Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
871 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 689.999 | 293.15 | 5 | 5 | 2.5 | 2.5 | 295.65 | 391.849 | 43% |
43% September - 2018 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. PC-II for Rs.25.250 m approved in DDWP-I on 07/05/2018. |
No Image |
Package-1
Package-2 | |||||||||||||||||||
871 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 689.999 | 218.15 | 5 | 5 | 2.5 | 0 | 218.15 | 466.849 | 32% |
32% July - 2018 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. PC-II for Rs.25.250 m approved in DDWP-I on 07/05/2018. |
No Image |
Package-1
Package-2 | |||||||||||||||||||
871 (OG) |
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.617 | 20.617 | 10 | 10 | 10 | 6.960268 | 27.577268 | 0 | 100% |
90% December - 2019 |
Single Span Bridge -abutments in progress. |
No Image |
PK-93, Dir Upper | |||||||||||||||||||
871 (OG) |
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.617 | 20.617 | 10 | 10 | 2.5 | 2.5 | 23.117 | 0 | 100% |
76% November - 2019 |
Single Span Bridge -abutments in progress. |
No Image |
PK-93, Dir Upper | |||||||||||||||||||
871 (OG) |
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.617 | 20.617 | 10 | 10 | 2.5 | 2.5 | 23.117 | 0 | 100% |
76% October - 2019 |
Single Span Bridge -abutments in progress. |
No Image |
PK-93, Dir Upper | |||||||||||||||||||
871 (OG) |
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.617 | 20.617 | 10 | 10 | 2.5 | 2.5 | 23.117 | 0 | 100% |
76% September - 2019 |
Single Span Bridge -abutments in progress. |
No Image |
PK-93, Dir Upper | |||||||||||||||||||
871 (OG) |
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.617 | 20.617 | 10 | 10 | 2.5 | 0 | 20.617 | 0 | 100% |
67% August - 2019 |
Single Span Bridge -abutments in progress. |
No Image |
PK-93, Dir Upper | |||||||||||||||||||
871 (OG) |
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.617 | 20.617 | 10 | 7.5 | 7.53 | 5.985 | 26.602 | 0 | 100% |
87% May - 2020 |
Single Span Bridge -abutments completed.
R/Wall in progress. |
No Image |
PK-93, Dir Upper | |||||||||||||||||||
871 (OG) |
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.617 | 20.617 | 10 | 7.5 | 7.53 | 5.985 | 26.602 | 0 | 100% |
87% April - 2020 |
Single Span Bridge -abutments completed.
R/Wall in progress. |
No Image |
PK-93, Dir Upper | |||||||||||||||||||
871 (OG) |
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.617 | 20.617 | 10 | 7.5 | 7.53 | 5.985 | 26.602 | 0 | 100% |
87% March - 2020 |
Single Span Bridge -abutments completed.
R/Wall in progress. |
No Image |
PK-93, Dir Upper | |||||||||||||||||||
871 (OG) |
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.617 | 20.617 | 10 | 7.5 | 7.53 | 5.985 | 26.602 | 0 | 100% |
87% February - 2020 |
Single Span Bridge -abutments completed.
R/Wall in progress. |
No Image |
PK-93, Dir Upper | |||||||||||||||||||
871 (OG) |
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.617 | 20.617 | 10 | 10 | 10 | 6.960268 | 27.577268 | 0 | 100% |
90% January - 2020 |
Single Span Bridge -abutments in progress.
