Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2020, July - 2018, August - 2020, August - 2019, September - 2020, September - 2018, September - 2019, October - 2020, October - 2019, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
879
(OG)
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 300 161.151 10 9.75 9.75 7.5 168.651 128.849 57% 56%
December - 2018
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress.
No Image
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner
879
(OG)
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 300 161.151 10 9.75 7.5 7.5 168.651 128.849 57% 56%
November - 2018
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress.
No Image
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner
879
(OG)
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 300 161.151 10 9.75 7.5 7.5 168.651 128.849 57% 56%
November - 2018
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress.
No Image
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner
879
(OG)
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 300 161.151 10 12.25 12.25 9.75 170.901 128.849 57% 57%
April - 2019
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. Liability Rs.10 m.
No Image
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner
879
(OG)
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 300 161.151 10 9.75 9.75 9.75 170.901 128.849 57% 57%
March - 2019
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. Liability Rs.10 m.
No Image
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner
879
(OG)
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 300 161.151 10 9.75 9.75 9.75 170.901 128.849 57% 57%
March - 2019
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. Liability Rs.10 m.
No Image
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner
879
(OG)
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 300 161.151 10 9.75 9.75 9.75 170.901 128.849 57% 57%
February - 2019
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. Liability 10 M
No Image
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner
879
(OG)
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 300 161.151 10 9.75 9.75 7.5 168.651 128.849 57% 56%
January - 2019
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress.
No Image
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner
879
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 129.568 40 38.725 38.725 15.2 144.768 30.432 85% 72%
December - 2019
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
879
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 129.568 40 40 10 10 139.568 30.432 85% 70%
November - 2019
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
879
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 129.568 40 40 10 10 139.568 30.432 85% 70%
October - 2019
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
879
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 129.568 40 40 10 10 139.568 30.432 85% 70%
September - 2019
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
879
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 129.568 40 40 10 0 129.568 30.432 85% 65%
August - 2019
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
879
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 129.568 40 51.868 51.868 20.781 150.349 30.432 85% 75%
May - 2020
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. P-II
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
879
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 129.568 40 38.725 38.725 18.423 147.991 30.432 85% 74%
April - 2020
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. P-II
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
879
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 129.568 40 38.725 38.725 18.423 147.991 30.432 85% 74%
March - 2020
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. P-II
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
879
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 129.568 40 38.725 38.725 18.423 147.991 30.432 85% 74%
February - 2020
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. P-II
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
879
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 129.568 40 38.725 38.725 15.2 144.768 30.432 85% 72%
January - 2020
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. P-II
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
December - 2020
No Image
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
December - 2020
No Image
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
October - 2020
No Image
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
September - 2020
No Image
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
August - 2020
No Image
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
July - 2020
No Image
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
May - 2021
No Image
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
April - 2021
No Image
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
March - 2021
No Image
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
February - 2021
No Image
879
(OG)
195155-Roll out Hospital Waste Management Regime at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 582.46 0 0 0 0 0 0 0 - -
January - 2021
No Image
879
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 668.658 189.346 0.001 0.0005 0.0005 0.0005 189.3465 479.311 28% 28%
September - 2018
Conusltancy services for feasilbility study and design and framing PC-I.
No Image
879
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 668.658 189.346 0.001 0.001 0.0005 0 189.346 479.311 28% 28%
July - 2018
Conusltancy services for feasilbility study and design and framing PC-I.
No Image
Pages : 1