6Km completed. Bridge - Work started.
No Image
Battagram
883
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 20.25 30 28.0875 28.0875 28.087 48.337 285.053 15% 14%
April - 2020
8.725Km road - Earth work 6Km completed. Bridge - Work started.
No Image
Battagram
883
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 20.25 30 28.0875 28.0875 28.087 48.337 285.053 15% 14%
March - 2020
8.725Km road - Earth work 6Km completed. Bridge - Work started.
No Image
Battagram
883
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 20.25 30 28.0875 28.0875 28.087 48.337 285.053 15% 14%
February - 2020
8.725Km road - Earth work 6Km completed. Bridge - Work started.
No Image
Battagram
883
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 20.25 30 28.0875 28.0875 28.087 48.337 285.053 15% 14%
January - 2020
8.725Km road - Earth work 6Km completed. Bridge - Work started.
No Image
Battagram
883
(OG)
150798-Construction and Blacktopping of roads in PK-77 District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 200 29.439 10 10 10 10 39.439 160.561 20% 20%
December - 2018
Length 11.3 Km - 8 units in progress.
No Image
1) Charkot to Ghazi Kot 2.30 Km (improvement/BT)
2) Charkot to Mangal Thana 1 Km (improvement/BT)
3) Swawai to Batkanai 1 Km ( improvement/BT)
4) Darahind road 1 Km (improvement/BT)
5) Dandikot road 1 Km (improvement/BT)
6) Badir to Ashari 1 Km (improvement/BT)
7) Khanano Dheri to Banda Tangai road 2 Km (improvement/widening and extension)
8) Banda Tangai to Nagrai raod 2 Km (improvement/widening and extension)
883
(OG)
150798-Construction and Blacktopping of roads in PK-77 District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 200 29.439 10 10 10 10 39.439 160.561 20% 20%
November - 2018
Length 11.3 Km - 8 units in progress.
No Image
1) Charkot to Ghazi Kot 2.30 Km (improvement/BT)
2) Charkot to Mangal Thana 1 Km (improvement/BT)
3) Swawai to Batkanai 1 Km ( improvement/BT)
4) Darahind road 1 Km (improvement/BT)
5) Dandikot road 1 Km (improvement/BT)
6) Badir to Ashari 1 Km (improvement/BT)
7) Khanano Dheri to Banda Tangai road 2 Km (improvement/widening and extension)
8) Banda Tangai to Nagrai raod 2 Km (improvement/widening and extension)
883
(OG)
150798-Construction and Blacktopping of roads in PK-77 District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 200 29.439 10 10 10 10 39.439 160.561 20% 20%
November - 2018
Length 11.3 Km - 8 units in progress.
No Image
1) Charkot to Ghazi Kot 2.30 Km (improvement/BT)
2) Charkot to Mangal Thana 1 Km (improvement/BT)
3) Swawai to Batkanai 1 Km ( improvement/BT)
4) Darahind road 1 Km (improvement/BT)
5) Dandikot road 1 Km (improvement/BT)
6) Badir to Ashari 1 Km (improvement/BT)
7) Khanano Dheri to Banda Tangai road 2 Km (improvement/widening and extension)
8) Banda Tangai to Nagrai raod 2 Km (improvement/widening and extension)
883
(OG)
150798-Construction and Blacktopping of roads in PK-77 District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 200 29.439 10 10 10 10 39.439 160.561 20% 20%
April - 2019
Length 11.3 Km - 8 units in progress. Liability Rs.40 m.
No Image
1) Charkot to Ghazi Kot 2.30 Km (improvement/BT)
2) Charkot to Mangal Thana 1 Km (improvement/BT)
3) Swawai to Batkanai 1 Km ( improvement/BT)
4) Darahind road 1 Km (improvement/BT)
5) Dandikot road 1 Km (improvement/BT)
6) Badir to Ashari 1 Km (improvement/BT)
7) Khanano Dheri to Banda Tangai road 2 Km (improvement/widening and extension)
8) Banda Tangai to Nagrai raod 2 Km (improvement/widening and extension)
883
(OG)
150798-Construction and Blacktopping of roads in PK-77 District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 200 29.439 10 10 10 10 39.439 160.561 20% 20%
March - 2019
Length 11.3 Km - 8 units in progress. Liability Rs.40 m.