Will be complted |
No Image |
PK-93, Dir Upper | |||||||||||||||||||
871 (OG) |
160623-F/S, Design & Construction of over head / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1975.619 | 240.904 | 255 | 255 | 255 | 254.354 | 495.258 | 1479.715 | 25% |
25% December - 2018 |
1) Mardan Charsadda flyover - 35/84 pile completed 2) Katlang Chowk flyover and Bypass road - Dropped and round about proposed - land acquisition in progress 3) Jawad chowk flyover - 39/39 girders completed piles 63/69 completed 6/11 pile cap completed 4/11 pier shaft completed 4) Bakshali Bridge - pile completed, pile cap 2/2 completed 5) Bhai Khan Bridge - piles, girders completed 6) Gujjar Abad Bridge - piles and griders completed, pier shaft in progress 7) Ghareeb Abad Bridge - piles and girders completed and pier shaft in progress. |
No Image |
1) Mardan - Charsadda Chowk flyover
2) Katlang Chowk flyover and bypass road
3) Jawad Chowk flyover
4) Bakhshali bridge
5) Bhai Khan bridge
6) Gujrat bridge
7) Gharib Abad bridge | |||||||||||||||||||
871 (OG) |
160623-F/S, Design & Construction of over head / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1975.619 | 240.904 | 255 | 255 | 255 | 252.879 | 493.783 | 1479.715 | 25% |
25% November - 2018 |
1) Mardan Charsadda flyover - 35/84 pile completed 2) Katlang Chowk flyover and Bypass road - Dropped and round about proposed - land acquisition in progress 3) Jawad chowk flyover - 39/39 girders completed piles 63/69 completed 6/11 pile cap completed 4/11 pier shaft completed 4) Bakshali Bridge - pile completed, pile cap 2/2 completed 5) Bhai Khan Bridge - piles, girders completed 6) Gujjar Abad Bridge - piles and griders completed, pier shaft in progress 7) Ghareeb Abad Bridge - piles and girders completed and pier shaft in progress. |
No Image |
1) Mardan - Charsadda Chowk flyover
2) Katlang Chowk flyover and bypass road
3) Jawad Chowk flyover
4) Bakhshali bridge
5) Bhai Khan bridge
6) Gujrat bridge
7) Gharib Abad bridge | |||||||||||||||||||
871 (OG) |
160623-F/S, Design & Construction of over head / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1975.619 | 240.904 | 255 | 255 | 255 | 252.879 | 493.783 | 1479.715 | 25% |
25% November - 2018 |
1) Mardan Charsadda flyover - 35/84 pile completed 2) Katlang Chowk flyover and Bypass road - Dropped and round about proposed - land acquisition in progress 3) Jawad chowk flyover - 39/39 girders completed piles 63/69 completed 6/11 pile cap completed 4/11 pier shaft completed 4) Bakshali Bridge - pile completed, pile cap 2/2 completed 5) Bhai Khan Bridge - piles, girders completed 6) Gujjar Abad Bridge - piles and griders completed, pier shaft in progress 7) Ghareeb Abad Bridge - piles and girders completed and pier shaft in progress. |
No Image |
1) Mardan - Charsadda Chowk flyover
2) Katlang Chowk flyover and bypass road
3) Jawad Chowk flyover
4) Bakhshali bridge
5) Bhai Khan bridge
6) Gujrat bridge
7) Gharib Abad bridge | |||||||||||||||||||
871 (OG) |
160623-F/S, Design & Construction of over head / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1975.619 | 240.901 | 255 | 455 | 455 | 395.167 | 636.068 | 1479.718 | 25% |
32% April - 2019 |
1) Mardan Charsadda flyover - 35/84 pile completed 2) Katlang Chowk flyover and Bypass road - Dropped and round about proposed - land acquisition in progress 3) Jawad chowk flyover - 39/39 girders completed piles 63/69 completed 6/11 pile cap completed 4/11 pier shaft completed 4) Bakshali Bridge - pile completed, pile cap 2/2 completed 5) Bhai Khan Bridge - piles, girders completed 6) Gujjar Abad Bridge - piles and griders completed, pier shaft in progress 7) Ghareeb Abad Bridge - piles and girders completed and pier shaft in progress. |
No Image |
1) Mardan - Charsadda Chowk flyover
2) Katlang Chowk flyover and bypass road
3) Jawad Chowk flyover
4) Bakhshali bridge
5) Bhai Khan bridge
6) Gujrat bridge
7) Gharib Abad bridge | |||||||||||||||||||
871 (OG) |
160623-F/S, Design & Construction of over head / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1975.619 | 240.901 | 255 | 455 | 455 | 381.111 | 622.012 | 1479.718 | 25% |
31% March - 2019 |
1) Mardan Charsadda flyover - 35/84 pile completed 2) Katlang Chowk flyover and Bypass road - Dropped and round about proposed - land acquisition in progress 3) Jawad chowk flyover - 39/39 girders completed piles 63/69 completed 6/11 pile cap completed 4/11 pier shaft completed 4) Bakshali Bridge - pile completed, pile cap 2/2 completed 5) Bhai Khan Bridge - piles, girders completed 6) Gujjar Abad Bridge - piles and griders completed, pier shaft in progress 7) Ghareeb Abad Bridge - piles and girders completed and pier shaft in progress. |
