Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
878 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 59.6 | 10 | 10 | 10 | 4.5 | 64.1 | 30.4 | 70% |
64% December - 2019 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
878 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 59.6 | 10 | 10 | 2.5 | 2.5 | 62.1 | 30.4 | 70% |
62% November - 2019 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
878 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 59.6 | 10 | 10 | 2.5 | 2.5 | 62.1 | 30.4 | 70% |
62% October - 2019 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
878 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 59.6 | 10 | 10 | 2.5 | 2.5 | 62.1 | 30.4 | 70% |
62% September - 2019 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
878 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 59.6 | 10 | 10 | 2.5 | 0 | 59.6 | 30.4 | 70% |
60% August - 2019 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
878 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 59.6 | 10 | 10 | 10 | 4.5 | 64.1 | 30.4 | 70% |
64% May - 2020 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
878 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 59.6 | 10 | 10 | 10 | 4.5 | 64.1 | 30.4 | 70% |
64% April - 2020 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
878 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 59.6 | 10 | 10 | 10 | 4.5 | 64.1 | 30.4 | 70% |
64% March - 2020 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
878 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 59.6 | 10 | 10 | 10 | 4.5 | 64.1 | 30.4 | 70% |
64% February - 2020 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
878 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 59.6 | 10 | 10 | 10 | 4.5 | 64.1 | 30.4 | 70% |
64% January - 2020 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
878 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 0 | 10 | 9.5 | 4.5005 | 0 | 0 | 189.917 | 5% |
- December - 2018 |
Length 8 Km - work started. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
878 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 0 | 10 | 9.5 | 4.501 | 0 | 0 | 189.917 | 5% |
- November - 2018 |
length 8 km-Work started. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
878 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 0 | 10 | 9.5 | 4.501 | 0 | 0 | 189.917 | 5% |
- November - 2018 |
length 8 km-Work started. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
878 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 0 | 10 | 14.413 | 14.413 | 14.413 | 14.413 | 189.917 | 5% |
7% April - 2019 |
Length 8 Km - work in progress. Cutting in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
878 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 0 | 10 | 9.5 | 4.5 | 4.5 | 4.5 | 189.917 | 5% |
2% March - 2019 |
Length 8 Km - work in progress. Cutting in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
878 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 0 | 10 | 9.5 | 4.5 | 4.5 | 4.5 | 189.917 | 5% |
2% March - 2019 |
Length 8 Km - work in progress. Cutting in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
878 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 0 | 10 | 9.5 | 4.5005 | 0 | 0 | 189.917 | 5% |
- February - 2019 |
Length 8 Km - work in progress.
Cutting in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
878 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 0 | 10 | 9.5 | 4.5005 | 0 | 0 | 189.917 | 5% |
- January - 2019 |
Length 8 Km - work started. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
- December - 2020 |
No Image | |
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
- December - 2020 |
No Image | |
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
- October - 2020 |
No Image | |
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
- September - 2020 |
No Image | |
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
- August - 2020 |
No Image | |
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
July - 2020 |
No Image | |
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
- May - 2021 |
No Image | |
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
- April - 2021 |
No Image | |
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
- March - 2021 |
No Image | |
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
- February - 2021 |
No Image | |
878 (OG) |
195151-Provision of standard Medical equipment/ non-medical equipment at Secondary hospitals (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1966.514 | 817.7 | 0 | 0 | 0 | 0 | 817.7 | 0 | - |
- January - 2021 |
No Image | |
878 (OG) |
20665-Construction / Supervision of new Road Works. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1104.58 | 1051.899 | 0.001 | 0.0005 | 0.0005 | 0.0005 | 1051.8995 | 52.68 | 95% |
95% September - 2018 |
Construction supervision of new road works. |
No Image |
878 (OG) |
20665-Construction / Supervision of new Road Works. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1104.58 | 1051.899 | 0.001 | 0.001 | 0.0005 | 0 | 1051.899 | 52.68 | 95% |
95% July - 2018 |
Construction supervision of new road works. |
No Image |
Pages : 1 |