No Image
1) Charkot to Ghazi Kot 2.30 Km (improvement/BT)
2) Charkot to Mangal Thana 1 Km (improvement/BT)
3) Swawai to Batkanai 1 Km ( improvement/BT)
4) Darahind road 1 Km (improvement/BT)
5) Dandikot road 1 Km (improvement/BT)
6) Badir to Ashari 1 Km (improvement/BT)
7) Khanano Dheri to Banda Tangai road 2 Km (improvement/widening and extension)
8) Banda Tangai to Nagrai raod 2 Km (improvement/widening and extension)
883
(OG)
150798-Construction and Blacktopping of roads in PK-77 District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 200 29.439 10 10 10 10 39.439 160.561 20% 20%
March - 2019
Length 11.3 Km - 8 units in progress. Liability Rs.40 m.
No Image
1) Charkot to Ghazi Kot 2.30 Km (improvement/BT)
2) Charkot to Mangal Thana 1 Km (improvement/BT)
3) Swawai to Batkanai 1 Km ( improvement/BT)
4) Darahind road 1 Km (improvement/BT)
5) Dandikot road 1 Km (improvement/BT)
6) Badir to Ashari 1 Km (improvement/BT)
7) Khanano Dheri to Banda Tangai road 2 Km (improvement/widening and extension)
8) Banda Tangai to Nagrai raod 2 Km (improvement/widening and extension)
883
(OG)
150798-Construction and Blacktopping of roads in PK-77 District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 200 29.439 10 10 10 10 39.439 160.561 20% 20%
February - 2019
Length 11.3 Km - 8 units in progress. Liability 40 M
No Image
1) Charkot to Ghazi Kot 2.30 Km (improvement/BT)
2) Charkot to Mangal Thana 1 Km (improvement/BT)
3) Swawai to Batkanai 1 Km ( improvement/BT)
4) Darahind road 1 Km (improvement/BT)
5) Dandikot road 1 Km (improvement/BT)
6) Badir to Ashari 1 Km (improvement/BT)
7) Khanano Dheri to Banda Tangai road 2 Km (improvement/widening and extension)
8) Banda Tangai to Nagrai raod 2 Km (improvement/widening and extension)
883
(OG)
150798-Construction and Blacktopping of roads in PK-77 District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 200 29.439 10 10 10 10 39.439 160.561 20% 20%
January - 2019
Length 11.3 Km - 8 units in progress.
No Image
1) Charkot to Ghazi Kot 2.30 Km (improvement/BT)
2) Charkot to Mangal Thana 1 Km (improvement/BT)
3) Swawai to Batkanai 1 Km ( improvement/BT)
4) Darahind road 1 Km (improvement/BT)
5) Dandikot road 1 Km (improvement/BT)
6) Badir to Ashari 1 Km (improvement/BT)
7) Khanano Dheri to Banda Tangai road 2 Km (improvement/widening and extension)
8) Banda Tangai to Nagrai raod 2 Km (improvement/widening and extension)
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
December - 2020
No Image
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
December - 2020
No Image
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
October - 2020
No Image
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
September - 2020
No Image
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
August - 2020
No Image
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
July - 2020
No Image
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
May - 2021
No Image
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
April - 2021
No Image
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
March - 2021
No Image
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
February - 2021
No Image
883
(OG)
195162-Provision of Doctors at Health Facilties in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1770 0 0 0 0 0 0 0 - -
January - 2021
No Image
883
(OG)
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 2796.766 1391.88 50 50 25 25 1416.88 1354.886 52% 51%
September - 2018
Pack-1 (7.3 Km) - earth work in progress, culverts and bridges in progress. Pack-2 (11.05 Km) - earth work, bridge and culverts in progress. Pack-3 (10 Km) - hillside cutting 90% completed. Pack-4 (8.55 Km) - earth work and culverts in progress. Pack-5 (10 Km) - earth work in progress. Pack-6 (12.553 Km) - earth work in progress. Km-52 to 55 - clearing, grubbing and NGC in progress. Bridge at Km-52+600, 54+360 and 64+100 - confirmatory bore in progress.
No Image
883
(OG)
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 2796.766 851.88 50 50 25 0 851.88 1894.886 32% 30%
July - 2018
Pack-1 (7.3 Km) - earth work in progress, culverts and bridges in progress. Pack-2 (11.05 Km) - earth work, bridge and culverts in progress. Pack-3 (10 Km) - hillside cutting 90% completed. Pack-4 (8.55 Km) - earth work and culverts in progress. Pack-5 (10 Km) - earth work in progress. Pack-6 (12.553 Km) - earth work in progress. Km-52 to 55 - clearing, grubbing and NGC in progress. Bridge at Km-52+600, 54+360 and 64+100 - confirmatory bore in progress.
No Image