No Image |
1) Mardan - Charsadda Chowk flyover
2) Katlang Chowk flyover and bypass road
3) Jawad Chowk flyover
4) Bakhshali bridge
5) Bhai Khan bridge
6) Gujrat bridge
7) Gharib Abad bridge | |||||||||||||||||||
871 (OG) |
160623-F/S, Design & Construction of over head / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1975.619 | 240.901 | 255 | 455 | 455 | 381.111 | 622.012 | 1479.718 | 25% |
31% March - 2019 |
1) Mardan Charsadda flyover - 35/84 pile completed 2) Katlang Chowk flyover and Bypass road - Dropped and round about proposed - land acquisition in progress 3) Jawad chowk flyover - 39/39 girders completed piles 63/69 completed 6/11 pile cap completed 4/11 pier shaft completed 4) Bakshali Bridge - pile completed, pile cap 2/2 completed 5) Bhai Khan Bridge - piles, girders completed 6) Gujjar Abad Bridge - piles and griders completed, pier shaft in progress 7) Ghareeb Abad Bridge - piles and girders completed and pier shaft in progress. |
No Image |
1) Mardan - Charsadda Chowk flyover
2) Katlang Chowk flyover and bypass road
3) Jawad Chowk flyover
4) Bakhshali bridge
5) Bhai Khan bridge
6) Gujrat bridge
7) Gharib Abad bridge | |||||||||||||||||||
871 (OG) |
160623-F/S, Design & Construction of over head / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1975.619 | 240.901 | 255 | 455 | 455 | 372.98 | 613.881 | 1479.718 | 25% |
31% February - 2019 |
1) Mardan Charsadda flyover - 35/84 pile completed 2) Katlang Chowk flyover and Bypass road - Dropped and round about proposed - land acquisition in progress 3) Jawad chowk flyover - 39/39 girders completed piles 63/69 completed 6/11 pile cap completed 4/11 pier shaft completed 4) Bakshali Bridge - pile completed, pile cap 2/2 completed 5) Bhai Khan Bridge - piles, girders completed 6) Gujjar Abad Bridge - piles and griders completed, pier shaft in progress 7) Ghareeb Abad Bridge - piles and girders completed and pier shaft in progress. |
No Image |
1) Mardan - Charsadda Chowk flyover
2) Katlang Chowk flyover and bypass road
3) Jawad Chowk flyover
4) Bakhshali bridge
5) Bhai Khan bridge
6) Gujrat bridge
7) Gharib Abad bridge | |||||||||||||||||||
871 (OG) |
160623-F/S, Design & Construction of over head / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1975.619 | 240.901 | 255 | 255 | 255 | 254.354 | 495.255 | 1479.718 | 25% |
25% January - 2019 |
1) Mardan Charsadda flyover - 35/84 pile completed 2) Katlang Chowk flyover and Bypass road - Dropped and round about proposed - land acquisition in progress 3) Jawad chowk flyover - 39/39 girders completed piles 63/69 completed 6/11 pile cap completed 4/11 pier shaft completed 4) Bakshali Bridge - pile completed, pile cap 2/2 completed 5) Bhai Khan Bridge - piles, girders completed 6) Gujjar Abad Bridge - piles and griders completed, pier shaft in progress 7) Ghareeb Abad Bridge - piles and girders completed and pier shaft in progress. |
No Image |
1) Mardan - Charsadda Chowk flyover
2) Katlang Chowk flyover and bypass road
3) Jawad Chowk flyover
4) Bakhshali bridge
5) Bhai Khan bridge
6) Gujrat bridge
7) Gharib Abad bridge | |||||||||||||||||||
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
- December - 2020 |
No Image | |
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
- December - 2020 |
No Image | |
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
- October - 2020 |
No Image | |
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
- September - 2020 |
No Image | |
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
- August - 2020 |
No Image | |
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
July - 2020 |
No Image | |
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
- May - 2021 |
No Image | |
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
- April - 2021 |
No Image | |
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
- March - 2021 |
No Image | |
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
- February - 2021 |
No Image | |
871 (OG) |
191567-990011 - T.B. Control Programme in FATA. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 333.577 | 291.567 | 0 | 0 | 0 | 0 | 291.567 | 0 | - |
- January - 2021 |
No Image | |