Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
879 (OG) |
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 161.151 | 10 | 9.75 | 9.75 | 7.5 | 168.651 | 128.849 | 57% |
56% December - 2018 |
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. |
No Image |
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner | |||||||||||||||||||
879 (OG) |
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 161.151 | 10 | 9.75 | 7.5 | 7.5 | 168.651 | 128.849 | 57% |
56% November - 2018 |
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. |
No Image |
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner | |||||||||||||||||||
879 (OG) |
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 161.151 | 10 | 9.75 | 7.5 | 7.5 | 168.651 | 128.849 | 57% |
56% November - 2018 |
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. |
No Image |
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner | |||||||||||||||||||
879 (OG) |
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 161.151 | 10 | 12.25 | 12.25 | 9.75 | 170.901 | 128.849 | 57% |
57% April - 2019 |
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. Liability Rs.10 m. |
No Image |
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner | |||||||||||||||||||
879 (OG) |
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 161.151 | 10 | 9.75 | 9.75 | 9.75 | 170.901 | 128.849 | 57% |
57% March - 2019 |
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. Liability Rs.10 m. |
No Image |
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner | |||||||||||||||||||
879 (OG) |
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 161.151 | 10 | 9.75 | 9.75 | 9.75 | 170.901 | 128.849 | 57% |
57% March - 2019 |
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. Liability Rs.10 m. |
No Image |
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner | |||||||||||||||||||
879 (OG) |
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 161.151 | 10 | 9.75 | 9.75 | 9.75 | 170.901 | 128.849 | 57% |
57% February - 2019 |
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress.
Liability 10 M |
No Image |
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner | |||||||||||||||||||
879 (OG) |
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 161.151 | 10 | 9.75 | 9.75 | 7.5 | 168.651 | 128.849 | 57% |
56% January - 2019 |
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress. |
No Image |
Package-1 (Km-1 to 12) PK-78 Buner
Package-2 (Km-13 to 20) PK-78 Buner | |||||||||||||||||||
879 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.568 | 40 | 38.725 | 38.725 | 15.2 | 144.768 | 30.432 | 85% |
72% December - 2019 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
879 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.568 | 40 | 40 | 10 | 10 | 139.568 | 30.432 | 85% |
70% November - 2019 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
879 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.568 | 40 | 40 | 10 | 10 | 139.568 | 30.432 | 85% |
70% October - 2019 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
879 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.568 | 40 | 40 | 10 | 10 | 139.568 | 30.432 | 85% |
70% September - 2019 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
879 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.568 | 40 | 40 | 10 | 0 | 129.568 | 30.432 | 85% |
65% August - 2019 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
879 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.568 | 40 | 51.868 | 51.868 | 20.781 | 150.349 | 30.432 | 85% |
75% May - 2020 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
P-II |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
879 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.568 | 40 | 38.725 | 38.725 | 18.423 | 147.991 | 30.432 | 85% |
74% April - 2020 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
P-II |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
879 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.568 | 40 | 38.725 | 38.725 | 18.423 | 147.991 | 30.432 | 85% |
74% March - 2020 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
P-II |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
879 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.568 | 40 | 38.725 | 38.725 | 18.423 | 147.991 | 30.432 | 85% |
74% February - 2020 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
P-II |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
879 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridge and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.568 | 40 | 38.725 | 38.725 | 15.2 | 144.768 | 30.432 | 85% |
72% January - 2020 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
P-II |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
879 (OG) |
195155-Roll out Hospital Waste Management Regime at DHQs (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 582.46 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
879 (OG) |
20675-F/S and Design of Projects of Various Roads. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.658 | 189.346 | 0.001 | 0.0005 | 0.0005 | 0.0005 | 189.3465 | 479.311 | 28% |
28% September - 2018 |
Conusltancy services for feasilbility study and design and framing PC-I. |
No Image |
879 (OG) |
20675-F/S and Design of Projects of Various Roads. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.658 | 189.346 | 0.001 | 0.001 | 0.0005 | 0 | 189.346 | 479.311 | 28% |
28% July - 2018 |
Conusltancy services for feasilbility study and design and framing PC-I. |
No Image |
Pages : 1 |